Sub topic 6
Assessing Power, Influence and Impact
Assume you know the project’s goals, scope, timeline, and budget. You should also know the basic roles of a sponsor, project manager, and team member. This chapter shows how to assess what each stakeholder can affect and how much attention the project should give them.
Three Different Measures
A stakeholder’s power is their formal ability to make decisions or control resources. A sponsor who approves the budget has high power. A team member who cannot approve changes usually has less formal power.
A stakeholder’s influence is their ability to shape decisions or other people’s behavior. Influence can come from expertise, trust, relationships, reputation, or access to decision-makers. A respected subject-matter expert may have strong influence even without a senior job title.
A stakeholder’s impact is the degree to which the project affects that stakeholder. Daily users may have little decision power, but the project may greatly change their work. That gives them high impact.
These measures are related but not interchangeable:
| Measure | Main question | Example |
|---|---|---|
| Power | Can this person authorize, stop, or change the project? | Executive sponsor |
| Influence | Can this person shape decisions or opinions? | Trusted technical expert |
| Impact | How much will the project change this person’s work or outcomes? | Daily end user |
Do not assume that a stakeholder with low power is unimportant. A group with high impact may reveal usability, safety, or adoption problems before powerful stakeholders notice them.
Rating Stakeholders Consistently
Use a simple scale, such as 1 to 5:
- 1 means very low.
- 2 means low.
- 3 means moderate.
- 4 means high.
- 5 means very high.
Write evidence beside each rating. For example, “power = 5 because Dana approves the release budget” is more useful than “power = 5” alone. Evidence makes ratings easier to review and update.
Rate the stakeholder’s current position, not their job title alone. A department manager may have high power during procurement but little power during user acceptance testing. A regulator may have limited day-to-day involvement but enough authority to stop a non-compliant launch.
Consider these questions:
- Can the stakeholder approve funding, scope, or schedule changes?
- Can the stakeholder block access, permissions, or delivery?
- Do other people follow the stakeholder’s advice?
- Will the project change the stakeholder’s work, costs, risks, or benefits?
- Can the stakeholder create legal, operational, or reputational consequences?
def quadrant(power, interest, threshold=3):
high_power = power >= threshold
high_interest = interest >= threshold
if high_power and high_interest:
return "Manage closely"
if high_power:
return "Keep satisfied"
if high_interest:
return "Keep informed"
return "Monitor"
stakeholders = [
("Dana Lee", 5, 4),
("Sam Ortiz", 2, 5),
("Acme Regulators", 5, 2),
("End users", 1, 5),
]
for name, power, interest in stakeholders:
print(f"{name}: {quadrant(power, interest)}")This example uses interest as a practical proxy for involvement. It does not replace judgment. Record impact separately when it affects engagement or risk.
Using the Assessment
A power and interest grid helps you choose an initial level of engagement. Power is shown vertically, and interest is shown horizontally.
Use the grid as a starting point:
- Manage closely: Involve these stakeholders in important decisions. Confirm expectations often.
- Keep satisfied: Give timely information and address concerns before they become blockers.
- Keep informed: Explain changes, gather feedback, and support adoption.
- Monitor: Track changes without spending more effort than the risk requires.
Impact adds another question: who will experience the consequences if the project succeeds or fails? For example, end users may belong in “keep informed” because they have low power and high interest, but their high impact may justify user testing, training, and feedback sessions.
Review Ratings Over Time
Power, influence, interest, and impact can change at each phase. A new executive may join. A regulator may become more involved before launch. A user group may lose interest after its main concerns are resolved.
Review the ratings at major milestones, after scope changes, and when a new risk appears. Record the reason for each change in the stakeholder register. If a rating changes, review the engagement and communication plan as well.
Exercise
A user group has power 1, interest 5, and impact 5. How should the project team engage it?
Show answer
Keep the group informed, but give it additional attention because the project strongly affects its work. Include representatives in user testing, explain changes clearly, and use their feedback to reduce adoption risks.