Sub topic 11
Scheduling Deliveries and Development Milestones
This chapter assumes you already know the basic vocabulary (category, silhouette, season, SKU) and the seasonal design and buying calendar. You should also be comfortable with a simple spreadsheet. It also assumes you have a draft breadth and depth: a style count, colors per style, sizes per style, and a unit budget. Here you spread that range across the selling season and work out the dates by which each style must be finished.
What the schedule decides
A line plan lists what you will make. The delivery schedule says when each style reaches stores or the warehouse. The development timeline says when each step must finish for that to happen. Both belong in the plan, because they change what the plan can contain.
Three decisions come out of this chapter:
- How many delivery windows ("drops") the season has, and which styles go in each.
- How the unit budget splits across those drops.
- The latest date for each development milestone, counted back from the in-store date.
Choosing delivery windows
A delivery window is a period in which a group of styles arrives and goes on sale. Choose windows from three inputs:
- Customer demand timing. Knitwear sells when the weather turns cold. Swimwear sells before the holidays. A style that arrives after its peak is sold on markdown.
- Floor refresh cadence. Many retailers want something new every four to six weeks. Fewer, larger drops are cheaper to produce and ship. More, smaller drops keep the floor fresh but thin out the units per SKU.
- Supply limits. Mill lead times, factory capacity, and shipping mode set the earliest realistic arrival for each category.
A typical three-drop season looks like this:
| Drop | In-store | Role in the season | Typical content |
|---|---|---|---|
| 1 | Early February | Launch and brand statement | Core styles, new color story, lighter knits |
| 2 | Mid March | Main volume | Core and fashion styles across all categories |
| 3 | Late April | Refresh and transition | Fashion and statement styles, seasonal colors |
Match the drop to the product role. Core styles are the dependable sellers and should be in stores early and stay in stock, so they usually load Drop 1 and Drop 2. Fashion and statement styles carry more risk, so placing some late lets you react to early sales and place a smaller, later order.
Allocating styles and units across drops
Start from the totals in your breadth and depth work. Assume 40 styles, 3 colors per style, 5 sizes per style, and a 12,000-unit budget. Distribute styles first, then units. Units should follow expected sales, not style count. A launch drop usually needs enough depth to survive several weeks of selling, and a late drop is often smaller.
This script checks each drop's depth. It uses the same arithmetic as the breadth and depth check: color-ways are styles times colors, and SKUs are color-ways times sizes.
drops = {
"Drop 1": (14, 4200),
"Drop 2": (14, 4800),
"Drop 3": (12, 3000),
}
colors_per_style = 3
sizes_per_style = 5
assert sum(s for s, _ in drops.values()) == 40
assert sum(u for _, u in drops.values()) == 12000
for name, (styles, units) in drops.items():
color_ways = styles * colors_per_style
per_color_way = units / color_ways
per_sku = per_color_way / sizes_per_style
print(f"{name}: {styles} styles, {color_ways} color-ways, "
f"{per_color_way:.1f} units/color-way, {per_sku:.1f} units/SKU")The output is:
Drop 1: 14 styles, 42 color-ways, 100.0 units/color-way, 20.0 units/SKU
Drop 2: 14 styles, 42 color-ways, 114.3 units/color-way, 22.9 units/SKU
Drop 3: 12 styles, 36 color-ways, 83.3 units/color-way, 16.7 units/SKUThe overall average is 20 units per SKU, but Drop 3 falls to 16.7. Averages hide this kind of gap. Suppose the plan sets a floor of 20 units per SKU. Drop 3 then fails the check, even though the season total passes. Fix it by moving units into Drop 3, reducing its colors, or cutting styles from it. Document whichever you choose.
Working backward from the in-store date
Development milestones are set by counting back from the in-store date. Each step has a duration, and the steps run in sequence. The in-store date minus the sum of all durations gives the latest date to start. If that date is already in the past, the schedule is impossible as drawn.
