Sub topic 9
Choosing an Engagement Approach for Each Stakeholder Group
This chapter assumes you understand basic project roles and can read a stakeholder register. You should also know how to rate power and interest, because those ratings help you choose an engagement approach. The goal is not to communicate with every stakeholder in the same way. The goal is to give each group the right level of involvement at the right time.
Match Engagement to Stakeholder Needs
Engagement is the way a project team involves, informs, consults, or collaborates with a stakeholder. A useful approach considers three factors:
- How much power the stakeholder has to affect decisions or outcomes.
- How interested the stakeholder is in the project.
- How much the project affects the stakeholder.
The power/interest grid provides a starting point:
| Stakeholder position | Main approach | Typical actions |
|---|---|---|
| High power, high interest | Manage closely | Involve in decisions, review risks, meet regularly |
| High power, low interest | Keep satisfied | Send concise updates, confirm major decisions |
| Low power, high interest | Keep informed | Share progress, gather feedback, explain changes |
| Low power, low interest | Monitor | Provide occasional updates and watch for changing needs |
These are guidelines, not fixed rules. A stakeholder with low formal power may still have strong informal influence. For example, an experienced team supervisor might persuade many employees even without approval authority.
Choose the Level of Involvement
Use a level of involvement that matches the stakeholder's role. Common levels include:
- Inform: Provide accurate information, such as a monthly status report.
- Consult: Ask for opinions or feedback before making a decision.
- Involve: Include the stakeholder in workshops, reviews, or planning sessions.
- Collaborate: Share responsibility for developing a solution.
- Empower: Give the stakeholder authority to make a defined decision.
A stakeholder can move between levels during the project. A compliance authority may only need to be informed during early planning, then consulted before a release. End users may be consulted during requirements work and involved in usability testing.
Design Group-Specific Engagement
Avoid treating a broad group as if every member has the same needs. “Customers” might include daily users, purchasing managers, administrators, and customer support staff. Their interests and decision rights may differ.
For each group, define:
- The purpose of engagement.
- The information the group needs.
- The response or decision expected from the group.
- The channel and frequency.
- The person responsible for the relationship.
- The trigger for increasing or decreasing engagement.
For example, a project team replacing an internal service might use these approaches:
- Executive sponsor: A short decision-focused meeting every two weeks. The sponsor approves major scope and budget changes.
- Customer support lead: A weekly working session during design and training. The lead reviews support procedures and identifies likely ticket increases.
- End users: Demonstrations at the end of each iteration, followed by structured feedback.
- Regulator: Formal evidence packages at agreed control points, with questions tracked to closure.
A communication plan records these decisions. It should state what will be communicated, rather than merely listing meetings. “Weekly project meeting” is less useful than “Review unresolved risks, decisions needed, and changes to the launch date.”
Adjust the Approach When Conditions Change
Engagement plans can fail when they are written once and ignored. Review them at phase boundaries, after major decisions, and when the project encounters a risk or change request.
Increase engagement when:
- A stakeholder gains approval authority.
- The project begins affecting the stakeholder's work.
- A decision is disputed.
- Feedback reveals a requirement gap.
- A stakeholder becomes a source of delivery risk.
Reduce or change engagement when:
- A decision has been completed.
- The stakeholder's responsibilities move to another group.
- The project enters a phase with different information needs.
- Repeated meetings produce no decisions or useful feedback.
Record changes in the stakeholder register. Include the reason for the change so that another project team member can understand the decision.
Common Errors
A weak engagement approach often has one of these problems:
- It measures importance only by job title.
- It sends every stakeholder the same report.
- It asks for feedback without explaining how feedback will be used.
- It invites stakeholders to meetings without giving them a decision or preparation task.
- It continues a meeting after its purpose has ended.
- It hides conflicts instead of escalating them through the agreed decision path.
The project manager should make engagement purposeful. Every interaction should inform, obtain input, reach a decision, build support, or manage a risk.
Exercise
A department manager has high power but low interest in a software rollout. The manager must approve any change to the department's budget. What engagement approach should you start with, and when should you increase it?
Show answer
Start by keeping the manager satisfied with concise updates about budget, major risks, and decisions. Increase engagement to consultation or involvement if the rollout changes the department's budget, work processes, or approval decisions.