What to do when the buffer runs out
This chapter assumes you already know the three buffer types (task, transition, project) and that you have sized at least one buffer from your own estimate history. Here you learn what to do when the slack you planned is gone and work is still unfinished.
Treat a spent buffer as a signal
A buffer exists to be used. Spending it means the plan worked as designed. The problem starts when the buffer is empty and the remaining work still exceeds the remaining time. At that point the schedule no longer absorbs surprises, so any further delay moves a deadline or displaces a commitment.
Decide quickly. Silent overrun is the common failure: people keep working, hope to catch up, and report the problem only after the date has passed. Early notice gives other people time to adjust.
Check the remaining work first
Before choosing a response, compare two numbers: the work left and the time left. Estimate the remaining work fresh. Do not subtract your original estimate from the time already spent, because the original estimate may have been wrong in a way that also affects the rest of the task.
def remaining_gap(hours_left_in_plan, hours_of_work_remaining, buffer_left):
"""Return how many hours the plan is short (0 if it still fits)."""
available = hours_left_in_plan + buffer_left
return max(0.0, hours_of_work_remaining - available)
# Task planned for 6h with a 2h buffer. 5h are spent, buffer is gone,
# and a fresh estimate says 3h of work remain.
gap = remaining_gap(
hours_left_in_plan=1,
hours_of_work_remaining=3,
buffer_left=0,
)
print(f"Short by {gap:.1f} hours")A gap of 0 means you can continue without changing anything. A positive gap means you must pick a response.
Choose a response
You have four options. Pick by asking what the deadline and the people depending on it can tolerate.
| Response | Use it when | Cost |
|---|---|---|
| Reduce scope | The core result matters more than every detail | Some features or polish are dropped |
| Borrow from a later buffer | The overrun is small and later work has slack | The later buffer is smaller, so later risk rises |
| Move the deadline | The date is flexible and others can adjust | Dependent people must replan |
| Add resources or cut other work | The date and scope are both fixed | Other commitments are dropped or delayed |
Work through the options in this order: scope, then later buffer, then deadline, then resources or dropped work. The earlier options disturb fewer people. Say which one you chose, so it is a decision and not a drift.
Borrow carefully
Borrowing from a project buffer is the intended use of that buffer. Borrowing from a buffer that protects a different task is riskier, because it removes cover for that task. Record each loan. Write down what you took, from where, and when it must be restored or accepted as lost.
If you borrow from a transition buffer, the cost shows up as back-to-back work with no recovery time. That is a short-term fix. Do it once, not every day.
Tell people early
Anyone who depends on the work should hear about the change as soon as you know. State three things: what changed, what you decided, and what you need from them.
For example: "The report review used up its buffer. I am cutting the appendix, so the main report still arrives Thursday. Tell me if you need the appendix."
This message is short, specific, and gives the other person a choice. It is easier to receive than a vague "it is running late".
Record what happened
Log the final actual duration against the original estimate, and note the cause of the overrun. If the cause was a one-off event, such as an outage, leave your buffer sizes alone. If the same cause repeats, the buffer was too small, and the next chapters on reviewing and calibration show how to adjust it.
Exercise
A task was planned at 8 hours plus a 2-hour buffer. After 9 hours the buffer is gone and a fresh estimate says 2 hours of work remain. The deadline is fixed for tomorrow, and the task has an optional section that would take 1 hour. What is the gap, and what is the first response you would try?
Show answer
Available time is the 1 hour left in the plan (8 + 2 - 9) plus 0 buffer, so 1 hour. Remaining work is 2 hours, so the plan is short by 1 hour. The first response to try is reducing scope: dropping the optional 1-hour section closes the gap without moving the deadline or touching other buffers. Then tell the people who expect that section.