Sub topic 10
Forecasting the cost at completion
This chapter assumes you can read short Python scripts and can do the arithmetic from the earlier chapters. You should already have a baseline budget per work package and a record of actual costs. It also assumes you can calculate variance as budget minus actual. Here you use those inputs to answer one question: what will this project cost when it finishes?
Budget, estimate, and forecast
The three terms are easy to confuse.
| Term | Question it answers | When it changes |
|---|---|---|
| Estimate | What do we expect this work to cost? | Before approval, as you refine the numbers |
| Budget (baseline) | What cost did we approve? | Only through change control |
| Forecast | What do we now expect the final cost to be? | Every reporting period |
The budget is a commitment, so it stays fixed. The forecast is a prediction, so it moves as you learn more. A forecast that never differs from the budget is usually not being updated.
The forecast is called the estimate at completion (EAC). The remaining pieces are:
- Actual cost (AC): what you have spent so far.
- Estimate to complete (ETC): what you expect to spend from now until the work is done.
- Budget at completion (BAC): the approved budget for the work.
The basic relationship is:
EAC = AC + ETCMoney already spent is a fact. You only forecast the part that has not happened yet.
Forecasting per work package
Forecast at the work-package level, not only for the whole project. A project total can look fine while one package is far over and another is far under. Netting them hides the overrun, and the underspend may not be available to the package that needs it.
For each work package, do the following:
- Take the actual cost recorded to date.
- Estimate the cost to finish the remaining work.
- Add them to get the forecast.
- Subtract the forecast from the budget to get the forecast variance.
A negative forecast variance means you expect an overrun. This differs from the variance in the previous chapter, which compared budget with actual spending so far. A package can be under budget today and still forecast an overrun, because the work remaining is larger than the money remaining.
The script below applies this to the three work packages from the running example. The budget figures come from the first example: design 40 hours at 80, development 120 hours at 90, and testing 50 hours at 70.
budget = {"Design": 3200.0, "Development": 10800.0, "Testing": 3500.0}
actual = {"Design": 3600.0, "Development": 5000.0, "Testing": 0.0}
estimate_to_complete = {"Design": 0.0, "Development": 6200.0, "Testing": 3500.0}
for name in budget:
forecast = actual[name] + estimate_to_complete[name]
variance = budget[name] - forecast
print(f"{name}: forecast {forecast:.2f}, variance {variance:.2f}")The output is:
Design: forecast 3600.00, variance -400.00
Development: forecast 11200.00, variance -400.00
Testing: forecast 3500.00, variance 0.00Each package behaves differently:
- Design is finished (its ETC is 0). Its actual cost of 3600 is final, so the 400 overrun is now a fact.
- Development has spent only 5000 of 10800, so it looks comfortable against its budget. The remaining work is expected to cost 6200, so the package will still end 400 over.
- Testing has not started. Its forecast simply equals its budget because nothing suggests otherwise.
Design shows that a completed package gives you no more forecasting to do. Testing shows the default for unstarted work, which is to keep the budget figure until you have a reason to change it. Development is where most of the judgment goes.
Rolling up to the project
Sum the package figures to get the project forecast. The sums below are plain arithmetic on the output above:
- Budget: 3200 + 10800 + 3500 = 17500
- Forecast: 3600 + 11200 + 3500 = 18300
- Forecast variance: 17500 − 18300 = −800
The project is forecast to overrun its labor budget by 800, which is about 4.6% of 17500. Report both the amount and the percentage. A reader cannot judge 800 without knowing the size of the budget it applies to.
The first chapter's budget also included a 1930 contingency reserve. The forecast overrun of 800 is smaller than that. Even so, do not treat the reserve as a free pool. Drawing on it means a deliberate decision that the overrun is a risk that has materialized, and that decision follows the change-control process in the next chapter. If you quietly absorb the overrun, the reserve disappears without anyone choosing to spend it.
How to estimate the cost to complete
The ETC is where forecasts succeed or fail. There are two common approaches, and they answer different questions.
Bottom-up re-estimate
You look at the remaining tasks and estimate them again, using what you now know. The Development figure of 6200 came from this kind of estimate. It is usually the most accurate method because it uses current knowledge of the work. It costs more effort, and it depends on the person estimating being honest about problems.
Trend-based projection
You assume the project will keep performing as it has so far. This needs a measure of how much work is done, usually as earned value:
- Earned value (EV): the budgeted cost of the work actually completed, which is BAC multiplied by the fraction complete.
- Cost performance index (CPI): EV divided by AC. A value below 1 means you are spending more than the budgeted cost for the work done.
