Sub topic 4
Mark Milestones
This chapter assumes you know basic project terms such as task, deadline, and deliverable. It also assumes you can read a calendar and understand that tasks may depend on other tasks.
A milestone is a significant point in a project schedule. It records that an important result, decision, or approval has been reached. Unlike a normal task, a milestone has no duration. It happens at one point in time.
Milestones help people answer questions such as:
- Has the design been approved?
- Is the product ready for testing?
- Has the customer accepted the deliverable?
- Can the project move to its next phase?
Choose meaningful milestones
Do not turn every completed task into a milestone. A milestone should help someone understand project progress or make a decision.
Useful milestones often represent:
- A completed deliverable, such as “Prototype complete”
- An approval, such as “Design approved”
- A phase boundary, such as “Build phase begins”
- An external event, such as “Vendor equipment delivered”
- A release or launch, such as “Version 1.0 released”
A milestone should have a clear completion rule. “Development mostly done” is difficult to verify. “All planned features pass acceptance tests” gives the team a specific condition to check.
A milestone can also be a decision gate. At a decision gate, a stakeholder decides whether the project may continue. For example, a steering committee might approve the design before the team begins implementation.
Place milestones in the schedule
A milestone is usually placed after the tasks that produce or verify its result. For example:
- Write requirements.
- Review requirements.
- Approve requirements.
- Begin design.
“Requirements approved” is a milestone after the review task. The design task depends on that milestone.
In a schedule, a milestone can have predecessors and successors just like a task. The difference is that its duration is zero. Its date is determined by its dependencies or by an explicitly planned date.
| Schedule item | Duration | Example purpose |
|---|---|---|
| Task | Several hours or days | Produce a specific piece of work |
| Milestone | Zero days | Record an approval, result, or key date |
| Deadline | Zero days | State the latest acceptable date |
A deadline and a milestone are related but not identical. A milestone says that an event is expected or achieved on a date. A deadline says that work must be complete by a date. A project may have a milestone called “Customer acceptance” and a separate deadline requiring that acceptance by June 30.
Represent milestones in Mermaid
Mermaid Gantt charts represent a milestone with the milestone keyword and a duration of 0d. The task identifier lets other tasks refer to it with an after dependency.
The design approval milestone occurs when the mockups finish. Frontend work starts after the approval milestone, so the dependency expresses a project rule: implementation cannot begin until the design is accepted.
Avoid common milestone errors
A milestone is weak when its name describes activity instead of an outcome. “Review design” is usually a task. “Design approved” is a milestone if an authorized person must approve it.
Watch for these errors:
- Giving a milestone a nonzero duration
- Creating too many milestones, which makes important events harder to see
- Omitting the person or group responsible for approval
- Using vague completion criteria
- Placing a milestone on a convenient date instead of calculating it from its predecessors
- Forgetting external dependencies, such as a supplier delivery or customer review
When a milestone moves, inspect both its predecessors and successors. A delayed approval may shift an entire phase. Record the reason for the change so the schedule history explains what happened.
Exercise
A team finishes testing on May 12, but a product owner must approve the test report before release work begins. What milestone should you add, and what should release work depend on?
Show answer
Add a zero-duration milestone named “Test report approved” after testing. Make release work depend on that milestone, because release cannot begin until the product owner gives approval.