Sub topic 15
Choosing an approach and building a roadmap
This chapter assumes you know the three approaches (new implementation, system conversion, selective data transition), the readiness tools, and the ECC maintenance dates covered earlier. Here you combine them into a decision and a plan.
Start with the constraints
Pick an approach by answering a few questions about your landscape. Do not start from a preferred technique.
- How much of your current process design do you want to keep?
- How much historical data must be available in the new system?
- How much custom code do you have, and how much is still used?
- Which deadline binds you: the ECC maintenance end date or a business event such as a merger?
- Which deployment option fits your governance and hosting needs?
Compare the approaches against those constraints
| Approach | Fits when | Main risk |
|---|---|---|
| New implementation | Processes are heavily customized or outdated, and you want to redesign them | Highest effort, because you must migrate master data and open items and retest every process |
| System conversion | Processes are largely sound, you need full history, and you want one project | Technical debt carries over, and the downtime window must be planned |
| Selective data transition | You need to move only some company codes, or merge several systems | Needs specialist tooling and services, and has the most complex scoping |
System conversion is the usual starting assumption for customers with stable processes. It keeps all history and runs as a single technical project. New implementation is common when the ECC system has grown messy. Selective transition suits carve-outs and consolidations, and rarely suits a plain one-to-one move.
Treat the diagram as a first filter. The readiness results can overturn it. For example, a Readiness Check may show that many simplification items affect you, or that most of your custom code is unused.
Anchor the timeline to the deadlines
SAP's published position is that mainstream maintenance for ECC 6.0 ends at the end of 2027, with optional extended maintenance to the end of 2030. Extended maintenance usually costs extra. Check the current dates and conditions on the SAP Support Portal and in SAP's maintenance announcements before you commit. Dates and terms have been revised before.
Work backward from the date you choose. Include the time to reach a stable production system, not only the go-live date. Third-party support is an option for bridging, but it does not provide SAP updates, so weigh it as a delay, not a replacement for the project.
Build the roadmap
A basic roadmap has five phases:
- Discover. Run the Simplification Item Catalog check and the Readiness Check, and list custom code with usage data.
- Decide. Choose the approach, the deployment option, and the target release. Use Maintenance Planner to confirm the software stack.
- Prepare. Clean up unused code and old data, and convert customers and vendors to Business Partner.
- Execute. Run sandbox conversions, then test cycles, then the cutover rehearsal.
- Stabilize. Handle hypercare, then roll out Fiori apps to users.
Plan at least one full rehearsal of the production cutover. It gives you a measured downtime figure to use in the plan.
Exercise
A company has stable, well-documented processes, needs ten years of financial history in the new system, and has one ECC system with moderate custom code. Which approach is the default choice, and what result could change that choice?
Show answer
System conversion is the default, because it keeps processes and full history in one project. The Readiness Check or custom code analysis could change it. For example, a large number of affected simplification items, or mostly obsolete code and processes, would point toward new implementation.