Handling changes without losing the baseline
This chapter covers what to do when scope, cost, or schedule changes after the budget is approved. You can then absorb the change and still compare actual spending with the original plan. It assumes you have built a budget with contingency, spread it over time as a baseline, and calculated variance against it.
Why a baseline needs protection
The baseline is the approved, time-phased budget that you measure actual costs against. Variance analysis only means something if the baseline stays fixed while you measure against it.
Suppose Design is budgeted at 3200.00 and costs 3600.00. The variance is -400.00, and that is useful information. Now suppose someone quietly edits the Design budget to 3600.00 so the report looks clean. The variance is 0, and the project has lost the evidence that the estimate was wrong. Every later estimate for this team will be as unreliable as that one.
Change control prevents this. It is a short, repeatable procedure that decides whether a proposed change is accepted, records the decision, and updates the baseline in a traceable way. The procedure does not exist to say no. It makes every change visible, priced, and approved by someone with the authority to spend the money.
What counts as a change
Not every deviation from the budget is a change. Telling them apart is the most common source of confusion.
| Situation | Is it a change? | Where it goes |
|---|---|---|
| Design takes 45 hours instead of 40 because the estimate was low | No, this is variance | Variance report and forecast |
| The client asks for a reporting dashboard that was not in scope | Yes, a scope change | Change request |
| The hosting vendor raises prices before you have bought anything | Usually yes, an external cost change | Change request, often funded from contingency |
| A tester is sick for a week and the work slips | No, this is a schedule variance | Forecast, and a risk review |
| The sponsor cuts the project end date by a month | Yes, a constraint change | Change request, re-baseline the schedule and cost |
The test is whether the thing you committed to deliver, or the conditions you committed under, have changed. If you are only doing the same work for a different cost, that is variance, and you report it and forecast it. You do not rewrite the baseline to hide it.
The change-control steps
A basic procedure has five steps, and a small project can run all of them in one short meeting.
- Raise a change request. Anyone can raise one. It states what is changing and why. Give it an ID such as CR-001 so it can be referenced later.
- Assess the impact. Estimate the change with the same method you used for the original budget: hours times rate for labor, quoted prices for non-labor items. Add the effect on schedule and on risk. Price it in full, even if you plan to absorb part of it.
- Decide the funding. Choose between drawing on contingency, increasing the budget, or removing other scope to pay for it.
- Approve or reject. The person who owns the budget decides. A project manager can often approve small changes under a stated threshold. Larger ones go to the sponsor.
- Update the baseline and log it. Create a new baseline version. Never overwrite the old one.
Funding a change: contingency or new budget
Contingency exists to absorb costs you expected might happen but could not price precisely. A change request that draws on contingency moves money inside the budget. The total stays the same, and the unspent contingency shrinks. A change that is funded by new money raises the total.
Use these decision criteria:
- Small, unforeseen cost inside the original scope. Draw on contingency. An example is a license that costs more than quoted.
- New scope the sponsor wants. Increase the budget. Contingency was sized for risk in the agreed scope, not for new features.
- New scope the sponsor wants but cannot fund. Trade it against other scope, and remove something of equal cost.
- Mixed. Split the funding, and record the split in the change request.
Many organizations separate two reserves. Contingency belongs to the project manager and covers known risks. A management reserve is held above the project, for unknown events. It needs sponsor approval to release. If your organization has one, say so in the change request, because it changes who must approve.
Worked example
Start with the budget built earlier in the tutorial. Labor is 17500.00, non-labor items are 1800.00, and contingency is 1930.00, for a total of 21230.00.
Midway through, the client asks for a reporting screen. Development estimates 30 extra hours at 90.00 per hour, so the cost is 2700.00. The sponsor approves CR-001. They agree to draw 1500.00 from contingency and add the remaining 1200.00 to the budget.
The code below keeps every baseline version in a list. Applying a change appends a new version and never edits an old one.