If past inefficiency will continue, the forecast is:
EAC = BAC / CPISuppose Development is 40% complete by measured work, with 5000 spent:
bac = 10800.0
percent_complete = 0.40
actual_cost = 5000.0
earned_value = bac * percent_complete
cpi = earned_value / actual_cost
eac_trend = bac / cpi
print(f"Earned value: {earned_value:.2f}")
print(f"CPI: {cpi:.3f}")
print(f"EAC (trend): {eac_trend:.2f}")The output is:
Earned value: 4320.00
CPI: 0.864
EAC (trend): 12500.00The trend method forecasts 12500, while the bottom-up re-estimate gave 11200. This 1300 gap is information, not a mistake. Either the trend is too pessimistic because early work was slow and the rest will go faster, or the re-estimate is too optimistic. You resolve the difference by asking the team what is different about the remaining work. If nothing is different, the trend deserves more weight.
Choosing a method
| Situation | Better method | Reason |
|---|---|---|
| Early deviation was a one-time event, such as a rework or a delayed delivery | Actual plus remaining budget (AC + BAC − EV) | The cause will not repeat |
| Early deviation reflects a wrong rate or a consistently underestimated task type | Trend-based (BAC / CPI) | The cause will continue |
| The original estimate is no longer valid, for example because of a scope or design change | Bottom-up re-estimate | History does not describe the remaining work |
| Progress data is too unreliable to compute CPI | Bottom-up re-estimate | The trend method would only multiply the error |
Where you are unsure, report a range using two methods and show the assumption behind each. A range of 11200 to 12500 for Development tells stakeholders more than a single figure that hides your uncertainty.
The forecasting cycle
Forecasting repeats every period. The diagram shows the loop.
The fork at the decision matters. A negative forecast variance gives you a choice:
- Corrective action: reduce the remaining cost, for example by trimming effort, reassigning people, or removing low-value work, so that the forecast returns to the baseline.
- Change request: accept that the baseline no longer holds and ask for more money or a changed scope, through the process covered in the next chapter.
Which one is right is a project decision, not a calculation. The forecast only makes the problem visible early enough to choose.
Common errors
- Forecasting the project total only. Package-level overruns cancel out in the total and surface too late.
- Reusing last period's ETC. If you spent money last period, the remaining work should have shrunk. An unchanged ETC after spending means the forecast has silently grown.
- Counting committed costs twice or not at all. Purchase orders you have signed but not yet paid belong in the forecast, either as actuals or as part of the ETC, but not both.
- Assuming future savings with no plan. An ETC below the remaining budget needs a reason you can state.
- Forgetting the unit. Hours are not money. Convert remaining hours into cost at the correct rate before adding them to actual cost.
- Letting the forecast drift to match the budget. Adjusting the ETC so that the variance is zero defeats the purpose. Forecast what you honestly expect.
Edge cases
- A finished package that came in under budget. Its forecast equals its actual cost. Do not move the saving to another package automatically. Treat any reallocation as a change.
- Spending ahead of progress. A package can be 60% spent and 30% complete. Compare the cost to the progress, not to the calendar.
- Late-arriving actuals. Accrue known costs that have not been invoiced yet, or note that the figure is incomplete.
- Currency or rate changes. If hourly rates or exchange rates shift, re-price the ETC at the new rates. Past actuals stay as recorded.
Exercise
A work package has a budget of 8000. Actual cost to date is 5000, and the team estimates 3800 to finish the remaining work. What is the forecast, what is the forecast variance, and what does the sign of the variance tell you?
Show answer
Forecast = AC + ETC = 5000 + 3800 = 8800. Forecast variance = budget − forecast = 8000 − 8800 = −800. The negative sign means the package is expected to overrun its budget by 800, even though only 5000 of the 8000 has been spent so far.
Exercise
A package has a BAC of 6000 and is 50% complete with an actual cost of 3750. Using the trend method, what is the CPI and the EAC? Is the package forecast to overrun?
Show answer
Earned value = 6000 × 0.50 = 3000. CPI = 3000 / 3750 = 0.8. EAC = BAC / CPI = 6000 / 0.8 = 7500. The package is forecast to overrun by 1500, because 7500 exceeds the budget of 6000.
Exercise
Your bottom-up ETC and the trend-based EAC for the same package differ by a large amount. Give two questions you would ask the team before choosing one, and one way you could report the result honestly while the question remains open.
Show answer
Questions: (1) Was the early overspending caused by a one-time event, or by a continuing problem such as underestimated effort? (2) Is the percent-complete figure based on measurable milestones, or on a guess? Reporting: give a range with both figures and state the assumption behind each, for example "11200 if the early delays do not recur, 12500 if the current spending rate continues."