Sub topic 5
Choosing a Contract Type
Assume you know basic project management terms such as scope, schedule, budget, and stakeholders. You should also understand how a work breakdown structure divides project work into manageable parts.
A contract type defines how the buyer pays the vendor and who carries the risk when costs or effort differ from the plan. Choose it after examining how clear the scope is, how uncertain the work will be, and how much control the project team needs over cost.
Fixed-price contracts
A fixed-price contract sets one agreed price for a defined scope. The vendor carries most cost-overrun risk. The buyer gains budget predictability, but changes usually require a formal change request.
Use this type when:
- Deliverables and acceptance criteria are clear.
- The vendor can estimate the work with reasonable confidence.
- The buyer wants a known maximum price.
- The work will not change often.
For example, a vendor might agree to install a specified electrical system for $120,000. If the vendor underestimates the labor, the vendor normally absorbs the loss. If the buyer adds two circuits, the parties should approve a change request before the extra work begins.
The main failure mode is an unclear scope. A vendor may price assumptions that the buyer did not notice, leading to disputes over what the fixed price includes.
Time-and-materials contracts
A time-and-materials, or T&M, contract pays for actual labor time and materials used. The buyer carries more cost risk, but the arrangement handles uncertain work better.
Use T&M when:
- The exact solution is not known yet.
- The work is exploratory or likely to change.
- The buyer needs access to specialized people quickly.
- The parties can monitor hours, rates, and materials.
Add controls such as hourly rate limits, a not-to-exceed amount, approved timesheets, and regular forecasts. Without these controls, a T&M contract can continue spending after the expected value has disappeared.
Cost-plus contracts
A cost-plus contract reimburses allowable costs and adds a fee or profit. The buyer carries most cost risk. The vendor has less incentive to reduce spending unless the contract adds performance incentives or a target cost.
Use cost-plus when:
- The work has high technical or market uncertainty.
- A reliable fixed price cannot be estimated.
- The buyer needs the vendor to begin before the design is complete.
Define allowable costs, records, audit rights, fee calculations, and approval rules. “Cost” must not mean every expense the vendor chooses to report.
Compare the trade-offs
| Contract type | Best fit | Main buyer risk | Main vendor risk |
|---|---|---|---|
| Fixed-price | Clear, stable scope | Paying for a price loaded with assumptions | Cost overruns |
| Time and materials | Changing or uncertain work | Spending more than planned | Limited work pipeline |
| Cost-plus | Highly uncertain or complex work | Cost growth and weak cost control | Audit and documentation burden |
A practical selection process
- Estimate how complete the scope and design are.
- Identify which party can best control each risk.
- Compare the need for price certainty with the need for flexibility.
- Add controls for the chosen type.
- Confirm that payment, acceptance, change, and dispute terms support the choice.
Exercise
A vendor must investigate an unknown system for two weeks, then deliver a defined repair. Which contract approach could fit, and what control would you add?
Show answer
Use T&M for the investigation and a fixed-price change or follow-on contract for the defined repair. Add a time limit, approved rates, timesheets, and a review before continuing.