What NPV measures
This chapter assumes you can lay out a cash flow timeline with consistent signs (outflows negative, inflows positive). It also assumes you know how a discount rate converts a future amount to today's value. Excel's NPV function is covered in the next chapter. Here the focus is on what the number means, so the arithmetic is done by hand.
The definition
Net present value (NPV) is the sum of all of a project's cash flows, each converted to its value at a single reference date, which is normally today (t=0). The conversion divides each cash flow by (1 + r) raised to the number of periods until it occurs:
NPV = CF0 + CF1 / (1 + r) + CF2 / (1 + r)^2 + ... + CFn / (1 + r)^n
Here r is the discount rate per period, and CFt is the net cash flow at the end of period t. The t=0 term has an exponent of zero, so it enters at face value.
NPV answers one question: after paying for the capital the project uses, at the rate r you chose, how much value does the project create or destroy, measured in today's money?
- A positive NPV means the project returns more than the discount rate demands.
- A zero NPV means it returns exactly the discount rate.
- A negative NPV means it returns less.
A worked example
A project costs 10,000 today and returns 3,000, 4,000, 4,000 and 3,000 at the ends of years 1 to 4. The discount rate is 8% per year.
| Year (t) | Cash flow | Discount factor 1/(1.08)^t | Present value |
|---|---|---|---|
| 0 | -10,000 | 1.0000 | -10,000.00 |
| 1 | 3,000 | 0.9259 | 2,777.78 |
| 2 | 4,000 | 0.8573 | 3,429.36 |
| 3 | 4,000 | 0.7938 | 3,175.33 |
| 4 | 3,000 | 0.7350 | 2,205.09 |
| Total | 1,587.55 |
The inflows are worth 11,587.55 in today's money against a 10,000 outlay, so NPV is about +1,587.55. The project earns its 8% cost of capital and creates about 1,588 of value on top.
You can reproduce this in Excel without the NPV function. Put the period numbers 0 to 4 in A4:A8 and the cash flows in B4:B8, with the rate in B1:
A1: Discount rate B1: 8%
A4: 0 B4: -10000
A5: 1 B5: 3000
A6: 2 B6: 4000
A7: 3 B7: 4000
A8: 4 B8: 3000
NPV by explicit discounting:
=SUMPRODUCT(B4:B8 / (1 + B1)^A4:A8)This formula applies the definition directly. It does not assume anything about where the first cash flow sits, because the period number is in the sheet. That makes it a useful independent check once you meet the NPV function.
NPV depends on the rate
NPV is not a property of the cash flows alone. It is a function of the cash flows and the discount rate. Evaluating the same project at three rates shows this:
| Discount rate | NPV |
|---|---|
| 0% | 4,000.00 |
| 8% | 1,587.55 |
| 20% | -960.65 |
At 0% there is no time value, and NPV is just the undiscounted sum of the cash flows. As the rate rises, later cash flows shrink more than earlier ones, so NPV falls. The project is attractive at 8% and unattractive at 20%. Somewhere in between, NPV crosses zero. At 15% it is about -21, so that crossing is just under 15%. That crossing point is the internal rate of return, which is the subject of a later chapter.
Plotting NPV against the rate gives an NPV profile. Because later cash flows are discounted more heavily as the rate rises, a project with a negative outflow first and inflows afterward has a downward-sloping profile.
Reading the result
Units and scale
NPV is in currency units at the reference date. It is an amount of value, not a percentage. This is the main difference from IRR and the reason NPV works well for comparing projects of different sizes: a project with NPV 50,000 adds more value than one with NPV 5,000, whatever their percentage returns.
Additivity
NPVs of independent projects at the same rate and reference date can be added. If you undertake projects A and B, the combined NPV is NPV(A) + NPV(B). IRRs have no such property.
The decision rule
For a single project with an upfront cost followed by inflows, accept it if NPV > 0 at the required rate. When choosing among mutually exclusive projects, pick the highest positive NPV. Later chapters compare this rule with IRR.
Assumptions behind the number
NPV is only as good as its inputs. These are the assumptions that most often go wrong in models:
- Timing convention. The formula treats each cash flow as occurring at the end of its period. Cash that actually arrives through the year is slightly more valuable than this implies. If a model needs mid-period timing, it must set the exponents explicitly (for example t - 0.5) rather than rely on the default.
- Rate and period must match. If cash flows are monthly, r must be a monthly rate. Using an annual 8% on monthly flows understates the discounting by a factor of twelve in the exponent. Convert deliberately, for example (1 + 8%)^(1/12) - 1 for the compound monthly equivalent.
- Nominal versus real. Discount nominal cash flows (inflation included) at a nominal rate, and real cash flows at a real rate. Mixing them biases NPV.
- Relevant cash flows only. Include incremental, after-tax cash flows. Sunk costs, which are already spent whatever you decide, do not belong in the timeline. Depreciation is not a cash flow, though the tax it shields is.
- A single constant rate. The formula applies one rate to every period. If the rate is expected to change over time, or if later cash flows are riskier than earlier ones, one flat rate is an approximation.
- Terminal value. Many models end with a lump sum for the value of the business after the last forecast year. That one number can dominate the NPV, so test how sensitive the result is to it.
Zero NPV is not break-even in the accounting sense
A project with NPV = 0 still earns the discount rate on all capital invested. It recovers the investment and pays investors their required return. So a zero NPV is acceptable, if unexciting. A project that merely returns its original outlay with no time value has a negative NPV at any positive rate.
Exercise
A project costs 1,000 today and returns 600 at the end of year 1 and 600 at the end of year 2. The discount rate is 10% per year. Calculate the NPV by discounting each cash flow, and state whether the project clears the 10% hurdle.
Show answer
PV of year 1 = 600 / 1.10 = 545.45. PV of year 2 = 600 / 1.21 = 495.87. Sum of inflows = 1,041.32. NPV = 1,041.32 - 1,000 = +41.32. The NPV is positive, so the project earns more than 10% and clears the hurdle. In Excel: =SUMPRODUCT(B2:B4 / (1 + 10%)^A2:A4), with periods 0, 1, 2 in A2:A4 and cash flows -1000, 600, 600 in B2:B4.
Exercise
A model discounts monthly cash flows using an annual rate of 12% entered directly as the rate. What is wrong, and what monthly rate would be consistent with a 12% effective annual rate?
Show answer
The rate period does not match the cash flow period, so each month is discounted as if it were a full year, which understates present values. A monthly rate consistent with a 12% effective annual rate is (1 + 12%)^(1/12) - 1, which is about 0.949% per month. Using 12%/12 = 1% gives a slightly higher effective annual rate of about 12.68%, so state which convention the model uses.