This chapter covers problems where the number of workers, the number of days, and the amount of output all change together. These problems build on the work-rate idea from earlier chapters. You do not need new formulas, only a careful way to scale a rate.
Prerequisites
This chapter assumes you can do the following:
- Work with fractions, ratios, and proportions.
- Solve a linear equation in one variable.
- Treat work as a rate, meaning job per unit time, and add rates for combined work.
If "rate = job ÷ time" is unfamiliar, review the chapters on work as a rate and on combining workers first.
The core idea: one worker, one unit of time
Worker-time scaling problems usually give you a group of identical workers. They say the group does some amount of output in some amount of time. They then change one or more quantities and ask for the result.
The key step is to find the unit rate. This is the output that one worker produces in one unit of time, such as one worker-day or one worker-hour. A worker-day is the work of one worker for one day. Once you know the unit rate, every other case is multiplication or division.
The general relationship is:
output = (unit rate) × (number of workers) × (time)
This is the same pattern as distance = rate × time. The group's rate is the unit rate times the number of workers.
Assumptions behind the model
The model holds only when these conditions are true:
- All workers (or machines) work at the same constant rate.
- Workers do not get in each other's way, so doubling the workers really does double the rate.
- The job is divisible, so any worker can contribute to any part of it.
GRE problems state or imply these conditions. If a problem says the workers have different speeds, you cannot use a single unit rate. Go back to adding individual rates.
Worked example 1: find the unit rate first
Problem. 5 machines produce 400 widgets in 4 hours. At the same rate per machine, how many widgets do 8 machines produce in 6 hours?
- Find the output per machine-hour. The 5 machines run for 4 hours, which is 5 × 4 = 20 machine-hours. They make 400 widgets, so the unit rate is 400 ÷ 20 = 20 widgets per machine-hour.
- Apply it to the new case. 8 machines for 6 hours is 8 × 6 = 48 machine-hours.
- Output = 48 × 20 = 960 widgets.
The code below does the same calculation. It works for any problem of this type.
def scaled_output(workers_1, time_1, output_1, workers_2, time_2):
unit_rate = output_1 / (workers_1 * time_1)
return unit_rate * workers_2 * time_2
print(scaled_output(5, 4, 400, 8, 6)) # 960.0Worked example 2: solve for time
Problem. 6 workers paint a fence in 10 days. How many days would 15 workers need?
The job is one fence, and the output does not change. So the total worker-days stay the same:
- Total work = 6 × 10 = 60 worker-days.
- With 15 workers, days = 60 ÷ 15 = 4.
Here, more workers means fewer days. This is an inverse proportion, where one quantity goes up as the other goes down and their product stays fixed.
def days_needed(workers_1, days_1, workers_2):
total_worker_days = workers_1 * days_1
return total_worker_days / workers_2
print(days_needed(6, 10, 15)) # 4.0Direct and inverse relationships
Most errors in this chapter come from mixing up which quantities move together. Use this table to decide.
| Quantity held fixed | Relationship between workers and time | Example |
|---|---|---|
| Output (same job) | Inverse: workers × time is constant | Double the workers, half the time |
| Time | Direct: output grows with workers | Double the workers, double the output |
| Workers | Direct: output grows with time | Double the time, double the output |
Before you calculate, ask what stays the same. If the job is the same size, use the inverse relationship. If the job size changes, use the full formula with the unit rate.
The scaling diagram
The decision process looks like this.
Worked example 3: both job size and workers change
Problem. 4 workers build 3 walls in 9 days. How many days do 6 workers need to build 5 walls?
- Worker-days used: 4 × 9 = 36 worker-days for 3 walls.
- Unit rate for the job: 36 ÷ 3 = 12 worker-days per wall.
- Five walls need 5 × 12 = 60 worker-days.
- With 6 workers: 60 ÷ 6 = 10 days.
Notice that the "cost" of one wall is 12 worker-days. This is a handy way to reframe the problem. Instead of rate in walls per worker-day, you use its reciprocal, worker-days per wall. Use whichever is easier with the given numbers.
def days_for_new_job(workers_1, days_1, jobs_1, workers_2, jobs_2):
worker_days_per_job = workers_1 * days_1 / jobs_1
return jobs_2 * worker_days_per_job / workers_2
print(days_for_new_job(4, 9, 3, 6, 5)) # 10.0Worked example 4: workers join or leave partway
Sometimes the crew changes in the middle of a job. Break the job into stages and add the worker-days.
Problem. 8 workers can finish a job in 12 days. They work together for 4 days, and then 4 workers leave. How many more days do the remaining workers need?
- Total work: 8 × 12 = 96 worker-days.
- Work done in the first 4 days: 8 × 4 = 32 worker-days.
- Work left: 96 − 32 = 64 worker-days.
- Remaining crew is 4 workers: 64 ÷ 4 = 16 more days.
