Sub topic 2
Choosing and applying a discount rate
This chapter assumes you can enter formulas and use cell references in Excel. It also assumes you know compound interest, meaning that interest earns interest. It builds on the previous chapter's idea that a dollar today is worth more than a dollar later. Here you decide which rate to use to turn future cash flows into present value, and how to apply that rate correctly in a model.
What the discount rate represents
A discount rate is the annual return you could expect from an alternative use of the money, given the risk of the cash flows you are valuing. It acts as a price of waiting and a price of risk. A higher rate shrinks future cash flows more, so present value falls.
The rate is a modeling judgment, not a fact you look up. Two analysts can value the same project differently because they chose different rates, and both can be defensible. Your job is to pick a rate you can justify and to show how much the answer depends on it.
Where the rate comes from
Four sources are common in practice.
| Source | What it is | Typical use |
|---|---|---|
| Opportunity cost | The return on the next best investment of similar risk | Personal or small-business decisions |
| Cost of capital (WACC) | The weighted average of the cost of debt (after tax) and the cost of equity | Corporate projects with average company risk |
| Hurdle rate | A minimum return set by management or investors | Capital budgeting approvals |
| Risk-adjusted rate | The base rate plus a premium for project-specific risk | Projects riskier or safer than the company overall |
Use a rate that matches the risk of the cash flows, not the risk of the company that happens to own them. A safe project inside a risky company deserves a lower rate than the company's WACC. A speculative project deserves a higher one.
Keep the rate consistent with the cash flows
Three consistency rules prevent most rate errors.
- Nominal with nominal, real with real. Nominal cash flows include expected inflation, so discount them with a nominal rate. Cash flows in constant prices need a real rate. Mixing them undervalues or overvalues the project.
- After-tax with after-tax. If your cash flows are after tax, use an after-tax rate. WACC already uses the after-tax cost of debt.
- Currency with currency. Discount cash flows in a given currency with a rate for that currency.
Match the rate to the period length
NPV and IRR assume the rate is per period, and the period is whatever spacing your cash flows have. If your cash flows are monthly, the rate you pass to NPV must be a monthly rate.
Do not divide an annual rate by 12. That gives a nominal rate that compounds to more than the annual rate. Convert it so that 12 months of compounding reproduce the annual rate:
B1: Annual discount rate = 8%
B2: Monthly discount rate =(1 + B1)^(1/12) - 1For 8%, the monthly rate is about 0.6434%. Dividing by 12 gives 0.6667%, which compounds to about 8.30% a year. This is the reverse of the annualizing step you will use for IRR later: for IRR you raise the periodic rate to the power 12, and here you take the twelfth root of the annual rate.
The dated functions XNPV and XIRR avoid this problem. They always take an annual rate and handle the timing from the dates.
Worked example: how much the rate matters
Use the same project as in the NPV chapter. The outflow at t=0 is -10,000, and the inflows at the end of years 1 to 4 are 3,000, 4,000, 4,000, and 3,000. Put the rate in its own cell and refer to it everywhere. Never type 8% inside a formula.
B1: Discount rate = 8%
B3: -10000
B4: 3000
B5: 4000
B6: 4000
B7: 3000
NPV at the rate in B1:
=NPV(B1, B4:B7) + B3At 8%, the NPV is about 1,587.55. Each inflow is divided by (1 + 0.08) raised to its year number. The present values are 2,777.78, 3,429.36, 3,175.33, and 2,205.09, which sum to 11,587.55, and subtracting the 10,000 outflow leaves the NPV.
The same cash flows at other rates give very different answers:
| Discount rate | NPV |
|---|---|
| 8% | about 1,587.55 |
| 12% | about 621.02 |
| 15% | about -21.40 |
The project clears an 8% or 12% hurdle but fails a 15% hurdle. The cash flows did not change. Only the judgment about the rate did. This is why you should test a range of rates and not report a single number.
Build a sensitivity column
List trial rates in a column and compute the NPV for each. The $ signs lock the cash flow range so the formula can be filled down:
A3:A9 hold trial rates: 6%, 8%, 10%, 12%, 14%, 16%, 18%
B3:B7 hold the cash flows from the example above (B3 is the t=0 outflow)
In C3, fill down to C9:
=NPV($A3, $B$4:$B$7) + $B$3Scan down the column for the sign change. The rate where NPV crosses zero is the project's IRR, which here is just under 15%. You will use this NPV profile again when comparing NPV and IRR.
A decision flow for choosing the rate
Common errors
- Hardcoding the rate. A rate typed into many formulas will be missed when you change it. Keep one input cell, and label it with its basis (annual, monthly).
- Percent entered as a whole number. Typing 8 instead of 8% gives a rate of 800%. Format the input cell as a percentage so the mistake is visible.
- Annual rate with monthly cash flows. The NPV comes out far too low, because each month is discounted as if it were a full year.
- Using the cost of debt for an equity-risk project. Cheap debt does not make a risky project safe. Use a rate that reflects the project's risk.
- A single point estimate. Report the NPV at a base rate and at rates a few points above and below it.
Exercise
A project has monthly cash flows and your annual discount rate is 12%. (1) What monthly rate should you pass to NPV? (2) Why is 12%/12 = 1% not quite right? Give the Excel formula for part (1).
Show answer
(1) Use =(1 + 0.12)^(1/12) - 1, which is about 0.9489% per month. (2) Compounding 1% for 12 months gives (1.01)^12 - 1, about 12.68% a year, which is higher than the 12% target. Dividing by 12 gives a nominal monthly rate, while the twelfth root gives the monthly rate that compounds to exactly 12% a year.