Sub topic 2
Estimate Task Durations
Assume you know basic project terms such as task, deadline, and deliverable. You should also be comfortable reading calendar dates. A work breakdown structure from the previous planning step gives you the tasks whose durations you need to estimate.
A task duration is the calendar or working time from its start to its finish. It is different from effort, which is the amount of labor required. A task might require 16 hours of effort but take four working days when one person can spend only four hours per day on it.
Choose a consistent unit
Use days or hours consistently within one schedule. For project-level planning, working days are often easier to read. State what a day means.
For example, this schedule assumes:
- One working day contains eight working hours.
- Work happens Monday through Friday.
- Holidays are excluded from working time.
- A task's duration includes review and rework that are part of that task.
- Tasks do not start before their predecessors finish.
The estimate should describe the task's scope. “Build checkout” is too broad if it includes design, implementation, testing, and deployment. Split it into schedulable tasks such as “Implement checkout form” and “Test checkout form.” Smaller tasks usually produce more reliable estimates because their assumptions are easier to inspect.
Estimate with evidence
Start with evidence from similar completed work. If a previous checkout form took three working days, use that result as a starting point. Adjust it for differences in scope, technology, team experience, and uncertainty.
When you lack historical data, ask the person doing the work to estimate the task. Record the assumptions alongside the number. An estimate without assumptions is difficult to challenge or improve.
A three-point estimate makes uncertainty visible:
- Optimistic: the task goes unusually smoothly.
- Most likely: normal conditions apply.
- Pessimistic: known risks occur, but the task remains feasible.
A common weighted estimate is the PERT estimate:
\[ E = \frac{O + 4M + P}{6} \]
Here, \(O\) is optimistic duration, \(M\) is most likely duration, and \(P\) is pessimistic duration. The most likely value receives four times the weight of either extreme.
| Task | Optimistic | Most likely | Pessimistic | PERT estimate |
|---|---|---|---|---|
| Implement checkout form | 2 days | 4 days | 8 days | 4.33 days |
| Test checkout form | 1 day | 2 days | 4 days | 2.17 days |
| Prepare launch notes | 1 day | 2 days | 3 days | 2 days |
Round estimates according to the schedule's precision. For a high-level plan, 4.33 days might become five working days. Do not present false precision when the inputs are rough.
tasks = {
"Implement checkout form": (2, 4, 8),
"Test checkout form": (1, 2, 4),
"Prepare launch notes": (1, 2, 3),
}
for name, (optimistic, likely, pessimistic) in tasks.items():
estimate = (optimistic + 4 * likely + pessimistic) / 6
print(f"{name}: {estimate:.2f} working days")Separate duration from uncertainty
Do not automatically hide every risk inside a longer task duration. Keep the normal task duration realistic, then record major risks separately. This lets you see whether the schedule is late because the work takes longer than expected or because an unexpected event occurred.
A contingency buffer is extra time reserved for uncertainty. Use it carefully. A large buffer on every task can conceal poor estimates and make dependencies harder to understand. You can instead place a shared buffer after a group of related tasks when the project method supports it.
Review estimates before scheduling
Check each estimate with these questions:
- Does the task have a clear result?
- Does the duration use working time or elapsed time?
- Does the estimate include reviews, testing, and handoffs?
- Is the assigned person available during the period?
- Are external approvals or materials included?
- Is the task small enough to estimate with reasonable confidence?
The output of this step is a duration and a set of assumptions for every schedulable task. Later, dependencies and working calendars will turn those durations into start and finish dates.
Exercise
A task has optimistic, most likely, and pessimistic estimates of 2, 5, and 11 working days. What is its PERT estimate, and why should you record the assumptions?
Show answer
The PERT estimate is (2 + 4 × 5 + 11) ÷ 6 = 5.5 working days. Recording assumptions explains what the estimate includes and gives the team something concrete to revise when scope or conditions change.