Sub topic 2
Internal, External, Primary and Secondary Stakeholders
This chapter assumes you understand basic project roles such as sponsor, project manager, and team member. You should also know that a project has a defined goal, scope, timeline, and budget.
Why Stakeholder Categories Matter
A stakeholder is a person, group, or organization that can affect a project, is affected by it, or believes it may be affected by it. Stakeholders do not all have the same relationship with the project. Categorizing them helps you decide whose needs to investigate, who should make decisions, and how to communicate.
Two classification systems are especially useful:
- Internal or external describes the stakeholder's relationship with the organization running the project.
- Primary or secondary describes how directly the stakeholder experiences the project's results or effects.
These systems describe different things. A stakeholder can be internal and primary, external and primary, internal and secondary, or external and secondary.
Internal and External Stakeholders
An internal stakeholder is part of the organization that sponsors or delivers the project. Examples include:
- The executive sponsor
- The project manager and project team
- Department managers
- Employees who will use a new process
- Finance, legal, security, or support departments
Internal stakeholders often have access to project decisions, resources, and organizational information. However, do not assume that all internal stakeholders agree. A finance manager may prioritize cost control, while a sales manager may prioritize speed.
An external stakeholder is outside the organization running the project. Examples include:
- Customers and end users
- Suppliers and contractors
- Regulators
- Partners
- Local communities
- Investors or owners outside the delivery organization
External stakeholders may have less direct access to project information, but their approval, behavior, or response can determine whether the project succeeds. A regulator may stop a launch. A supplier may delay a critical component. A customer may reject a product that technically meets its specification.
Primary and Secondary Stakeholders
A primary stakeholder experiences a direct effect from the project's output, activities, or decisions. For a payroll replacement project, employees who receive pay through the system are primary stakeholders. The payroll team is also primary because its daily work changes.
A secondary stakeholder is affected indirectly or has an indirect interest. For the same project, the facilities team might be secondary if it only provides office access for training. A professional association might be secondary if it monitors the project's effect on industry practices.
“Secondary” does not mean unimportant. A secondary stakeholder can have substantial power. A regulator may not use a new system every day, but its approval may be required before release.
| Category | Main question | Example in a payroll project |
|---|---|---|
| Internal | Is the stakeholder part of the delivery organization? | Finance manager |
| External | Is the stakeholder outside that organization? | Payroll software supplier |
| Primary | Does the stakeholder experience a direct effect? | Employee paid through the system |
| Secondary | Is the effect or interest indirect? | Industry association |
Classifying a Stakeholder
Use these questions when classifying someone:
- Is the person or group inside the organization delivering the project?
- Will the person use the output or experience a direct change?
- Can the person approve, block, fund, regulate, or materially influence the project?
- Does the person represent others whose interests may not be visible?
Record both classifications in the stakeholder register. Also record the reason for each classification. This prevents labels from becoming unsupported assumptions.
Common Errors
Teams often identify only people with formal project roles. This misses customers, support staff, suppliers, and groups affected by changed work.
Another error is treating primary stakeholders as the only important stakeholders. Secondary stakeholders can control funding, approvals, public reputation, or access to resources.
Finally, avoid assuming that one representative speaks for an entire group. “Customers” may include new customers, long-term customers, users with disabilities, and customers in different regions. Their interests may differ.
Exercise
Exercise
A company is introducing an online service. The security team works inside the company and must approve the design. Customers outside the company will use the service every day. A trade association will publish guidance about the service but will not use it. Classify each group as internal or external and primary or secondary.
Show answer
The security team is internal and primary because its work and approval directly affect the project. Customers are external and primary because they use the service directly. The trade association is external and secondary because it is outside the company and has an indirect interest.