Sub topic 2
Breaking scope into costable work packages
A budget can only be as complete as the list of work behind it. This chapter shows how to turn a scope statement into a set of work packages. A work package is a piece of work small enough to estimate, assign, and track. The next chapter prices them.
This chapter assumes you can read a short Python script, work with percentages, and tell scope (what the project delivers) from schedule (when it delivers it).
Why decomposition comes before estimating
Estimating a whole project in one number hides three problems:
- You cannot see which parts drive the cost.
- You cannot tell what was left out.
- You cannot compare actual spending against anything finer than "the project".
Breaking the scope down fixes all three. Each piece gets its own estimate, owner, and actual cost. Errors in individual estimates also tend to partly cancel when you add the pieces up.
The standard tool is the work breakdown structure (WBS). A WBS is a hierarchical tree that divides the project's total scope into smaller and smaller components. The root is the whole project. The leaves at the bottom are work packages.
The 100% rule
The most useful rule for checking a WBS is the 100% rule:
- The children of any node must account for 100% of that node's scope.
- They must not include anything outside it.
The rule catches errors in both directions. A missing child is an unbudgeted piece of work. An extra child, or two children that overlap, is work you will pay for twice.
A common source of missing scope is work that produces no customer-visible deliverable. Project management, meetings, deployment, training, and handover are the usual cases. Give them their own branch so they get a budget line.
Decompose by deliverable, not by activity
A WBS can be organized in two ways.
- By deliverable. Branches are things the project produces, such as "User interface mockups" or "Test report".
- By activity. Branches are verbs, such as "Meeting", "Coding", or "Reviewing".
Prefer deliverables for budgeting. Deliverables have clear boundaries, so you can say when one is done and whether it is in scope. Activities such as "Coding" run through the whole project, so they are hard to cap or compare against a budget.
Activities still appear, but one level down. A deliverable-based work package can be broken into activities when you build the schedule. Costing happens at the package level.
| Approach | Example node | Strength | Typical problem |
|---|---|---|---|
| By deliverable | "Data model" | Clear definition of done | Needs real thought to name deliverables |
| By activity | "Coding" | Easy to brainstorm | Overlaps between nodes; no end point |
| By phase | "Phase 2" | Matches the calendar | Mixes unrelated deliverables in one node |
A hybrid is common: top-level branches by phase or major deliverable, with deliverables below. Keep one organizing principle per level. Mixing "Design" (a phase) and "Database" (a component) as siblings invites overlap.
What makes a good work package
A work package is a good costing unit when it meets these tests:
- One deliverable. You can say in one sentence what exists when it is finished.
- One owner. A single person or team is accountable for it, even if others contribute.
- Estimable. Someone with relevant experience can give an effort figure without major guessing.
- Trackable. You can record actual hours or spending against it separately.
- Reasonably sized. Not so large that it hides detail, and not so small that tracking it costs more than the work.
Many teams use a size guideline known as the 8/80 rule. A work package should take at least 8 hours and no more than 80 hours of effort. Treat the numbers as a rule of thumb. A small project may use 4 to 40 hours, and a large program may use packages of several hundred hours. What matters is that your team picks one range and applies it consistently.
A worked decomposition
Suppose you are budgeting a small customer portal. The scope statement says the project delivers a designed, built, and tested web portal. The first level has three deliverable groups: Design, Development, and Testing. The next level breaks each into work packages.
Each node gets a numeric ID that shows its position. The ID "1.2.1" means the first child of the second child of the root. Stable IDs let you attach estimates, actual costs, and change requests to the same package for the life of the project.
The six leaves are the work packages. The next chapters attach costs to them.
Writing the WBS dictionary
A tree of names is not enough. Two people can read "Front end" and picture different work. The WBS dictionary is a short entry for each work package that fixes its meaning. It usually records:
- the ID and name
- the deliverable and its acceptance criteria
- the owner
- what is included and, importantly, what is excluded
- assumptions and dependencies on other packages
The "excluded" line prevents most overlap disputes. For "Front end", you might write: "Includes the login, dashboard, and invoice pages. Excludes the content of help pages, which are the client's responsibility."
Checking a WBS with code
You can check part of the 100% rule mechanically, even though scope itself needs human judgment. The script below stores the WBS as nested dictionaries and rolls effort up from the leaves. It flags leaves that have no owner or deliverable, duplicate IDs, and effort outside the 8 to 80 hour range.
