Keeping Buffer Time from Being Given Away
This chapter assumes you have already placed buffers in your schedule. It covers how to stop them from being filled with other work. It builds on the earlier chapters on buffer sizing and placement.
Why buffers get raided
A buffer looks like free time on a calendar. A colleague sees an open slot and asks for it. You see the same slot at 4 p.m. on a good day and add one more task. Each time the cost looks small, because the overrun the buffer is meant to absorb has not happened yet.
The buffer is only worth something on the day a task runs long. If you spend it earlier, that day's overrun lands on your evening, your deadline, or someone else.
Make the buffer look like a commitment
A buffer that looks empty will be filled. Change how it appears:
- Block it on the calendar as busy, not free.
- Give it a name that describes its job, such as "Overrun cover" or "Transition", instead of "Buffer".
- Keep it at a fixed, predictable place, so you and others learn where it is.
- Keep it as one block where possible. A buffer split into 10-minute scraps is easy to ignore.
A named, busy block gets treated as a meeting with yourself. People usually ask before overriding a meeting.
Test every new request against the buffer
Decide before the request arrives what counts as spare time. Spare time is capacity minus planned work minus buffer. The buffer is excluded from what you can promise.
def fits_without_buffer(capacity, planned, buffer, request):
"""All values are in minutes. Returns True if the request leaves the buffer intact."""
spare = capacity - planned - buffer
return request <= spare
# 8-hour day, 330 minutes planned, 90 minutes of buffer
print(fits_without_buffer(480, 330, 90, 45)) # True
print(fits_without_buffer(480, 330, 90, 90)) # FalseHere the spare time is 60 minutes. A 45-minute request fits. A 90-minute request would eat the whole buffer, so it needs a different answer.
The third branch matters most. When the request does not fit, the answer is to trade, not to squeeze. A swap keeps the day's total load the same and keeps the buffer untouched.
Rules that hold up
- Say what you would drop. "I can do that, and it means the report moves to Thursday" is a real offer. It gives the requester the actual cost.
- Offer a later slot. Most requests are not due today. Name the next opening that does not touch a buffer.
- Protect the buffer at the planning stage. Decide the buffer size when you plan the day, not when you are already behind. Under pressure you will negotiate it away.
- Use the buffer only for overruns and transitions. New work is not an overrun. A task that ran late is.
- Check the buffer at a fixed time. If a buffer is still unused at midday, leave it in place. Some days it will go unused, and that is the buffer working as designed.
Common errors
- Treating an unused buffer as a surplus. Unused time on a quiet day does not prove the buffer is too big. Judge the size over several weeks of data, as the review chapter explains.
- Giving away "just this once". One exception sets the precedent. The next request cites it.
- Protecting the buffer by being vague. "I'm busy then" invites questions. A stated reason, such as "that block covers overruns on my release work", is harder to dispute and easier to respect.
- Shrinking buffers to look productive. A day with no spare room looks efficient only until the first delay.
Exercise
Your day has 480 minutes of capacity, 360 minutes of planned work, and a 60-minute buffer. A teammate asks for a 90-minute review today. Using the spare-time test, does it fit? Name two responses that keep the buffer intact.
Show answer
Spare time is 480 - 360 - 60 = 60 minutes, so a 90-minute review does not fit. Two responses that keep the buffer intact: offer a later day when there is spare time, or swap the review for a planned task of similar size if the review is more urgent.