Sub topic 11
Planning around the deadlines
This chapter assumes you know the ECC mainstream and extended maintenance dates from the previous chapter. It also assumes you know the three migration approaches in outline. Here we turn those dates into a project plan.
Start from the dates
SAP's published position for ECC 6.0 is that mainstream maintenance ends on 31 December 2027. Extended maintenance has been offered as a paid option until 31 December 2030. SAP has also announced transition options that run beyond that, tied to its private cloud offering. Dates and conditions have changed before, so confirm them at the source before you commit a budget:
- SAP Note 1648480, which covers maintenance for SAP Business Suite 7.
- SAP's Product Availability Matrix.
- Your SAP account team, in writing.
Work backward from the deadline
Do not ask "when should we start?" Ask "when must we go live, and what has to be finished before that?" Subtract each phase's duration from the target date.
A typical conversion of a mid-sized landscape takes 12 to 24 months from assessment to go-live. A new implementation takes longer. Your own estimate must come from the readiness results, not from a rule of thumb.
Build in constraints and buffer
Several fixed points reduce the time you really have:
- Year-end close. Finance teams usually refuse a cutover near it.
- Other projects that compete for the same testers and ABAP developers.
- Dependencies on partners, such as add-on vendors who must certify their products for S/4HANA.
- Rehearsals. Plan at least two full cutover runs, because the first one almost always exposes problems.
Add buffer between your target go-live and the deadline. A project that goes live in the last month has no room for a failed cutover.
Options when you cannot make the date
| Option | What you get | Main cost or risk |
|---|---|---|
| Paid extended maintenance from SAP | Continued SAP support and fixes | Extra fee, a fixed end date |
| SAP transition options | Longer ECC support linked to a cloud contract | Contract commitment, so read the terms |
| Third-party support | Lower support fees, support from a non-SAP provider | No SAP fixes or legal updates, and contract and licence questions |
| Run unsupported | No support spend | Security and compliance exposure |
Third-party support needs particular care. The provider can fix problems and advise, but it cannot deliver SAP code corrections or legal changes such as tax updates. Check how your SAP licence and any future S/4HANA licence terms treat this choice.
Keep the plan alive
Review the plan on a fixed schedule, for example every quarter. Re-check SAP's published dates, the readiness results, and the status of your add-ons. If the custom code analysis finds more work than expected, move the start date earlier instead of shrinking the testing phase.
Exercise
Your target is to run on S/4HANA before 31 December 2027, the end of ECC mainstream maintenance. The conversion needs 18 months of work, and you want a 3-month buffer. Which date is the latest start for the project, and what should you check before relying on the 2027 date?
Show answer
Work backward 21 months (18 plus 3) from 31 December 2027, which gives 31 March 2026 as the latest start. That date is already past if today is after it, so the realistic options are a shorter scope or a bridge such as extended maintenance. Before relying on the 2027 date, check SAP Note 1648480, the Product Availability Matrix, and your SAP account team for the current published dates and conditions.