from dataclasses import dataclass
@dataclass(frozen=True)
class Baseline:
version: int
packages: dict
contingency: float
@property
def total(self):
return sum(self.packages.values()) + self.contingency
@dataclass(frozen=True)
class ChangeRequest:
id: str
reason: str
deltas: dict
from_contingency: float
status: str = "proposed"
def apply_change(history, cr):
if cr.status != "approved":
raise ValueError(f"{cr.id} is {cr.status}, not approved")
current = history[-1]
if cr.from_contingency > current.contingency:
raise ValueError(f"{cr.id} asks for more contingency than remains")
packages = dict(current.packages)
for name, delta in cr.deltas.items():
packages[name] = packages.get(name, 0.0) + delta
new = Baseline(
version=current.version + 1,
packages=packages,
contingency=current.contingency - cr.from_contingency,
)
return history + [new]
history = [
Baseline(
version=1,
packages={
"Design": 3200.0,
"Development": 10800.0,
"Testing": 3500.0,
"Software licenses": 1200.0,
"Hosting": 600.0,
},
contingency=1930.0,
)
]
cr = ChangeRequest(
id="CR-001",
reason="Client requested a reporting screen",
deltas={"Development": 30 * 90.0},
from_contingency=1500.0,
status="approved",
)
history = apply_change(history, cr)
for b in history:
print(f"v{b.version}: total {b.total:.2f}, contingency {b.contingency:.2f}")
print(f"Budget increase: {history[-1].total - history[0].total:.2f}")
print(f"Development v1 {history[0].packages['Development']:.2f}, "
f"v2 {history[1].packages['Development']:.2f}")Running it prints:
v1: total 21230.00, contingency 1930.00
v2: total 22430.00, contingency 430.00
Budget increase: 1200.00
Development v1 10800.00, v2 13500.00The check is that 2700.00 of new cost was funded by 1500.00 of contingency and 1200.00 of new budget. The total moved from 21230.00 to 22430.00, which is exactly the 1200.00 increase.
Two details in the code matter. The dataclasses are frozen, so b.version = 5 raises an error and a baseline cannot be edited by accident. The function rejects any change whose status is not approved, so an unapproved request cannot change a number.
Reporting against two baselines
After CR-001 you have two valid reference points: the original baseline (v1) and the current approved baseline (v2). Report variance against the current one, because it reflects what the sponsor agreed to fund. Keep the original visible as well, so readers can see how far the project has moved from the first commitment.
A short table does this well:
| Measure | Original (v1) | Current (v2) | Change |
|---|---|---|---|
| Development budget | 10800.00 | 13500.00 | +2700.00 |
| Contingency remaining | 1930.00 | 430.00 | -1500.00 |
| Total budget | 21230.00 | 22430.00 | +1200.00 |
The forecast calculation from the previous chapter still applies, with one adjustment. Variance is budget minus forecast, and the budget in that formula is now the v2 figure. If Development's actual cost so far is 5000.00 and 6200.00 remains, the forecast is 11200.00. Against v1 that gives a variance of -400.00. Against v2 it gives +2300.00, because the extra scope came with extra budget. Both numbers are correct, but they answer different questions, so label them.
Common errors
- Re-baselining to erase an overrun. An estimate error is variance. Approving a change for it removes the signal. If a project is hopelessly off, a full re-plan can be legitimate, but it needs sponsor approval and the old baseline must be kept.
- Approving after the fact. If work starts before approval, the cost is already incurred and the review becomes a formality. For genuine emergencies, allow verbal approval but record it in writing within a day.
- Pricing only the labor. Changes also add testing, documentation, and often hosting or licenses. Run the same estimating steps you used for the original scope.
- Forgetting the contingency effect. If contingency was set as 10% of direct costs, new scope arguably deserves its own reserve. Decide this explicitly. Either add 10% to the change or state that the change is estimated without contingency.
- Losing small changes. Ten changes of 150.00 each total 1500.00. Log every change regardless of size, even if a manager can approve small ones without a meeting.
- No rejected-change record. Rejected requests come back. A log that says "rejected on 12 March, sponsor declined funding" saves the same debate.
The change log
The change log is the audit trail. It can be a spreadsheet tab with one row per request. At minimum record these columns:
- Change ID and date raised
- Requester and description
- Cost impact, split by funding source
- Schedule impact
- Decision, decision date, and approver
- Baseline version created
With the log and the saved baseline versions, anyone can rebuild how the budget got from 21230.00 to its current value, one approved step at a time.
Exercise
Testing is budgeted at 3500.00 and is forecast to cost 3900.00 because the tester estimate was too low. No scope has changed. Should you raise a change request to increase the Testing budget to 3900.00? Explain what to do instead.
Show answer
No. The scope is the same and only the cost of doing it differs from the estimate, so this is variance, not a change. Leave the baseline at 3500.00, report a variance of -400.00 in the forecast, and note the cause. If the overrun should be covered from contingency, raise a request for that draw, because spending a reserve needs approval. That request moves money from contingency to the package. It does not erase the variance record.
Exercise
Using the v2 baseline from the worked example (total 22430.00, contingency 430.00), a second request, CR-002, adds 800.00 of hosting cost and asks to draw all of it from contingency. Can apply_change accept it, and what are the new total and contingency if so?
Show answer
It cannot. The request asks for 800.00 but only 430.00 of contingency remains, so apply_change raises a ValueError. The change must be split, for example 430.00 from contingency and 370.00 as a budget increase, or fully funded with new budget. With that split the new total is 22430.00 + 800.00 - 430.00 = 22800.00 and contingency becomes 0.00.