Sub topic 3
Link Tasks with Dependencies
Assume you know basic project terms such as task, deliverable, and deadline. You should also be comfortable reading dates on a calendar. This chapter uses a small website project to show how tasks constrain one another.
A dependency is a relationship that determines when one task can start or finish relative to another task. The earlier task is the predecessor. The later task is the successor. For example, developers cannot begin frontend implementation until the approved mockups are available.
Dependencies form the logic of a schedule. Task duration tells you how long work takes. A dependency tells you how work is ordered.
Model dependencies as directed links
Write each relationship in a consistent direction:
predecessor → successor
For example:
Wireframes → Mockups
This means that the wireframes must be completed before the mockups can begin. It does not necessarily mean that the same person performs both tasks.
The most common dependency type is finish-to-start (FS). The predecessor must finish before the successor starts.
| Type | Meaning | Example |
|---|---|---|
| Finish-to-start (FS) | The predecessor finishes before the successor starts | Finish wireframes, then start mockups |
| Start-to-start (SS) | The successor starts after the predecessor starts | Start testing after development starts |
| Finish-to-finish (FF) | The successor finishes after the predecessor finishes | Finish documentation when implementation finishes |
| Start-to-finish (SF) | The successor finishes after the predecessor starts | Rare handover or replacement scenario |
Use finish-to-start unless the work genuinely overlaps. Unusual dependency types can make a schedule harder to understand.
A dependency can also include a lag, which is a deliberate delay between related tasks. For example, a review might start one day after a build finishes. A negative lag, sometimes called a lead, allows overlap, but it can hide risk. Prefer expressing real overlap with separate tasks and a clear start-to-start relationship.
Example: a website schedule
Consider these tasks:
- Wireframes: 5 days
- Mockups: 7 days
- Backend: 12 days
- Frontend: 10 days
- Integration: 4 days
The relationships are:
- Mockups starts after Wireframes finishes.
- Backend starts after Wireframes finishes.
- Frontend starts after Mockups finishes.
- Integration starts after both Frontend and Backend finish.
The two branches after Wireframes can run in parallel. Integration must wait for the slower branch.
The last task has two predecessors. In a schedule calculation, Integration cannot start until both predecessors have finished. Its effective start is controlled by whichever predecessor finishes later.
Create useful dependency links
Start with the work breakdown structure, which divides a project into manageable tasks. For each task, ask:
- What must be finished before this task can start?
- What information, decision, or deliverable does it require?
- Which tasks can safely run at the same time?
- What must this task enable afterward?
Record the reason for important links. “Frontend depends on approved mockups” is clearer than “Frontend depends on Design.”
Avoid linking tasks merely because they appear next to each other in a list. A list order is not always a work constraint. Excessive links remove useful parallelism and make every delay spread farther through the schedule.
Common dependency errors
Confusing responsibility with sequence
A designer and developer can work on related tasks at the same time. Assigning both tasks to one person does not automatically create a dependency. Add a link only when one task needs an output from the other.
Creating circular dependencies
A circular dependency is a loop such as:
A → B → C → A
No task in that loop can begin first. Break the loop by identifying the actual starting input, decision, or assumption.
Using vague summary tasks
A task named “Build website” is too broad to schedule well. Split it into tasks with clear outputs, such as “Implement checkout API” and “Build checkout page.” Dependencies should connect work that can be independently estimated and checked.
Ignoring external dependencies
Some predecessors belong outside the project, such as a vendor delivery or a legal approval. Represent these as explicit tasks or milestones. Otherwise, the schedule may imply that the team controls work it does not control.
> callout warning > Every dependency should answer the question, “What specific condition makes the successor ready to start or finish?” If you cannot name that condition, the link may be unnecessary or unclear. > ```
Once the links are defined, a forward pass can calculate each task's earliest start and finish. Tasks with several predecessors use the latest predecessor finish as their constraint.
Exercise
Wireframes takes 5 days. Mockups takes 7 days and depends on Wireframes. Backend takes 12 days and also depends on Wireframes. Which task controls the earliest start of Integration if Integration depends on both Mockups and Backend?
Show answer
Backend controls it because it finishes later: day 17 versus day 12 for Mockups, assuming both start after Wireframes.