Sub topic 13
Verifying Invoices and Paying Against Milestones
Prerequisites and the payment model
Assume you understand scope, schedule, budget, stakeholders, and the basic structure of a contract. You should also know how a work breakdown structure connects project work to deliverables.
A vendor invoice is a request for payment. The project manager should not approve it merely because the vendor submitted it. Payment should follow the contract, evidence of completed work, and the project's approval process.
For milestone-based payment, the vendor earns payment when a defined result is accepted. A milestone is a significant checkpoint in the work. Acceptance means that the authorized reviewer confirms the result meets the stated criteria.
The payment amount usually follows this sequence:
- Confirm that the claimed milestone is in the contract.
- Check that the acceptance criteria have been met.
- Match the invoice to the accepted amount and contract rate.
- Apply retainage, credits, taxes, or approved changes.
- Obtain the required approvals.
- Send the approved invoice to accounts payable.
Checking an invoice
Use consistent evidence rather than judgment alone. Depending on the work, evidence might include a signed inspection, test results, an approved design, a delivery receipt, or a timesheet.
A three-way match compares the invoice with the contract or purchase order and evidence that the goods or services were received. This catches common errors such as duplicate billing, incorrect rates, unsupported expenses, and payment for work that has not been accepted.
| Check | Question |
|---|---|
| Vendor identity | Is the invoice from the contracted legal entity? |
| Contract reference | Does it cite the correct contract or purchase order? |
| Scope | Does each charge relate to authorized work? |
| Milestone | Is the claimed milestone accepted and documented? |
| Amount | Do rates, quantities, and calculations match the contract? |
| Adjustments | Are retainage, credits, taxes, and approved changes handled correctly? |
Retainage is a percentage withheld until later completion or final acceptance. It protects the buyer when defects or unfinished work remain. The contract must state the rate and the condition for releasing it.
CONTRACT_VALUE = 120_000
RETAINAGE_RATE = 0.10
milestones = [
{"name": "Design approved", "share": 0.20, "accepted": True},
{"name": "Build complete", "share": 0.50, "accepted": True},
{"name": "Acceptance test passed", "share": 0.30, "accepted": False},
]
earned = sum(
CONTRACT_VALUE * milestone["share"]
for milestone in milestones
if milestone["accepted"]
)
retainage = earned * RETAINAGE_RATE
payable = earned - retainage
print(
f"Earned: {earned:.2f}, "
f"retainage held: {retainage:.2f}, "
f"payable now: {payable:.2f}"
)This example pays only for accepted milestones. It calculates earned value of $84,000, holds $8,400 as retainage, and makes $75,600 payable.
Handling exceptions and approvals
Return an invoice when the evidence is missing, the amount is wrong, or the work differs from the approved scope. Record the reason and the action required. Do not silently edit the vendor's invoice.
A change request must be approved before extra work starts. If an invoice includes unapproved work, separate that amount and escalate it through change control. A project manager should never use an invoice approval to authorize a change after the fact.
Keep an invoice log with the submission date, review status, accepted milestones, disputed amount, approvers, and payment date. This creates an audit trail and helps identify repeated vendor problems.
Exercise
A vendor invoices for the final 30% milestone, but the client witness test is not signed. What should you do?
Show answer
Place that portion on hold, record the missing acceptance evidence, notify the vendor and reviewer, and pay only any separately accepted amount allowed by the contract.