Sub topic 6
Fit-to-standard and process redesign
Prerequisites and scope
This chapter assumes you know the basic SAP ERP modules (finance, logistics, procurement) and how a landscape of development, quality, and production systems works. It also assumes you know what custom ABAP code is. You do not need hands-on S/4HANA experience.
Fit-to-standard is the working method used to decide which of your business processes can run as SAP delivers them and which need change. It matters most in greenfield projects, but it also applies to brownfield and selective transitions whenever you redesign processes.
From fit-gap to fit-to-standard
Older SAP projects used a fit-gap approach. The team wrote detailed business requirements first. Consultants then checked each requirement against the system. Anything that did not match became a "gap", and a gap usually became a custom development or a configuration workaround.
This had a predictable result. Requirements were often written to describe the old ECC process, so ECC habits were copied into the new system. Gaps turned into custom code, which raised cost and made later upgrades harder.
Fit-to-standard reverses the order:
- The business sees the standard solution first, running in a prepared system.
- The team compares the standard process with how the company works today.
- The team records only the differences that matter, and decides how to close each one.
The starting point is the delivered standard, not the old system. A difference is something to justify, not something that is assumed to be needed.
Where it sits in the project
In SAP Activate, the methodology covered in a later chapter, fit-to-standard happens in the Explore phase. It follows the Prepare phase and comes before Realize, where configuration and building take place.
A typical flow looks like this:
The activities in practice
Prepare a starter system
The team needs a system with the standard solution already set up. SAP provides preconfigured content, such as SAP Best Practices, and a model company with sample data. The system should be pre-filled with data the business recognizes, so people see something close to their own world.
Run workshops by process area
Workshops are organized by end-to-end process, for example order-to-cash, procure-to-pay, and record-to-report. Each one is led by a consultant who demonstrates the standard process in the system. Business process owners attend, because they can decide whether a difference is acceptable.
The workshop is a demonstration followed by discussion. It is not a requirements interview. Participants should see screens, roles, and data flows, not slides.
Record the results
For each process step, the team notes one of the following:
- It fits the standard and needs no change.
- It needs configuration, such as a different approval setting or a new payment term.
- It needs a change to the business process, so the company adapts.
- It needs an extension, because no standard option covers it.
Differences go into a backlog. Each item gets an owner, a business reason, and a rough effort estimate.
Prioritize and decide
Not every difference deserves the same effort. A useful check for each backlog item:
- Does the difference give a competitive advantage, or is it only a habit?
- Is it required by law or regulation?
- Is the standard process close enough that a training effort would solve it?
- What would an extension cost over the system's lifetime, including testing at every release?
Items that fail these checks are usually resolved by adopting the standard.
Process redesign
Fit-to-standard is partly a process redesign exercise. S/4HANA changes how several processes work, so some redesign is needed even if the business would rather change nothing. Examples from the data model and functional changes covered earlier:
| Area | ECC behavior | S/4HANA behavior | Redesign effect |
|---|---|---|---|
| Customers and vendors | Separate master records | Business partner as the single master data concept | Roles and number ranges must be planned |
| Finance | Separate general ledger and controlling data | Universal Journal (ACDOCA) as one line-item table | Reconciliation steps may disappear |
| Material numbers | 18 characters | Up to 40 characters | Interfaces and field lengths need checking |
| Credit management | Classic credit management | SAP Credit Management | Process and configuration change |
Some manual reconciliation steps and period-end tasks exist only because ECC kept data in separate places. When the data is in one place, the step can be removed instead of rebuilt.
Examples of redesign decisions
- Reconciliation between finance and controlling. In ECC, teams ran reconciliation reports to align the two ledgers. With the Universal Journal this check is largely unnecessary, so the redesigned process drops it.
- Customer and vendor maintenance. A company that is both customer and vendor can now be one business partner with two roles. The redesign needs a rule for who owns the record and who may change it.
- Custom approval workflows. A custom ABAP workflow may be replaced by a standard flexible workflow. The team accepts a slightly different approval path in exchange for lower maintenance.
Fit-to-standard in each transition path
The method is used in all three paths, but the weight differs.
| Path | Role of fit-to-standard |
|---|---|
| Greenfield | Central. The whole process model is designed from the standard, so workshops cover the full scope. |
| Brownfield | Smaller. Existing processes are kept, so the focus is on what the conversion changes, such as the business partner and simplification items. |
| Selective data transition | Targeted. Redesign applies to the entities or processes that are being changed, while others move as they are. |
In brownfield, the existing configuration carries over. That is its advantage, and it is also a risk, because old habits and old customizing stay in place. Teams that want the benefit of fit-to-standard in a brownfield project can run it as a separate step after the technical conversion, in the form of optimization.
Common errors
- Treating workshops as requirements gathering. If participants arrive with long wish lists, the workshop becomes a fit-gap exercise under a new name. Set the rule that the standard is shown first.
- Missing decision makers. If process owners are absent, differences get recorded as "needed" because nobody present can refuse them.
- Starting without a representative system. Demonstrations with unrecognizable data lose the audience, and the business then falls back on listing old requirements.
- Letting every gap become custom code. This works against the clean core principle, covered later. Extensions should be a deliberate decision with an owner, not a default.
- Ignoring data. A process that fits the standard can still fail if the master data does not meet the new model. Link the workshop outcomes to data migration planning.
- No record of decisions. Without a documented reason for each accepted difference, the same discussion returns during testing.
Checklist for a workshop series
- Confirm the starter system has recognizable data.
- Invite process owners with authority to decide.
- Agree the principle: standard first, differences justified.
- Walk through each end-to-end process in the system.
- Record each outcome (fit, configure, change process, extend) with a reason.
- Review the backlog with the project sponsor and set priorities.
- Pass accepted items into Realize and link them to data migration and testing.
Exercise
During a fit-to-standard workshop, a purchasing manager asks for a custom approval step that exists in the ECC system. The standard process has a configurable approval with a different threshold structure. Name three questions the team should ask before accepting a custom extension, and name the likely outcome if the answers are weak.
Show answer
Possible questions: (1) Is the difference required by law or does it give competitive advantage, or is it only a habit? (2) Could configuring the standard approval or a small process change give an acceptable result? (3) What will the extension cost to maintain, including retesting at every release, and who owns it? If the answers are weak, the team should adopt the standard process, perhaps with configuration and training, and record the decision and reason in the backlog.
Exercise
Why does fit-to-standard matter more in a greenfield project than in a brownfield conversion?
Show answer
In greenfield, the whole process model is built new from the standard, so every process area can be reviewed and redesigned. In brownfield, existing processes and customizing carry over, so the workshops are limited to what the conversion changes, such as the business partner and simplification items.