Sub topic 7
Spreading the budget over time
The budget total tells you how much the project will cost. It does not say when the money is needed. This chapter turns that single number into a monthly plan. The plan has two uses. It is the baseline you compare actual spending against, and it is the cash-flow view that finance uses to reserve funds.
This chapter assumes you can already assemble a budget total from labor, non-labor costs and contingency. It also assumes you have a schedule that says which work package runs in which months. If you need either of these, read the earlier chapters first.
Why phase the budget
A total of 21,230.00 cannot tell you whether you are on track in month 2. Suppose you have spent 8,000.00 by then. That might be healthy or a serious overrun, depending on how much you planned to have spent by that date. Time phasing gives each period a planned value, so every later comparison has something to measure against.
Phasing answers three questions:
- Baseline: how much did we plan to spend in each period, and cumulatively?
- Cash flow: when does money actually leave the account?
- Funding: how much must be available at each point?
The baseline and the cash flow are different views of the same budget. The baseline follows when work is planned to happen. Cash flow follows when invoices are paid. Keep them separate, because they differ whenever payment terms or purchase timing differ from work timing.
The method
Phasing has four steps:
- Take each work package's budget from the estimate.
- Place each package on the schedule, giving it a start period and an end period.
- Spread each package's cost across its periods using a rule, such as evenly.
- Add the packages period by period, then add a running total.
The final cumulative figure must equal the budget total. If it does not, the phasing has lost or duplicated money. This is the main check on the whole exercise.
A worked example
We continue with the example budget. Labor is 17,500.00, non-labor items are 1,800.00, direct costs are 19,300.00, and 10% contingency adds 1,930.00, for a total of 21,230.00.
The schedule runs five months:
| Item | Cost | Months | Spread rule |
|---|---|---|---|
| Design | 3,200.00 | M1 to M2 | Even |
| Development | 10,800.00 | M2 to M4 | Even |
| Testing | 3,500.00 | M4 to M5 | Even |
| Software licenses | 1,200.00 | M1 | One-time purchase |
| Hosting | 600.00 | M3 to M5 | Even |
Design is 3,200.00 over two months, so each month carries 1,600.00. Development is 10,800.00 over three months, which is 3,600.00 a month. Testing is 1,750.00 a month. Hosting is 200.00 a month. The licenses are bought once, so all 1,200.00 lands in month 1.
Phasing in code
The script below spreads each item, adds the contingency, and builds the cumulative baseline.
MONTHS = ["M1", "M2", "M3", "M4", "M5"]
CONTINGENCY_RATE = 0.10
# name: (cost, first month, last month), months numbered from 1
items = {
"Design": (3200.0, 1, 2),
"Development": (10800.0, 2, 4),
"Testing": (3500.0, 4, 5),
"Software licenses": (1200.0, 1, 1),
"Hosting": (600.0, 3, 5),
}
def spread(amount, start, end, n_months):
"""Spread amount evenly over start..end; the last month absorbs rounding."""
plan = [0.0] * n_months
span = end - start + 1
share = round(amount / span, 2)
for m in range(start, end + 1):
plan[m - 1] = share
plan[end - 1] = round(amount - share * (span - 1), 2)
return plan
direct = [0.0] * len(MONTHS)
for cost, start, end in items.values():
for i, value in enumerate(spread(cost, start, end, len(MONTHS))):
direct[i] += value
print(f"{'Mon':<3}{'Direct':>10}{'Cont.':>10}{'Total':>10}{'Cumulative':>12}")
cumulative = 0.0
for month, d in zip(MONTHS, direct):
contingency = d * CONTINGENCY_RATE
total = d + contingency
cumulative += total
print(f"{month:<3}{d:>10.2f}{contingency:>10.2f}{total:>10.2f}{cumulative:>12.2f}")
assert round(cumulative, 2) == 21230.00, "phased total does not match the budget"Running it prints:
Mon Direct Cont. Total Cumulative
M1 2800.00 280.00 3080.00 3080.00
M2 5200.00 520.00 5720.00 8800.00
M3 3800.00 380.00 4180.00 12980.00
M4 5550.00 555.00 6105.00 19085.00
M5 1950.00 195.00 2145.00 21230.00The last line of the script is the reconciliation check. If someone later edits a start month or forgets an item, the assertion fails instead of silently producing a baseline that does not add up.
The spread function gives the last month whatever remains after the earlier months are rounded. Dividing 1,000.00 by 3 gives 333.33 per month. The first two months take 666.66, so the last month takes 333.34. Without this step, the monthly figures would sum to 999.99 and the check would fail.
The S-curve
Plotting the cumulative column gives the baseline curve. It starts slowly, steepens when several packages overlap, and flattens as work ends. This shape is called an S-curve. Most projects have one, because more work runs in parallel in the middle than at either end.
Month 4 is the peak because Development and Testing overlap there, and Hosting has started. Peaks like this are where overruns tend to show up first, so watch them closely once tracking begins.
