Sub topic 9
Combining Workers: Adding Rates
What this chapter assumes
You should already be comfortable with fractions, solving one-variable linear equations, and the idea from the previous chapter that a job can be treated as one whole unit completed at some rate. Here you will use that idea to solve problems where two or more workers, machines, or pipes operate at the same time.
The core idea: rates add, times do not
A work rate is the fraction of a job finished in one unit of time. If a worker finishes a job alone in 6 hours, the rate is 1/6 job per hour. The relationship is the same as distance = rate × time:
- work done = rate × time
- time = work ÷ rate
- rate = work ÷ time
When workers operate at the same time and do not interfere with each other, their rates add:
combined rate = rate₁ + rate₂ + rate₃ + ...
The combined time is then 1 divided by the combined rate, when the job is one whole unit.
Times do not add. If Ana takes 6 hours and Ben takes 12 hours, the team does not take 18 hours or 9 hours. Working together, they must take less time than the faster worker would alone, so the answer must be less than 6 hours. This is the first check to run on every combined-work problem.
Worked example: two workers
Ana finishes a job alone in 6 hours. Ben finishes the same job alone in 12 hours. How long do they take together?
- Ana's rate is 1/6 job per hour.
- Ben's rate is 1/12 job per hour.
- Combined rate: 1/6 + 1/12 = 2/12 + 1/12 = 3/12 = 1/4 job per hour.
- Time = 1 ÷ (1/4) = 4 hours.
Check: 4 is less than 6, the faster worker's time. In 4 hours Ana does 4/6 = 2/3 of the job and Ben does 4/12 = 1/3, and 2/3 + 1/3 = 1. The check passes.
from fractions import Fraction
def combined_time(*times):
combined_rate = sum(Fraction(1, t) for t in times)
return 1 / combined_rate
print(combined_time(6, 12)) # 4The function uses Fraction so the arithmetic stays exact. With ordinary floating-point numbers, 1/6 + 1/12 would carry rounding error, and you would see a value near 4 rather than exactly 4. On the GRE you work by hand, so the same rule applies: keep fractions as fractions until the last step.
The shortcut for two workers
For two workers with individual times a and b, adding the rates and inverting gives:
combined time = (a × b) ÷ (a + b)
For Ana and Ben: (6 × 12) ÷ (6 + 12) = 72 ÷ 18 = 4 hours.
This is the "product over sum" formula. It is fast, but it applies only to two workers. For three or more, add the rates directly. The formula also hides the logic, so if you forget it mid-problem, rebuild it from rates.
def two_worker_time(a, b):
return (a * b) / (a + b)
print(two_worker_time(6, 12)) # 4.0When the combined time is given
Many GRE problems run the other direction. You know the combined time and one worker's time, and you must find the other worker's time. Subtract the known rate from the combined rate.
Example: Ana and Ben together finish a job in 4 hours. Ana alone takes 6 hours. How long does Ben take alone?
- Combined rate: 1/4.
- Ana's rate: 1/6.
- Ben's rate: 1/4 − 1/6 = 3/12 − 2/12 = 1/12.
- Ben's time: 12 hours.
Always convert back from rate to time at the end. A frequent error is to answer "1/12" when the question asks for hours.
Using a variable for an unknown time
Some problems state a relationship between the workers' times instead of giving numbers. Suppose one pump takes 3 hours longer than another to fill a pool, and together they take 2 hours. Let the faster pump take t hours alone. Then:
1/t + 1/(t + 3) = 1/2
Multiply through by 2t(t + 3):
2(t + 3) + 2t = t(t + 3)
4t + 6 = t² + 3t
t² − t − 6 = 0
(t − 3)(t + 2) = 0
t = 3 (reject t = −2, since time cannot be negative). So the faster pump takes 3 hours and the slower pump takes 6 hours.
Check: 1/3 + 1/6 = 1/2. The combined time is 2 hours, as stated.
Rejecting a negative or otherwise impossible root is a routine step in these quadratic setups. State it, because the GRE often places the rejected value among the wrong answer choices.
Workers with different jobs-per-time data
Rates need not be given as "alone, the job takes N hours." A problem may say a machine makes 40 widgets per hour and another makes 25 per hour. Then the rates are already in units of output per hour, and they add directly: 65 widgets per hour. To make 520 widgets:
time = 520 ÷ 65 = 8 hours.
In this form the job is not "1 whole." Use whatever unit of work the problem gives, and keep it the same for every worker. The rule is that all rates must measure the same work in the same time unit.
Keeping time units consistent
If one worker is described in minutes and another in hours, convert before adding. Ana takes 2 hours and Ben takes 90 minutes:
- Ana: 1/2 job per hour.
