Sub topic 2
Deciding What to Outsource
Assume you know basic project terms such as scope, schedule, budget, stakeholders, and work breakdown structure. You should also understand that a contract creates obligations for both the buyer and the seller.
Outsourcing means obtaining project work from an external organization or person. The project team still owns the project result. Outsourcing transfers selected work and some delivery responsibility, but it does not remove the project manager’s responsibility to plan, coordinate, and verify the work.
Start with a make-or-buy decision
A make-or-buy decision compares doing work with internal staff (make) against procuring it from an external party (buy). Begin with a clearly defined work package from the work breakdown structure.
Ask these questions:
- Does the team have the required skills and capacity?
- Is the work part of the organization’s long-term capability?
- How quickly must the work start and finish?
- What is the complete internal cost?
- What risks would an external party introduce?
- Can the result be checked with clear acceptance criteria?
- Would outsourcing expose confidential information or critical knowledge?
Do not compare only the vendor’s quoted price with an employee’s salary. Include recruiting, training, tools, management time, quality checks, taxes, overhead, transition costs, and the cost of delay.
| Criterion | Make: internal team | Buy: external party |
|---|---|---|
| Control | Usually higher day-to-day control | Governed through the contract |
| Speed | Limited by internal capacity | May provide specialized capacity quickly |
| Cost certainty | Can vary with productivity and staffing | Depends on contract type and scope quality |
| Knowledge | Retained inside the organization | May leave when the contract ends |
| Risk | Organization carries delivery risk | Some delivery risk shifts to the vendor |
Use weighted criteria
A weighted decision matrix makes the reasoning visible. A criterion has a weight that represents its importance. Each option receives a score, such as 1 through 5. Multiply each score by its weight and add the results.
criteria = {
"cost": 0.25,
"speed": 0.20,
"capability": 0.25,
"control": 0.15,
"risk": 0.15,
}
scores = {
"make": {
"cost": 3,
"speed": 2,
"capability": 4,
"control": 5,
"risk": 3,
},
"buy": {
"cost": 4,
"speed": 5,
"capability": 5,
"control": 3,
"risk": 3,
},
}
totals = {
option: sum(criteria[name] * score for name, score in values.items())
for option, values in scores.items()
}
for option, total in totals.items():
print(f"{option}: {total:.2f}")
print("Recommendation:", max(totals, key=totals.get))The matrix supports a decision. It does not replace judgment. Record the assumptions behind each score and test how the result changes if a weight or estimate changes.
Check the boundary and ownership
Outsourcing one work package creates dependencies. Define who supplies inputs, who makes decisions, who integrates the result, and who accepts it. Keep internal ownership for architecture, regulatory decisions, stakeholder commitments, or other work that must remain under direct organizational control.
Use a simple sequence:
The decision record should name the work, chosen option, alternatives considered, assumptions, expected benefits, risks, and approval authority. Revisit it if scope, funding, schedule, or internal capacity changes.
Exercise
A vendor offers a low price for work that the team cannot describe with measurable outputs. What should the project manager do first?
Show answer
Define the deliverables, boundaries, and acceptance criteria before comparing prices or awarding the work.