Choosing a spread rule
Even spreading is the simplest rule and suits work that runs at a steady pace. It is not always right. Pick the rule that matches how the cost behaves.
| Rule | Use it when | Example |
|---|---|---|
| Even | Effort is steady across the package | A developer working full time for three months |
| One-time | The cost happens at a single moment | A license bought on day one |
| Front-loaded | Most cost comes early | Equipment ordered at the start, followed by minor tuning |
| Milestone-based | Cost is triggered by an event, not the calendar | A vendor paid 50% at signing and 50% at delivery |
| Weighted | Effort rises or falls inside a package | Testing that ramps up toward release |
A weighted rule needs weights that sum to 1. For a three-month package with weights 0.2, 0.3 and 0.5, a 10,000.00 cost is phased as 2,000.00, 3,000.00 and 5,000.00. The same last-month rounding rule applies.
Where contingency goes
The example above spread contingency in proportion to direct cost, so each month carries 10%. That is easy to follow, but it is only one choice. Teams handle contingency in two main ways:
- Proportional: every month carries its share. The baseline is smooth and the final cumulative figure matches the approved budget.
- Held as a reserve: contingency stays outside the monthly plan as a single line. It is released into a package only when a risk occurs or an estimate proves too low.
The reserve approach keeps the monthly baseline equal to the direct plan, here 19,300.00 in total. Spending above that plan is then visible as a draw on the reserve, which is useful because overruns are not hidden inside a smooth 10% allowance. Whichever you choose, state it in the budget document and apply it consistently. A baseline that mixes the two approaches cannot be reconciled.
From baseline to cash flow
The baseline records when cost is incurred. Cash flow records when it is paid. If invoices are settled 30 days after the work, each month's cash out is the previous month's cost. The snippet below shifts the baseline by one month.
baseline = [3080.00, 5720.00, 4180.00, 6105.00, 2145.00]
payment_lag_months = 1
cash_out = [0.0] * (len(baseline) + payment_lag_months)
for i, cost in enumerate(baseline):
cash_out[i + payment_lag_months] += cost
for month, value in enumerate(cash_out, start=1):
print(f"M{month}: cash out {value:.2f}")The output is:
M1: cash out 0.00
M2: cash out 3080.00
M3: cash out 5720.00
M4: cash out 4180.00
M5: cash out 6105.00
M6: cash out 2145.00The project's cash needs now extend into month 6, one month past the end of the work. A project can finish its work on schedule and still have a payment due after the work is done. If your funding is released by fiscal year or by quarter, this shift can move cost into a different funding period.
In practice, payment timing differs by item. A license may be paid in advance and a contractor 45 days after the invoice. For a rough cash-flow view, one lag for everything is acceptable. For a funding request, give each item its own lag.
Common errors
- Phasing without the schedule. Dividing the total by the number of months ignores overlaps and gaps. The result looks tidy but cannot be compared meaningfully with real spending.
- Forgetting non-labor timing. Licenses, equipment and travel are often paid at one moment. Spreading them evenly hides a cost spike.
- Failing the reconciliation. Rounding, a dropped item, or a package scheduled twice makes the phased total differ from the budget. Always check the final cumulative figure.
- Mixing baseline and cash flow. If actuals are recorded when work is done, compare them with the baseline. If they are recorded when invoices are paid, compare them with the cash-flow plan. Comparing across the two views creates variances that are only timing differences.
- Changing the baseline casually. Once approved, the phased baseline is the reference for variance. Editing it to match actual spending erases the evidence of overruns. Changes go through the change-control step covered later in this tutorial.
- Ignoring period length. Months have different numbers of working days. For short projects, phase by week instead. For long ones, align periods with the accounting calendar so that figures match finance reports.
What this enables
With a phased baseline you can compare, in any month, what you planned to have spent by then with what you have actually spent. The next chapter records the actuals, and the one after it computes the variance from them. If the baseline is wrong, every later variance figure is wrong too, which is why the reconciliation check is worth the effort.
Exercise
A project has a 6,000.00 work package scheduled from month 2 to month 4, spread evenly. A 900.00 equipment purchase is made in month 3. Contingency is 10% of direct cost, spread proportionally. What is the planned total for each of months 1 to 4, and what is the cumulative figure at the end of month 4?
Show answer
Month 1 has no work, so it is 0.00. The package costs 6,000.00 / 3 = 2,000.00 a month in months 2, 3 and 4. The equipment adds 900.00 in month 3. Direct costs are 0.00, 2,000.00, 2,900.00 and 2,000.00 for months 1 to 4. With 10% contingency, the planned totals are 0.00, 2,200.00, 3,190.00 and 2,200.00. The cumulative figure at the end of month 4 is 7,590.00. This equals (6,000.00 + 900.00) x 1.10, so it reconciles with the budget total.
Exercise
A 1,000.00 cost is spread evenly over three months, and each month's share is rounded to two decimals. Why does the monthly figure 333.33 cause a problem, and how does the chapter's spread function fix it?
Show answer
Three shares of 333.33 sum to 999.99, so the phased total is 0.01 short of the budget and the reconciliation check fails. The function rounds the shares for all months except the last, then gives the last month the remainder, 1,000.00 - 666.66 = 333.34. The three months now sum to exactly 1,000.00.
Exercise
The cash-flow example shifted every cost by one month. Why can a project finish its work in month 5 but still show cash out in month 6, and why does that matter for funding?
Show answer
Invoices are paid after the work is done, so the last month's cost (2,145.00 in the example) is paid in month 6. The funding must therefore remain available one month beyond the end of the work. If funding is released by fiscal period and month 6 falls in a new period, the cost moves into that period's funding.