Sub topic 7
Prioritizing with a Power/Interest Grid
Assume you understand basic project roles, scope, schedule, and budget. This chapter focuses on turning stakeholder information into priorities. The goal is not to label people permanently. The goal is to decide where the project team should spend attention now.
What the Grid Shows
A power/interest grid compares two factors:
- Power is a stakeholder’s ability to approve, block, fund, change, or redirect the project.
- Interest is how closely the stakeholder cares about the project’s work or results.
Rate both factors consistently, often on a scale from 1 to 5. A rating of 3 or higher can represent “high.” Place each stakeholder in one of four quadrants:
| Power | Interest | Recommended approach |
|---|---|---|
| High | High | Manage closely |
| High | Low | Keep satisfied |
| Low | High | Keep informed |
| Low | Low | Monitor |
Power is not the same as job seniority. A subject-matter expert may have little formal authority but enough specialist knowledge to affect a safety decision. An external regulator may have high power even though they are not part of the project organization.
Rating Stakeholders
Use evidence rather than intuition. Ask questions such as:
- Can this person approve the business case or release funding?
- Can this group delay work through a formal review?
- Does the stakeholder control information, access, or technical knowledge?
- Will the project directly change this stakeholder’s work?
- How often does the stakeholder need updates or decisions?
Record the reason for each rating. For example, “power 5 because the sponsor controls funding” is more useful than simply writing “5.” Ratings can change during the project. A user group may have low power during design but high influence during acceptance testing.
The following function applies a threshold of 3. It separates the classification rule from the stakeholder data, making the rule easy to test or change.
def quadrant(power, interest, threshold=3):
high_power = power >= threshold
high_interest = interest >= threshold
if high_power and high_interest:
return "Manage closely"
if high_power:
return "Keep satisfied"
if high_interest:
return "Keep informed"
return "Monitor"
stakeholders = [
("Dana Lee", 5, 4),
("Sam Ortiz", 2, 5),
("Acme Regulators", 5, 2),
("End users", 1, 5),
]
for name, power, interest in stakeholders:
print(f"{name}: {quadrant(power, interest)}")The output places the executive sponsor in “Manage closely,” the support lead and end users in “Keep informed,” and the regulators in “Keep satisfied.” These are starting points for engagement, not automatic communication schedules.
Choosing the Right Attention
Manage closely
Involve high-power, high-interest stakeholders in important decisions. Confirm expectations, review risks, and provide timely progress information. Avoid involving them in every minor task because excessive detail can slow decisions.
Keep satisfied
These stakeholders can strongly affect the project but may not want frequent operational detail. Provide concise updates about risks, decisions, compliance, budget, and outcomes. Escalate issues before they become surprises.
Keep informed
These stakeholders care about the result but may lack formal authority. Share relevant progress, explain changes, and provide ways to give feedback. Ignoring this group can create resistance during adoption.
Monitor
Use lightweight communication. Check whether their power or interest changes, especially after a new risk, policy, dependency, or project phase appears.
Handling Movement and Conflicts
Stakeholders can move between quadrants. A department manager may become highly interested when a rollout changes local procedures. A sponsor’s interest may decrease after funding is approved. Review the grid at phase gates, major scope changes, and risk reviews.
Conflicting interests require explicit handling. For example, executives may want an early launch, while compliance staff require additional evidence and end users need training. Record the conflict, identify the project objective or constraint it affects, and bring it to the person with authority to resolve the trade-off. Do not hide the conflict by giving every stakeholder the same message.
Exercise
Exercise
A regulator has power 5 and interest 2. Which quadrant applies, and what should the project team communicate?
Show answer
The regulator belongs in “Keep satisfied.” Provide concise, accurate updates about compliance, risks, required evidence, and decisions. Escalate potential violations early.