The job takes 4 + 16 = 20 days in total. A sanity check: the full crew would have needed 12 days. Losing half the crew for most of the job should add a lot of time, and 20 is plausible.
def remaining_days(workers, planned_days, days_worked, workers_left):
total = workers * planned_days
done = workers * days_worked
return (total - done) / workers_left
print(remaining_days(8, 12, 4, 4)) # 16.0Worked example 5: output per worker in a different unit
Some problems give the output in one unit and the time in another. Convert first, as in the units chapter.
Problem. 3 machines make 540 parts in 2 hours. How many parts do 5 machines make in 90 minutes?
- Convert 90 minutes to 1.5 hours.
- Unit rate: 540 ÷ (3 × 2) = 90 parts per machine-hour.
- New case: 90 × 5 × 1.5 = 675 parts.
If you skipped the conversion and used 90 as hours, you would get 40,500. That answer is far too large, since 5 machines for even 2 hours would give only 900 parts. A quick bound like this catches unit errors.
Proportion shortcut
When only some quantities change, a proportion can be faster than finding the unit rate. Write each quantity as a ratio of new to old and multiply.
For worked example 1, the output scales by:
- workers: 8/5
- time: 6/4
New output = 400 × (8/5) × (6/4) = 400 × 1.6 × 1.5 = 960.
For inverse quantities, flip the ratio. If the job is fixed and workers change from 6 to 15, then time scales by 6/15 (old workers over new workers). So 10 × 6/15 = 4 days.
from fractions import Fraction
def scale(old_value, *ratios):
result = Fraction(old_value)
for r in ratios:
result *= r
return result
print(scale(400, Fraction(8, 5), Fraction(6, 4))) # 960
print(scale(10, Fraction(6, 15))) # 4Common errors
- Treating an inverse relationship as direct. If 6 workers need 10 days, 15 workers do not need 25 days. More workers means less time for the same job.
- Forgetting that the job size changed. If the second case has more output, the total worker-time must grow too.
- Mixing units. Hours and minutes, or days and weeks, in the same calculation give wrong answers. Convert first.
- Assuming a sequence. Worker-time scaling treats all workers as working at the same time. If a problem says one group works first and another works afterward, handle the stages separately, as in worked example 4.
- Using a rounded unit rate. If the unit rate is 100 ÷ 3, keep it as a fraction. Rounding early shifts the final answer.
- Counting workers instead of rates when workers differ. Unit rates apply only to identical workers. For different speeds, add the individual rates.
Edge cases and checks
Three checks take a few seconds and catch most mistakes.
- Direction check. If workers increase and the job is fixed, your answer for time must be smaller than the original. If workers increase and time is fixed, output must be larger.
- Boundary check. Imagine doubling the workers. Does your answer double (or halve) as expected? If you computed 960 widgets for 8 machines in 6 hours, then 16 machines in 6 hours should give 1,920.
- Whole-number check. Some problems ask for a count of workers. A fractional answer such as 3.5 workers means you either made an error or the question expects you to round up, because you cannot hire half a worker. Read the question to see which applies.
On the GRE, a Quantitative Comparison question may ask you to compare two quantities such as "days needed by 12 workers" and "days needed by 10 workers with the same job." You do not need exact values. The inverse relationship tells you the 12-worker crew finishes sooner, so you can answer from the direction check alone.
Summary
- Convert the given case to worker-time units, such as worker-days.
- If the job size is fixed, worker-time is fixed. Workers and time are inversely related.
- If the job size changes, find the unit rate and multiply by the new workers and the new time.
- If the crew changes midway, split the job into stages.
- Always check the direction, convert units, and test with a simple boundary case.
Exercise
12 workers can lay 2,400 bricks in 5 days. At the same rate per worker, how many days would 9 workers need to lay 3,600 bricks?
Show answer
Total worker-days for the given case: 12 × 5 = 60 worker-days for 2,400 bricks, so the unit rate is 2,400 ÷ 60 = 40 bricks per worker-day. The new job needs 3,600 ÷ 40 = 90 worker-days. With 9 workers: 90 ÷ 9 = 10 days.
Exercise
A crew of 10 workers is scheduled to finish a job in 15 days. After 6 days, 5 more workers join the crew. How many days in total does the job take?
Show answer
Total work: 10 × 15 = 150 worker-days. After 6 days, the crew has done 10 × 6 = 60 worker-days, so 90 worker-days remain. The crew is now 15 workers, so the rest takes 90 ÷ 15 = 6 days. The total is 6 + 6 = 12 days.
Exercise
Quantity A: the number of days 14 workers need to complete a job. Quantity B: the number of days 16 workers need to complete the same job. All workers have the same rate. Which quantity is greater, or are they equal?
Show answer
Quantity A is greater. For a fixed job, workers × days is constant, so more workers means fewer days. The 14-worker crew takes longer than the 16-worker crew.