The problem MIRR addresses
IRR has two weaknesses:
- Reinvestment assumption. IRR implicitly treats every interim inflow as reinvested at the IRR itself. A project that returns 15% looks 15% good only if you can place each payout in another 15% investment.
- Multiple solutions. When the cash flow signs change more than once, the NPV equation can have several roots, so
IRRreturns whichever one the solver finds first.
MIRR replaces the single implied rate with two explicit assumptions that you choose:
- A finance rate: the cost of borrowing, used to discount negative cash flows to t=0.
- A reinvestment rate: the return on cash you receive, used to compound positive cash flows to the final period.
The model then reduces the project to one outflow today and one inflow at the end. The MIRR is the single rate that grows the first into the second.
How MIRR is computed
For n periods:
- Discount every negative cash flow to t=0 at the finance rate. Call the total PV₋.
- Compound every positive cash flow to period n at the reinvestment rate. Call the total FV₊.
- Solve for the rate: MIRR = (FV₊ / PV₋)^(1/n) − 1.
Because the answer is a closed-form expression, MIRR needs no iteration. It has no guess argument and cannot fail to converge.
Using Excel's MIRR function
The syntax is =MIRR(values, finance_rate, reinvest_rate). Use the same project as in earlier chapters: −10,000 at t=0, then 3,000, 4,000, 4,000 and 3,000 at the ends of years 1 to 4.
B3:B7 hold periodic cash flows, with B3 as the t=0 outflow
D1: Finance rate (cost of borrowing) = 6%
D2: Reinvestment rate = 8%
=MIRR(B3:B7, D1, D2)Unlike NPV, MIRR takes the whole range including the t=0 cash flow. There is no timing pitfall here, because the function treats the first value as t=0.
The result is about 12.05%. IRR on the same flows gives about 14.9%. The gap exists because MIRR assumes the inflows grow at 8%, not at 14.9%.
Verifying the result by hand
Cross-check MIRR with the three steps above. This project has a single outflow at t=0 and inflows from t=1, so the PV of outflows is just −B3:
FV of inflows at t=4, divided by the t=0 outflow, raised to 1/4:
=(NPV(D2, B4:B7) * (1 + D2)^4 / -B3)^(1/4) - 1NPV(D2, B4:B7) discounts the inflows to t=0. Multiplying by (1 + D2)^4 carries that value forward to t=4, which is the same as compounding each inflow to the end. The formula returns the same 12.05% as MIRR. If the two disagree, check that the rate cells are not swapped.
What MIRR does with multiple sign changes
Take flows of −1,000 at t=0, +5,000 at t=1 and −6,000 at t=2, such as a project with a large closing cost. Two rates make NPV zero here: 100% and 200%. IRR reports one of them depending on the guess, and neither is meaningful.
With a 10% finance rate and a 10% reinvestment rate, MIRR works as follows:
- PV of outflows = 1,000 + 6,000 / 1.1² ≈ 5,958.68.
- FV of inflows = 5,000 × 1.1 = 5,500.
- MIRR = (5,500 / 5,958.68)^(1/2) − 1 ≈ −3.9%.
MIRR gives one unambiguous answer. It is negative, which agrees with the NPV at 10% of about −1,413.
Relationship to NPV
Set the finance rate and the reinvestment rate both equal to a required return r. Then MIRR exceeds r exactly when NPV at r is positive, so MIRR and NPV give the same accept/reject decision for a single project. MIRR still can rank mutually exclusive projects differently from NPV, because it is a percentage and ignores project size.
| Measure | Answer type | Reinvestment assumption | Unique answer | Needs iteration |
|---|---|---|---|---|
| NPV | Currency amount | Discount rate | Yes | No |
| IRR | Rate | The IRR itself | Not always | Yes |
| MIRR | Rate | Rate you specify | Yes | No |
Limits and edge cases
- No built-in date version. There is no
XMIRR.MIRRassumes equally spaced periods, so for irregular dates you must build the calculation yourself. - Sign requirement. The range needs at least one negative and one positive value. Otherwise
MIRRreturns#DIV/0!. - Bad rate inputs. Non-numeric rates produce
#VALUE!. - Blanks and text. Empty cells, text and logical values inside the range are ignored. This can shift the timeline silently, because a skipped cell is not counted as a period. Enter an explicit 0 for a period with no cash flow.
- Rate sensitivity. The result depends on two inputs you pick. A MIRR quoted without its finance and reinvestment rates cannot be reproduced or judged.
- Periodic output. As with
IRR, the result is per period. Annualize a monthly MIRR with=(1 + MIRR(...))^12 - 1.
For dated cash flows, you can reproduce MIRR on the same 365-day basis that XNPV uses. Here A2:A6 hold ascending dates, B2:B6 hold cash flows, D1 is the finance rate and D2 is the reinvestment rate:
=( SUMPRODUCT((B2:B6>0) * B2:B6 * (1 + D2)^((MAX(A2:A6) - A2:A6) / 365))
/ -SUMPRODUCT((B2:B6<0) * B2:B6 / (1 + D1)^((A2:A6 - MIN(A2:A6)) / 365))
)^(365 / (MAX(A2:A6) - MIN(A2:A6))) - 1The numerator compounds positive flows to the last date. The denominator discounts negative flows to the first date. The exponent annualizes the growth over the actual number of days.
Using it in a model
A practical pattern is to report NPV as the decision metric, IRR or XIRR as the familiar headline rate, and MIRR as a check on whether the headline rate is credible. If IRR is 25% but MIRR at realistic rates is 11%, the project's appeal depends heavily on reinvesting at an optimistic return. Add a check cell that flags the case where IRR and MIRR differ by more than a threshold you set, such as 3 percentage points.
Exercise
A project has cash flows of -5,000 at t=0, then 2,000, 2,500 and 2,500 at the ends of years 1, 2 and 3. The finance rate is 5% and the reinvestment rate is 7%. Write a manual formula for the MIRR using NPV, assuming the cash flows are in B3:B6, the finance rate is in D1 and the reinvestment rate is in D2. Then state roughly what it returns.
Show answer
Only the t=0 flow is negative, so PV of outflows is -B3 = 5,000. Compound the inflows to t=3: =(NPV(D2, B4:B6) * (1 + D2)^3 / -B3)^(1/3) - 1. The FV of inflows is 2,000 × 1.07² + 2,500 × 1.07 + 2,500 = 2,289.80 + 2,675 + 2,500 = 7,464.80. The ratio is 7,464.80 / 5,000 = 1.4930, and the cube root is about 1.1427, so MIRR ≈ 14.3%. This equals =MIRR(B3:B6, D1, D2). The finance rate does not affect the result because there are no negative flows after t=0.
Exercise
Why does MIRR not need a guess argument, and why can it still give a misleading impression of a project?
Show answer
MIRR is a closed-form calculation: it compounds inflows, discounts outflows and takes a root, so there is no iteration to start or fail. It can still mislead because the result depends on the finance and reinvestment rates you assume. An optimistic reinvestment rate inflates it, and as a percentage it ignores project size, so it can rank mutually exclusive projects differently from NPV.