Sub topic 12
Worker-Time Scaling: Workers, Days, and Output
Assume you can work with fractions, ratios, and one-variable equations. This chapter uses a simplified model: workers have equal productivity, work the same number of hours per day, and do not interfere with one another.
The worker-time model
When each worker contributes at the same rate, the total amount of work depends on:
- the number of workers,
- the number of days,
- the hours worked per day,
- the productivity of each worker.
If the daily hours and individual productivity stay constant, use:
\[ \text{workers} \times \text{days} \propto \text{amount of work} \]
The symbol \(\propto\) means “is proportional to.” If the amount of work stays the same, worker-days stay the same:
\[ W1D1=W2D2 \]
Here, \(W\) is the number of workers and \(D\) is the number of days.
For example, 6 workers completing a job in 10 days represent:
\[ 6(10)=60 \]
worker-days. If 12 equally productive workers do the same job, the time is:
\[ 12D=60 \]
so \(D=5\) days.
Scaling output
If the time and number of workers change, compare the total worker-days:
\[ \frac{\text{new work}}{\text{old work}} = \frac{W2D2}{W1D1} \]
Suppose 8 workers work for 6 days. A new project uses 12 workers for 10 days, under the same conditions. Its output is:
\[ \frac{12\cdot10}{8\cdot6} = \frac{120}{48} = 2.5 \]
The new project represents 2.5 times as much work.
| Situation | Workers | Days | Worker-days |
|---|---|---|---|
| Original project | 8 | 6 | 48 |
| New project | 12 | 10 | 120 |
If workers have different productivity, worker count alone is not enough. A worker who completes twice as much per day as another should count as two equal-productivity workers.
A worked example
A crew of 15 workers can pave a road in 8 days. After 3 days, 5 workers leave. How many additional days will the remaining workers need?
First find the total work:
\[ 15(8)=120 \]
The crew completes 3 days of work:
\[ 15(3)=45 \]
The unfinished work is:
\[ 120-45=75 \]
There are now 10 workers, so let \(d\) be the additional number of days:
\[ 10d=75 \]
Thus,
\[ d=7.5 \]
The remaining workers need 7.5 additional days.
A common mistake is to apply \(15(8)=10d\) immediately. That treats the entire job as unfinished and ignores the work already completed.
def remaining_days(workers, total_days, days_completed, workers_left):
total_work = workers * total_days
completed_work = workers * days_completed
unfinished_work = total_work - completed_work
return unfinished_work / workers_left
print(remaining_days(15, 8, 3, 10)) # 7.5When the simple model fails
The worker-day equation needs adjustment when conditions change:
- Workers have different rates.
- Workers work different numbers of hours per day.
- The project has a fixed setup time.
- Adding workers causes communication or space limits.
- The workers do not work simultaneously.
If daily hours differ, use worker-hours instead:
\[ \text{workers}\times\text{hours per day}\times\text{days} \]
For instance, 4 workers working 6 hours per day for 5 days produce:
\[ 4\cdot6\cdot5=120 \]
worker-hours.
GRE strategy and checks
For a time-pressure problem:
- Decide whether the total work is fixed.
- If it is fixed and workers are equally productive, set \(W1D1=W2D2\).
- If some work is already complete, subtract completed worker-days first.
- Check the direction of the answer. More workers should mean fewer days for the same job.
- Keep the units consistent.
Exercise
Ten workers finish a job in 12 days. After working for 4 days, 2 workers leave. How many more days will the remaining workers need?
Show answer
Total work is 10(12) = 120 worker-days. Work completed is 10(4) = 40 worker-days, leaving 80. The remaining 8 workers need 80/8 = 10 more days.