Controlling Changes to Vendor Work
Assume you know basic project management terms such as scope, schedule, budget, stakeholder, and work breakdown structure. Also assume you understand that a contract defines obligations between a buyer and a vendor. This chapter focuses on what happens when the vendor's agreed work needs to change.
A vendor change is any approved or proposed adjustment to the contracted scope, price, schedule, quality requirements, or acceptance criteria. Examples include adding server-room circuits, replacing a specified material, or moving a delivery date.
Start with the contract baseline
The contract baseline is the approved version of the vendor's work. It should identify:
- The work the vendor must perform
- The deliverables and acceptance criteria
- The agreed price or pricing method
- The required dates and dependencies
- The people authorized to approve changes
- The process for submitting and approving changes
Compare every request with this baseline. A vendor may describe extra work as a small clarification, but the project manager must determine whether it changes the agreement.
Do not authorize extra work through an informal conversation. A casual request can create a payment dispute or an unplanned schedule commitment.
Analyze the requested change
Record the request in a change log and ask the vendor for enough detail to evaluate it. The analysis should cover:
- Description of the requested change
- Reason for the change
- Added or removed deliverables
- Cost impact and pricing basis
- Schedule impact and affected dependencies
- Effect on quality, safety, security, or compliance
- New risks and required mitigations
- Changes to acceptance tests or documentation
The project manager then checks whether the request is already included in the contract. If it is included, the vendor may need to perform it without a price increase. If it is outside the baseline, the request follows formal change control.
| Change status | Meaning | Vendor action |
|---|---|---|
| Submitted | Request is recorded but not approved | Do not begin changed work |
| Under review | Impact analysis is in progress | Provide estimates and clarification |
| Approved | Authorized people accepted the change | Begin according to the approved version |
| Rejected | Request will not be added | Continue the baseline work |
| Implemented | Approved change is complete and accepted | Provide evidence and update records |
Route the request for approval
Use the approval path defined in the contract and project governance. A change may require the project manager, sponsor, procurement representative, finance team, or client to approve it. The approval must cover both the change itself and its cost or schedule effect.
For example, a request to add two circuits might have a cost impact of $4,200 and extend the work by three days. The approval record should state those exact effects, identify the funding source, and show who approved them.
Update the working plan
After approval, update the contract record, scope, schedule, budget, risk register, and acceptance criteria. Tell affected stakeholders what changed. The vendor and project team should work from the same current version.
At completion, verify the changed deliverable against its revised acceptance criteria. Do not pay for changed work based only on the vendor's invoice. Confirm that the approved work was performed and accepted.
Exercise
A vendor asks to add a feature for $8,000 and says it will take five extra days. What should you do first?
Show answer
Record the request, compare it with the contract baseline, and obtain a documented impact analysis before seeking approval. Do not authorize the vendor to begin informally.