Track Progress Against a Baseline
Assume you can read a schedule with tasks, durations, dependencies, and working dates. You also know how a forward pass calculates the earliest dates. This chapter adds a baseline and current progress so you can see whether the project is following the approved plan.
What a baseline means
A baseline is a saved copy of the approved schedule. It records the planned start date, planned finish date, duration, and sometimes the planned cost for each task. After work begins, the baseline stays unchanged.
The current schedule records what actually happened and what you now expect to happen. Comparing the two answers questions such as:
- Did a task start later than planned?
- Is the task taking longer than expected?
- Is the final delivery date moving?
- Which unfinished tasks need attention?
A baseline is useful only if it is captured after the schedule has been reviewed and approved. Saving a new baseline every time the project slips hides the original variance.
Compare planned and current dates
Consider this small schedule:
| Task | Baseline start | Baseline finish | Actual or forecast finish | Progress |
|---|---|---|---|---|
| Design | Day 0 | Day 5 | Day 5 | 100% |
| Build | Day 5 | Day 15 | Day 17 | 50% |
| Test | Day 15 | Day 20 | Day 22 | 0% |
Design finished on time. Build is still active and now has a forecast finish two days later than its baseline finish. Because Test depends on Build, Test also moves two days later.
Progress should describe completed work, not just elapsed time. A task that has consumed half its planned time is not necessarily 50% complete. For example, testing may be almost finished after many test cases pass, or it may have made little progress despite several days of work. Define what “complete” means before assigning a percentage.
A useful progress record includes:
- The status date.
- Actual start and finish dates.
- Completed work or an evidence-based percentage.
- Remaining duration.
- A forecast finish date.
- A reason for any variance.
Show the comparison
A Gantt chart can place the baseline behind the current schedule. Use a muted color for the baseline and a strong color for completed or forecast work.
Many Gantt tools provide baseline bars automatically. A text-based Mermaid Gantt chart is useful for communicating a schedule, but support for a separate baseline and percentage-complete overlay varies by renderer. For a precise comparison, use a project scheduling tool or draw both layers with code.
import matplotlib.pyplot as plt
from matplotlib.patches import Patch
tasks = [
{"name": "Design", "baseline_start": 0, "baseline_days": 5,
"current_start": 0, "forecast_days": 5, "progress": 1.0},
{"name": "Build", "baseline_start": 5, "baseline_days": 10,
"current_start": 5, "forecast_days": 12, "progress": 0.5},
{"name": "Test", "baseline_start": 15, "baseline_days": 5,
"current_start": None, "forecast_days": 5, "progress": 0.0},
]
fig, ax = plt.subplots(figsize=(8, 3.5))
for row, task in enumerate(tasks):
ax.barh(row, task["baseline_days"], left=task["baseline_start"],
height=0.25, color="lightgray")
if task["current_start"] is not None:
completed = task["forecast_days"] * task["progress"]
remaining = task["forecast_days"] - completed
ax.barh(row + 0.15, completed, left=task["current_start"],
height=0.25, color="steelblue")
ax.barh(row + 0.15, remaining,
left=task["current_start"] + completed,
height=0.25, color="skyblue")
ax.set_yticks(range(len(tasks)))
ax.set_yticklabels([task["name"] for task in tasks])
ax.invert_yaxis()
ax.set_xlabel("Project day")
ax.legend(handles=[
Patch(color="lightgray", label="Baseline"),
Patch(color="steelblue", label="Completed"),
Patch(color="skyblue", label="Remaining forecast"),
])
plt.tight_layout()
plt.show()The gray bars show the approved plan. The dark blue portion shows completed work. The light blue portion shows the current forecast remaining. Build extends beyond its baseline, so its variance deserves investigation.
Interpret variance and rebaseline carefully
A schedule variance is the difference between a current date and its baseline date. A positive finish variance means the forecast is later than planned. Trace that difference through dependencies rather than correcting dates by hand.
Common causes include:
- A predecessor finished late.
- The original duration was too optimistic.
- A resource became unavailable.
- Scope changed.
- A dependency was missing or incorrectly linked.
If the scope genuinely changes, get approval before creating a new baseline. Keep the original baseline for historical comparison, and label the new one with its approval date. Do not move unfinished work to make the chart appear on track.
Exercise
Build was planned for Day 5 through Day 15, but its current forecast is Day 17. Test depends on Build and was planned to finish on Day 20. What is Test's forecast finish if its duration does not change?
Show answer
Day 22. Build finishes two days late, so the finish-to-start dependency moves Test two days later.