Sub topic 6
Reading your calendar to find real capacity
This chapter assumes you already have a weekly planning routine with a review step and a short list of outcomes. It also assumes you can read your calendar and keep a task list. The question here is how many hours you can plan against before you pick tasks.
Why calendar hours are not capacity
A 40-hour contract does not give you 40 hours of planned work. Meetings, admin, context switches and interruptions take a share of every day. If you plan against 40 hours, the plan is over-full before Monday starts.
Capacity is the number of hours you can reasonably commit to planned work this week. You get it by starting with working hours and removing what is already spoken for. This number is the limit that estimates in the next chapter are checked against.
Two mistakes cause most bad capacity numbers:
- Counting working hours as focus hours.
- Using last week's calendar or a typical week instead of the actual week ahead.
The capacity calculation
The calculation has four steps.
- Write down your working hours for the week. Subtract days off, public holidays and known partial days.
- Add up fixed commitments: meetings, appointments, recurring rituals and travel.
- Subtract fixed commitments from working hours. The result is your focus hours.
- Reserve a share of the focus hours as a buffer. What remains is your plannable hours.
The buffer is covered fully in a later chapter. A starting value of 20% is common. Adjust it from your retrospectives.
def plannable_hours(working_hours, fixed_hours, buffer_ratio=0.2):
"""Hours left for planned work after meetings and a buffer."""
focus = max(working_hours - fixed_hours, 0)
return focus * (1 - buffer_ratio)
capacity = plannable_hours(working_hours=40, fixed_hours=12)
print(capacity) # 22.4With 40 working hours and 12 fixed hours, you have 28 focus hours. Reserving 20% leaves 22.4 plannable hours. Only about 56% of the original 40 hours is available for the outcomes you chose.
The max(..., 0) guard handles an overloaded week. If fixed commitments exceed working hours, focus time is zero, not negative. That result is itself useful. It tells you to renegotiate meetings before you plan anything.
Reading the calendar in a fixed order
Open the calendar for the coming week and go through it the same way each time. A fixed order prevents you from skipping the dull parts.
- Remove unavailable time. Mark days off, holidays, sick leave you know about, and early finishes.
- List hard-time events. These are meetings and appointments that cannot move, such as a client call or a medical visit.
- List soft-time events. These are recurring meetings you could skip, shorten or move, such as a status sync.
- Add travel and transitions. Commutes, room changes and the time to prepare for or recover from a meeting count as well.
- Add recurring routines. Email triage, standups and support rotations take time even when they are not on the calendar.
- Look at the shape of each day, not only the total.
The sixth step matters because hours are not interchangeable. Four free hours split into eight 30-minute gaps are worth much less than one four-hour block.
Focus hours versus fragmented hours
Deep work, such as writing, design or debugging, needs an uninterrupted stretch. A common minimum is 90 minutes. Gaps shorter than that suit small tasks: replies, reviews and quick fixes.
For each day, sort free time into two types:
| Type | Typical length | Suits |
|---|---|---|
| Deep block | 90 minutes or more | Writing, analysis, design, complex coding |
| Fragment | Under 90 minutes | Email, approvals, short reviews, errands |
Count deep blocks separately from fragments. A week with 20 plannable hours, all in fragments, cannot hold a six-hour drafting task as one piece. You can still do it in smaller chunks, but expect more overhead each time you restart.
Worked example
Consider a week with these facts:
- Working hours are 40, but Friday afternoon is a public holiday, so 36.
- Recurring meetings total 8 hours.
- A client workshop on Wednesday takes 3 hours.
- Travel to the workshop adds 1 hour.
- Daily email and chat triage takes about 30 minutes, five days, so 2.5 hours. Take 2 hours because Friday is short.