The hour figures here are placeholders chosen to match the example budget. How to arrive at them is the subject of the next chapter.
wbs = {
"id": "1",
"name": "Customer portal",
"children": [
{
"id": "1.1",
"name": "Design",
"children": [
{"id": "1.1.1", "name": "User interface mockups",
"owner": "Ana", "deliverable": "Approved mockups", "hours": 16},
{"id": "1.1.2", "name": "Data model",
"owner": "Ana", "deliverable": "Schema document", "hours": 24},
],
},
{
"id": "1.2",
"name": "Development",
"children": [
{"id": "1.2.1", "name": "Back-end API",
"owner": "Ben", "deliverable": "Deployed API", "hours": 70},
{"id": "1.2.2", "name": "Front end",
"owner": "Chloe", "deliverable": "Working web pages", "hours": 50},
],
},
{
"id": "1.3",
"name": "Testing",
"children": [
{"id": "1.3.1", "name": "Test plan",
"owner": "Dev", "deliverable": "Signed-off test plan", "hours": 10},
{"id": "1.3.2", "name": "Test execution",
"owner": "Dev", "deliverable": "Test report", "hours": 40},
],
},
],
}
def leaves(node):
children = node.get("children", [])
if not children:
yield node
for child in children:
yield from leaves(child)
def total_hours(node):
children = node.get("children", [])
if not children:
return node["hours"]
return sum(total_hours(child) for child in children)
def check(root, low=8, high=80):
problems = []
seen = set()
for pkg in leaves(root):
if pkg["id"] in seen:
problems.append(f"{pkg['id']} is used more than once")
seen.add(pkg["id"])
for field in ("owner", "deliverable"):
if not pkg.get(field):
problems.append(f"{pkg['id']} {pkg['name']} has no {field}")
if not low <= pkg["hours"] <= high:
problems.append(
f"{pkg['id']} {pkg['name']} has {pkg['hours']} h, "
f"outside {low}-{high} h"
)
return problems
for branch in wbs["children"]:
print(f"{branch['name']}: {total_hours(branch)} h")
print(f"Total: {total_hours(wbs)} h")
issues = check(wbs)
print("No problems found." if not issues else "\n".join(issues))Running it prints:
Design: 40 h
Development: 120 h
Testing: 50 h
Total: 210 h
No problems found.These roll-ups, 40, 120, and 50 hours, are the hours used in the budget calculation in later chapters. Change a package's hours to 5 or 95 and the check reports it. Delete an owner and it names the package.
Common errors
- Missing management and support work. Project management, reviews, environments, and handover are real costs. If they have no package, they will appear later as unexplained overruns.
- Overlapping packages. "Front end" and "User interface" may describe the same effort. Use the dictionary's exclusion lines to separate them.
- Mixed organizing principles. Siblings such as "Phase 1", "Database", and "Meetings" cannot be checked against the 100% rule.
- Packages with no owner. If nobody is accountable, nobody will report actuals, and variance analysis later has nothing to compare.
- Splitting too far. A hundred two-hour packages produce a budget that costs more to maintain than it saves. Split where it improves estimates or tracking.
- Splitting too little. A 300-hour package called "Build the system" cannot be estimated with any confidence. It also gives no early warning when it slips.
- Treating the WBS as a schedule. The WBS says what the work is, not in what order it happens. Sequence and dates belong to the schedule, which you will use later when spreading the budget over time.
Keeping the WBS stable
The package IDs become the keys for the whole budget. Estimates, actuals, variances, and change requests all refer to them. Two habits help:
- Never reuse an ID for different work. Retire it and create a new one.
- When scope changes, add or split packages and record why. Do not silently change what an existing package contains. A later chapter covers the change-control step that governs this.
Exercise
A WBS for an office move has these children under "Move": "Pack boxes", "Truck rental", "Phase 1", and "Unpack boxes". What two problems does this list have, and how would you fix them?
Show answer
The children mix organizing principles: "Pack boxes" and "Unpack boxes" are activities, "Truck rental" is a cost item, and "Phase 1" is a time period. This makes the 100% rule hard to apply, and "Phase 1" probably overlaps the others. Fix it by choosing one principle, such as deliverables (for example "Old office cleared", "Goods transported", "New office set up", "Project management"), then moving the activities and the truck rental under the deliverable they serve. Check that nothing is missing, such as cleaning or IT reconnection.
Exercise
A work package called "Reporting module" is estimated at 260 hours, has two owners, and its deliverable is "Reports". Which of the five work-package tests does it fail, and what would you do?
Show answer
It fails "one owner" (two owners), "one deliverable" (the name "Reports" is vague and may cover several reports), and "reasonably sized" (260 hours is far above the usual 80-hour guideline). Split it into packages for each distinct report or component, give each one deliverable with acceptance criteria, and assign a single accountable owner to each.
Exercise
In the script, change the "Test plan" package to 6 hours and remove its owner. What does check(wbs) report?
Show answer
It reports two problems: "1.3.1 Test plan has no owner", and "1.3.1 Test plan has 6 h, outside 8-80 h". The package ID appears in each message so you can find it in the tree.