Reviewing and Adjusting Over Time
This chapter assumes you already track estimates against actual durations, can size a buffer from that record, and know the three buffer types (task, transition, project). It covers the last step in the cycle: reviewing what happened and changing your buffers to match.
Why buffers need a review loop
A buffer sized once goes stale. Your tasks change, your tools change, and your estimating improves or drifts. A buffer that was right in January can be too small by June, or so large that it hides slack you could use.
The review loop has four steps. Collect the data, compare it with the plan, adjust the buffer, then run it again.
Choosing a review rhythm
Match the rhythm to how fast your work changes.
- Weekly, for 10 to 15 minutes: check whether buffers were used and by how much.
- Monthly: recompute your ratios from the log and resize task buffers.
- After each project: review the project buffer and note what caused any overrun.
Keep the weekly review short. Its job is to spot a problem early. The monthly review is where you change numbers.
What to compare
Look at each buffer type separately, because each one fails in a different way.
| Buffer type | What to measure | Sign it is too small | Sign it is too large |
|---|---|---|---|
| Task buffer | Actual divided by estimate | You overrun the buffered estimate often | You finish early almost every time |
| Transition buffer | Gap between planned and real start of the next item | You start late after most meetings | The gaps sit unused |
| Project buffer | Share of buffer consumed at each milestone | It is gone before the halfway point | More than half remains near the end |
A single overrun tells you little. Look for a pattern across several weeks before you change a number.
Recalculating a task buffer
The sizing method from earlier chapters can be rerun on recent data. Using only the latest tasks lets the buffer follow your current performance instead of your old habits.
from statistics import quantiles
# (estimated_hours, actual_hours), oldest first
history = [(2, 3), (4, 5), (1, 1.5), (3, 3), (5, 8),
(2, 2.5), (3, 3.5), (4, 4.5), (1, 1.2), (6, 7)]
def p80_ratio(records):
ratios = [actual / estimate for estimate, actual in records]
return quantiles(ratios, n=10)[7]
all_time = p80_ratio(history)
recent = p80_ratio(history[-5:])
print(f"All-time p80 ratio: {all_time:.2f}")
print(f"Last five tasks: {recent:.2f}")Here the recent ratio is lower than the all-time one, so the older data is pulling the buffer up. That suggests your estimates have improved. Reduce the buffer, but not all the way to the recent value at once. Five tasks is a small sample, so move partway and check again next month.
Adjusting without overreacting
Three rules keep adjustments stable.
- Change one thing at a time. If you resize the task buffer and move transition gaps in the same week, you cannot tell which change helped.
- Move in small steps, such as 10 to 20 percent of the current buffer.
- Require at least four to five data points before acting.
Also ask why a buffer was used, not only how much. If a task overran because a colleague was late, a larger personal buffer will not fix it. That problem needs a change in placement, a dependency check, or a conversation. Record the cause next to each overrun so you can tell estimating error from outside interruption.
Watching for drift
Two failure modes show up only over time.
- Estimates inflate. If you start padding your estimates because you know a buffer exists, the buffer is counted twice. Your ratios will fall toward 1.0, which looks like improvement but is not.
- Parkinson's law returns. If tasks finish exactly at the end of their buffered time every week, work is expanding to fill the slot. Try one shorter slot as a test and see whether the task still gets done.
Keeping the process cheap
A review that takes an hour will be skipped. A spreadsheet with four columns (task, estimate, actual, cause of any overrun) is enough. Add a note when a buffer was given away to a new commitment, since that explains overruns that are not estimating errors.
Practice
Exercise
Over six weeks, your 4-hour tasks have taken an average of 4.1 hours, but your all-time p80 ratio is still 1.5, so you plan 6 hours for each. You finished early on 9 of the last 10 tasks. What should you do, and how large should the first change be?
Show answer
The buffer is too large for your current performance, and the old data is inflating the ratio. Recompute the p80 ratio from the most recent tasks, then reduce the buffer in a small step, for example by 10 to 20 percent of the current buffer, instead of jumping to the new value. Also check whether your raw estimates grew after you started buffering, because that would make the shrinking ratio misleading. Review again after a month.
Exercise
A task overran its buffer three times this month. Each time, the cause in your log is "waiting for a code review from the same colleague". Should you increase your task buffer?
Show answer
No. The cause is an outside dependency, not estimating error, so a larger personal buffer treats the wrong problem. Change the plan instead: schedule the review request earlier, agree on a response time with the colleague, or place the dependent work later in the day or week.