Sub topic 11
Staggered Starts and Partial Jobs
The Working Model
Assume you can add and subtract fractions, solve a linear equation, and use basic ratios. In a work problem, a rate is the fraction of one job completed per unit of time. If a worker finishes a job in \(t\) hours, the worker's rate is
\[ \text{rate}=\frac{1}{t}\text{ job per hour}. \]
A partial job is the amount completed during a specified time:
\[ \text{work completed}=\text{rate}\times\text{time}. \]
For several workers, calculate each person's contribution separately. Add the contributions to find the total completed work.
Staggered Starts
A staggered-start problem has workers who begin at different times. The key is to divide the timeline into periods during which the group of active workers stays the same.
Suppose Worker A can finish a job alone in 6 hours. Worker B can finish it alone in 12 hours. A starts first, and B joins after 2 hours.
- A's rate is \(1/6\) job per hour.
- B's rate is \(1/12\) job per hour.
- During the first 2 hours, A completes \(2(1/6)=1/3\) of the job.
- The remaining work is \(1-1/3=2/3\).
- Once B joins, their combined rate is \(1/6+1/12=1/4\).
The time needed for the remaining work is
\[ \frac{2/3}{1/4}=\frac{2}{3}\times4=\frac{8}{3} \]
hours. Therefore, the total time from A's start is
\[ 2+\frac{8}{3}=\frac{14}{3}\text{ hours}. \]
The phrase “how long does it take them after B joins?” would instead ask for only \(8/3\) hours. Always identify the time reference in the question.
Partial Jobs and Early Departure
The same method works when a worker leaves before the job ends. For example, A works alone for 3 hours, then A and B work together for \(x\) hours. If A's rate is \(1/8\) and B's rate is \(1/12\), then
\[ 3\left(\frac18\right)+x\left(\frac18+\frac1{12}\right)=1. \]
The first term is A's initial contribution. The second term is the contribution of both workers during the overlapping period.
Simplify:
\[ \frac38+x\left(\frac{5}{24}\right)=1 \]
\[ x\left(\frac{5}{24}\right)=\frac58 \]
\[ x=3. \]
The workers need 3 hours together after A's first 3 hours.
from fractions import Fraction
def remaining_time(initial_rate, initial_hours, combined_rate):
completed = initial_rate * initial_hours
remaining = 1 - completed
return remaining / combined_rate
a_rate = Fraction(1, 8)
b_rate = Fraction(1, 12)
together_rate = a_rate + b_rate
print(remaining_time(a_rate, 3, together_rate)) # 3A Timeline Prevents Errors
Draw a quick timeline when the start or stop times differ.
This separates the periods and makes it harder to use the wrong rate for the wrong amount of time.
GRE Strategy and Checks
For a fast solution:
- Convert each completion time into a rate.
- Break the situation into time periods.
- Compute the work completed in each period.
- Set the total completed work equal to 1.
- Check that the answer is positive and that combined workers finish faster than either worker alone.
If one worker works alone before another joins, the total time must be greater than the time needed if both had started together. This provides a useful estimate check.
Exercise
Worker A finishes a job in 4 hours. A works alone for 1 hour, then Worker B joins. Together, they finish the remaining work in 1 hour. What is B's completion time when working alone?
Show answer
A completes 1/4 of the job alone, so the remaining 3/4 is completed in 1 hour at a combined rate of 3/4 job per hour. B's rate is 3/4 - 1/4 = 1/2 job per hour, so B alone takes 2 hours.