- Ben: 90 minutes = 1.5 hours, so 1/1.5 = 2/3 job per hour.
- Combined: 1/2 + 2/3 = 3/6 + 4/6 = 7/6 job per hour.
- Time: 6/7 hour, about 51.4 minutes.
Adding 1/2 and 1/90 without converting gives a meaningless number. The question also decides the unit of the answer. If it asks for minutes, convert at the end.
Three or more workers
The method extends without change. Workers who take 4, 6, and 12 hours:
1/4 + 1/6 + 1/12 = 3/12 + 2/12 + 1/12 = 6/12 = 1/2 job per hour
Time = 2 hours. A common denominator, here 12, keeps the work clean. Finding the least common multiple of the three times first is usually the fastest approach.
A useful trick is to choose a convenient job size. If the times are 4, 6, and 12, let the job be 12 units. Then the workers produce 3, 2, and 1 units per hour, a total of 6 units per hour, so the 12-unit job takes 2 hours. The answer is the same because the job size cancels. Use the least common multiple of the individual times and you avoid fractions entirely.
from math import lcm
def combined_time_units(*times):
job = lcm(*times)
units_per_hour = sum(job // t for t in times)
return job / units_per_hour
print(combined_time_units(4, 6, 12)) # 2.0How the rates fit together
The diagram shows the flow of reasoning for a standard combined-work problem.
Common errors
| Error | Why it fails | Correct approach |
|---|---|---|
| Adding times (6 + 12 = 18) | Times do not add. Rates do. | Add 1/6 + 1/12 |
| Averaging times (9 hours) | The team must beat the fastest worker | Combine rates |
| Forgetting to invert | 1/4 is a rate, not a time | Time = 1 ÷ rate |
| Mixing minutes and hours | Rates are in different units | Convert first |
| Using product over sum for 3 workers | The formula holds for two workers only | Add all rates |
| Accepting a negative root | Time cannot be negative | Reject it |
Assumptions behind the model
Adding rates assumes that each worker keeps a constant rate and that workers do not slow each other down. The GRE states or implies these conditions in nearly every problem, with phrases such as "working at constant rates" or "working independently." If a problem describes workers who get in each other's way, or a rate that changes partway through, you cannot simply add. Split the problem into stages and handle each stage with its own rates. Later chapters cover staggered starts and partial jobs.
Quick estimation checks
Before doing exact arithmetic, bound the answer:
- The combined time is less than the fastest individual time.
- If two workers have the same time t, the combined time is exactly t/2.
- If one worker is much slower than the other, the combined time is just under the faster worker's time. With times 6 and 60, expect a little under 6 hours. The exact value is 360 ÷ 66, about 5.45 hours.
These checks eliminate wrong answer choices without full computation, which saves time on the exam.
Exercise
Machine A fills an order in 10 hours. Machine B fills the same order in 15 hours. Working together at constant rates, how many hours do they need?
Show answer
Rates: 1/10 + 1/15 = 3/30 + 2/30 = 5/30 = 1/6 job per hour. Time = 6 hours. Check with product over sum: (10 × 15) ÷ (10 + 15) = 150 ÷ 25 = 6. The result is below 10, the faster machine's time.
Exercise
Together, Priya and Sam paint a fence in 8 hours. Priya alone would take 20 hours. How long would Sam take alone?
Show answer
Combined rate is 1/8 and Priya's rate is 1/20. Sam's rate is 1/8 − 1/20 = 5/40 − 2/40 = 3/40 job per hour. Sam's time is 40/3 hours, or 13 1/3 hours. The result is greater than 8, as it must be, since Sam is slower than the team.
Exercise
Three printers take 3, 4, and 6 hours to print a batch alone. How many minutes do they take together?
Show answer
Use a job of 12 units, the least common multiple. The printers make 4, 3, and 2 units per hour, a total of 9 units per hour. Time = 12 ÷ 9 = 4/3 hours, which is 80 minutes.
Exercise
One pipe takes 2 hours longer than another to fill a tank alone. Together they fill it in 1.5 hours. How long does the faster pipe take alone?
Show answer
Let the faster pipe take t hours. Then 1/t + 1/(t + 2) = 2/3. Multiply by 3t(t + 2): 3(t + 2) + 3t = 2t(t + 2), so 6t + 6 = 2t² + 4t, so t² − t − 3 = 0 after dividing by 2 and rearranging: 2t² − 2t − 6 = 0, giving t² − t − 3 = 0. This has roots t = (1 ± √13)/2, so t ≈ 2.30 hours. The faster pipe takes about 2.3 hours, and the slower takes about 4.3 hours. Check: 1/2.30 + 1/4.30 ≈ 0.435 + 0.233 = 0.668, which is close to 2/3.