Sub topic 4
Simplification items and readiness checks
This chapter assumes you know the basic SAP ERP modules (finance, logistics, procurement), the development, quality, and production landscape, and what custom ABAP code and master and transactional data are. It also assumes you have read the chapter on what changes in S/4HANA. Here you learn how SAP records those changes in a structured form, and how you use that record to judge how ready a system is for conversion.
What a simplification item is
A simplification item is a documented description of one change between SAP ECC and SAP S/4HANA that can affect an existing customer. SAP publishes them in the Simplification Item Catalog. Each entry has the same basic parts:
- A title and an application area, such as Finance, Logistics, or Cross-Application.
- A description of what changed and why.
- The business impact: which processes, transactions, or data are affected.
- The required and recommended actions before, during, and after conversion.
- A technical check identifier, so a tool can test whether your system is affected.
Typical changes the catalog describes include:
- A transaction code is removed and replaced by a different one.
- A data structure is merged into another, such as customers and vendors moving into the business partner.
- A table is replaced by a view or a new table.
- A whole functional area is replaced by a successor, such as the older credit management moving to SAP Credit Management.
- A feature is no longer available and has no direct successor.
Not every item applies to every customer. An item for a module you never activated has no effect on you. The catalog is large, so the work lies in finding the items that are relevant to your system.
Why this matters for the transition path
Simplification items drive scope in a different way for each path.
- In a brownfield conversion, you carry your existing configuration and data forward. Each relevant item is a task you must complete, because the system must be technically and functionally valid after conversion.
- In a greenfield implementation, you do not convert anything. Items still tell you what the new standard does differently, which feeds fit-to-standard workshops, but they do not block a technical conversion.
- In a selective data transition, items affect both the source data you choose to move and the target design.
Because of this, the readiness checks in this chapter are most binding for brownfield. They are still useful input for the other two paths.
The tools that evaluate readiness
Several tools work together. They answer different questions, so you normally use more than one.
| Tool | Question it answers | Where it runs |
|---|---|---|
| Readiness Check for SAP S/4HANA | Which simplification items affect this system, and what is its overall readiness? | Cloud application, fed by data from your ECC system |
| Simplification Item Check (SI-Check) | Which items block conversion in the technical sense? | Report in the source system, and again in the conversion tooling |
| Custom Code Migration app and ABAP Test Cockpit | Which custom code breaks or needs change? | Central check system or the source system |
| Software Update Manager (SUM) | Can the system be technically converted? | Runs the conversion itself |
| Maintenance Planner | Are add-ons, business functions, and product versions supported on the target release? | SAP cloud service |
The Readiness Check for SAP S/4HANA is the usual first step. You run an extraction report in the ECC system, upload the result, and receive an analysis. It covers relevant simplification items, custom code scope, add-on compatibility, data volume, and recommended SAP Fiori apps.
The SI-Check is closer to the system. It runs the item checks directly against your data, for example looking at whether a table contains records that a change makes invalid. SUM runs the check again during the conversion preparation and stops the process if blocking conditions remain.
How readiness checks flow
The checks form a sequence. Early checks are cheap and give an estimate. Later checks are strict and stop the technical process.
Note the loop between fixing and checking. Expect to repeat it several times on a sandbox copy before you try the real conversion.
Classifying items by relevance
Once you have the list of items that apply to your system, sort them. A practical classification uses two questions: does the item block the conversion, and does it change a business process?
| Category | Meaning | Example action |
|---|---|---|
| Blocking, technical | SUM or the SI-Check stops the conversion until you resolve it | Complete customer/vendor integration to business partner |
| Data cleansing required | Existing data violates a new rule | Fix inconsistent or obsolete master data records |
| Process change | A transaction or process is replaced | Retrain users, update procedures, adjust authorizations |
| Custom code impact | Your own objects use removed or changed artifacts | Adapt or retire the code |
| Informational | No action beyond awareness | Note the change in documentation |
Many teams record each relevant item in a tracking list with an owner, a category, a status, and an effort estimate. This list becomes a large part of the brownfield project plan.
Example: reading a result
Suppose the Readiness Check reports 180 relevant items out of several hundred in the catalog. Do not treat 180 as 180 work packages. A typical breakdown is:
- Around two thirds are informational or need only user communication.
- A smaller group needs configuration changes, such as new settings after the finance data model change.
- A few are blocking and need data work, for example business partner synchronization or the removal of obsolete material number formats.
- Some link to custom code findings and are handled by the code team.
The numbers vary by system. What stays constant is the habit: group, assign owners, and estimate each group, not each line.
Where the checks run, and on which system
Run checks on a system copy that has production-like data, not only on the development system. Many blocking conditions come from data, not from configuration. A development system with little data can pass a check that production fails.
For the same reason, rerun the SI-Check on a fresh copy of production before the final conversion rehearsal. Data changes continuously, so a clean result from three months earlier does not guarantee a clean result today.
Common errors and gotchas
- Treating the Readiness Check as final. It is an estimate based on extracted data. The SI-Check inside SUM is the authoritative gate.
- Running checks only in development. Blocking items hide in production data volumes and history.
- Ignoring items classified as informational. Some of them remove functions your users rely on. Review them with process owners even if no technical step is required.
- Using an outdated catalog. SAP updates the catalog with each S/4HANA release. Check against the target release you plan to convert to, not an older one.
- Not rehearsing remediation. Data fixes such as business partner conversion can take hours on a large system. Time them in rehearsal so you can plan the cutover window.
- Forgetting add-ons and industry solutions. An unsupported add-on can block the conversion regardless of what the item list says. Maintenance Planner reveals this.
Using the results to choose a path
Readiness findings are evidence for the later decision chapter. Some signals to watch:
- A short list of mostly informational items, with few blockers, supports a brownfield conversion.
- A very long list of process-changing items, combined with heavily modified standard processes, points toward fit-to-standard and possibly greenfield.
- Large amounts of obsolete data blocking the conversion, or a wish to leave history behind, may point toward selective data transition.
- A large custom code finding set is not by itself a reason to avoid brownfield, but it affects effort. The next chapters on custom code cover this in detail.
Exercise
A Readiness Check on your ECC system returns a clean report with no blocking items. A colleague says the brownfield conversion is therefore safe to schedule. What is wrong with this reasoning, and what should you do next?
Show answer
The Readiness Check is an estimate built from extracted data, not the gate that controls the conversion. The SI-Check and the checks inside SUM run against real data on the exact target release, and they can still report blockers, especially from production data. Next, run the SI-Check on a recent production-like copy, run the custom code analysis, check add-ons in Maintenance Planner, and rehearse the conversion on a sandbox before scheduling.
Exercise
Why can a development system pass the SI-Check while the production system fails it?
Show answer
Many blocking conditions come from data rather than configuration, such as inconsistent customer and vendor records or obsolete entries. A development system usually holds little or clean data, so those conditions never appear. Production holds the full volume and history, so the same check finds violations there.