Fixed hours are 8 + 3 + 1 + 2 = 14. Focus hours are 36 − 14 = 22. With a 20% buffer, plannable hours are 17.6.
def plannable_hours(working_hours, fixed_hours, buffer_ratio=0.2):
"""Hours left for planned work after meetings and a buffer."""
focus = max(working_hours - fixed_hours, 0)
return focus * (1 - buffer_ratio)
fixed = {
"recurring meetings": 8,
"client workshop": 3,
"travel": 1,
"email and chat triage": 2,
}
capacity = plannable_hours(working_hours=36, fixed_hours=sum(fixed.values()))
print(round(capacity, 1)) # 17.6Keeping the commitments in a dictionary makes the arithmetic visible. You can see which line to cut when the result is too small.
Checking the plan against capacity
Once you have a capacity figure, compare it with the estimated hours of your chosen work. The estimates come from the next chapter, but the check is a single comparison.
def check_plan(tasks, capacity):
"""tasks is a list of (name, estimated_hours) pairs."""
total = sum(hours for _, hours in tasks)
return total, total <= capacity
tasks = [("Draft proposal", 6), ("Review pull requests", 4), ("Prepare demo", 5)]
total, fits = check_plan(tasks, capacity=22.4)
print(total, fits) # 15 TrueThe three tasks total 15 hours against 22.4 plannable hours, so the plan fits with room to spare. If fits is False, do not squeeze. Remove or shrink an outcome, or free up capacity by cancelling a meeting.
Edge cases
Part-time or irregular schedules. Use the hours you actually work this week, not a standard contract. Planning from a 40-hour default when you work 24 inflates capacity by two thirds.
On-call or support rotations. Reserve a fixed block for interrupts. If you are on call, a 30% buffer is more realistic than 20%.
Meetings you have not seen yet. Calendars fill during the week. If your team adds meetings often, add a small allowance, for example 2 hours, for those that have not been scheduled.
Time zones. If meetings land outside your normal hours, count them against the week and subtract the matching time elsewhere. Otherwise you plan hours you will not have the energy to use.
Back-to-back days. A day with six hours of meetings has few usable focus hours left, whatever the arithmetic says. Treat it as a no-plan day and place nothing important there.
Pace changes. Energy varies through the day. If you do your best work before noon, count morning deep blocks as worth more than afternoon ones, and place demanding outcomes there.
Common errors
- Using the average week. The coming week is unusual in some way. Always read the real calendar.
- Ignoring invisible time. Email, chat and short conversations are real work. Include them as fixed hours.
- Skipping the buffer here. The buffer belongs in the capacity figure, not as an afterthought during scheduling.
- Tuning the number to fit the plan. If you shrink fixed hours until the plan fits, the plan is no more realistic than before.
- Counting hours you will not control. If a meeting is likely to overrun, count it at its likely length.
Calibrating over time
Your first capacity numbers will be rough. Improve them with data. At each retrospective, compare planned focus hours with the hours you actually spent on planned work. If the actual figure is consistently lower, either your fixed-hours list is missing something or your buffer is too small.
For example, if you plan 22 hours and regularly finish 16, your effective capacity is about 73% of plan. Apply that ratio as an extra reduction for the next few weeks, then look for the missing category of time.
Exercise
You work 40 hours this week, but you take Monday morning off (4 hours). Fixed commitments are 9 hours of meetings, 2 hours of travel and 3 hours of email triage. You use a 20% buffer. Your chosen work is estimated at 14 hours. How many hours can you plan, and does the plan fit?
Show answer
Working hours are 40 − 4 = 36. Fixed hours are 9 + 2 + 3 = 14. Focus hours are 36 − 14 = 22. Plannable hours are 22 × 0.8 = 17.6. The 14 estimated hours are below 17.6, so the plan fits with 3.6 hours to spare.
Exercise
Your calendar shows 16 free hours on Thursday and Friday, but they consist of sixteen separate 30-minute gaps between meetings. Why should you not count all 16 as focus hours for a six-hour writing task?
Show answer
The writing task needs long uninterrupted stretches, usually 90 minutes or more. Thirty-minute gaps are fragments. Restarting after each one costs time, and gaps next to meetings are partly lost to preparation and recovery. Use these hours for small tasks such as email and approvals, and find or create deep blocks elsewhere in the week.