A simplified sequence for a Drop 1 style:
| Step | Weeks | What must be true at the end |
|---|---|---|
| Range review and line freeze | 2 | The style list, colors, and prices are approved |
| Fabric booking and tech packs | 4 | Fabric is committed and the specification is complete |
| Prototype and fit round | 6 | The fit is approved or the style is dropped |
| Sales sample and approval | 3 | Buyers or merchants have confirmed quantities |
| Bulk production | 8 | Finished goods are packed |
| Shipping and receiving | 5 | Goods are in the distribution center |
These durations are illustrative. Replace them with your own factory and freight data. This script counts backward from an in-store date:
from datetime import date, timedelta
in_store = date(2027, 2, 1)
steps = [
("Range review and line freeze", 2),
("Fabric booking and tech packs", 4),
("Prototype and fit round", 6),
("Sales sample and approval", 3),
("Bulk production", 8),
("Shipping and receiving", 5),
]
end = in_store
schedule = []
for name, weeks in reversed(steps):
start = end - timedelta(weeks=weeks)
schedule.append((name, start, end))
end = start
for name, start, finish in reversed(schedule):
print(f"{name:<32} {start} -> {finish}")The output is:
Range review and line freeze 2026-07-20 -> 2026-08-03
Fabric booking and tech packs 2026-08-03 -> 2026-08-31
Prototype and fit round 2026-08-31 -> 2026-10-12
Sales sample and approval 2026-10-12 -> 2026-11-02
Bulk production 2026-11-02 -> 2026-11-30
Shipping and receiving 2026-11-30 -> 2027-02-01Wait: the bulk production and shipping lines above are wrong if you run the code, because the script counts durations as written. Bulk production runs 8 weeks and shipping runs 5 weeks, so the real output is:
Range review and line freeze 2026-07-20 -> 2026-08-03
Fabric booking and tech packs 2026-08-03 -> 2026-08-31
Prototype and fit round 2026-08-31 -> 2026-10-12
Sales sample and approval 2026-10-12 -> 2026-11-02
Bulk production 2026-11-02 -> 2026-12-28
Shipping and receiving 2026-12-28 -> 2027-02-01Use the second listing. The first listing shows the bulk production end date as 2026-11-30, but 8 weeks after 2026-11-02 is 2026-12-28.
Correction to the diagram: the last task should read Shipping and receiving :b2, 2026-12-28, 35d. Use that line in your own chart.
Lead times differ by category and fabric
One shared timeline is a starting point. Real lead times vary:
- Imported or specialty fabrics add weeks for mill production and dyeing. Book them first, since the fabric usually sets the critical path.
- Knitwear may require yarn purchase and several sample rounds.
- Printed or embellished styles need artwork approval and lab dips, which add rounds.
- Woven basics in stock fabrics can run much shorter.
Group styles by lead time, not only by category. If the three longest-lead styles all sit in Drop 1, the line freeze for that drop moves earlier for everyone.
Protecting the schedule
Add a buffer before any date you cannot move. Common sources of slippage:
- Factory and holiday closures. Lunar New Year shuts many factories for two or more weeks. A bulk run that crosses it needs extra time.
- Late approvals. A fit round that takes a week longer pushes every later date by a week, since the steps are sequential.
- Fabric delays. Late fabric delays cutting, sewing, and shipping together.
- Air freight rescue. It saves the date but cuts margin. Check the cost against the style's target margin before agreeing to it.
Mark a few milestones as gates: line freeze, fit approval, and fabric commitment. At each gate, decide whether to proceed, cut the style, or move it to a later drop. A planned gate review costs less than a late discovery.
Common errors
- Dates set forward from today. Planners choose a convenient start date and see where they land. Start from the in-store date.
- All depth in one drop. The season total looks fine, but a later drop runs below the unit floor.
- Ignoring replenishment. Core styles that sell through need a reorder path. Reserve some capacity or a fast-follow slot.
- One timeline for every style. Long-lead fabric and print styles need earlier gates.
Exercise
A season has 12 styles in its last drop, each in 3 colors and 5 sizes, with 2,400 units budgeted. The plan sets a floor of 20 units per SKU. Does the drop pass? If not, name one way to fix it.
Show answer
The drop has 12 × 3 = 36 color-ways and 36 × 5 = 180 SKUs. 2,400 / 180 = 13.3 units per SKU, which is below 20. To reach 20 units per SKU with 2,400 units, you can support 2,400 / 20 = 120 SKUs, which is 24 color-ways. Reduce the drop to 24 color-ways (for example 12 styles in 2 colors, or 8 styles in 3 colors). Alternatively, move units into the drop from another drop.
Exercise
A style must be in the distribution center, ready to ship to stores, by 1 March 2027. Shipping and receiving take 5 weeks, and bulk production takes 8 weeks. When must shipping start, and when must bulk production start?
Show answer
Shipping must start 5 weeks before 1 March 2027, which is 25 January 2027. Bulk production ends on 25 January, so it must start 8 weeks earlier, on 30 November 2026.