Sub topic 5
Break big projects into small steps
This chapter assumes you already capture tasks in one inbox and can rewrite a vague item as a next action that starts with a verb. Here you will learn to take an item that is too big for a single sitting and turn it into steps you can finish one at a time.
Why a project is not a task
A project is any outcome that needs more than one action to finish. "Plan the Q3 presentation" is a project. "Draft a three-bullet outline of the Q3 presentation" is a task inside it.
A project on a to-do list causes three problems:
- You cannot start it. There is no first move, so the item sits there and you feel a small pull of dread each time you see it.
- You cannot finish it in one session. It never fits into a daily list, so it is passed over in favor of easier items.
- You cannot see progress. Until the last step is done, the item looks exactly as it did on day one.
The fix is to keep two levels. The project is the outcome. The next actions are the steps that move it forward. Only next actions go on your daily list.
A working model: outcome, steps, next action
Every project has three parts.
- Outcome. A sentence describing the finished state, written in the past tense or as a clear condition. For example: "The Q3 presentation is delivered and the team has the slides."
- Steps. The list of actions needed to reach the outcome, in rough order.
- Next action. The one step you could start right now. Exactly one step per project is marked as next, even if later steps are known.
Keeping only one next action visible per project stops the list from filling with items that are blocked or not yet relevant.
How to break a project down
Use this sequence whenever a project is too large to act on.
Step 1: State the outcome
Write what "finished" looks like in one sentence. If you did the previous chapter's work on defining done, reuse that sentence. If you cannot write it, the project is not clear yet, and your first step is to clarify it, for example "Ask Dana what the presentation must cover (5 min)".
Step 2: List steps without ordering them
Brain-dump every action you can think of. Do not sort yet. Write them as verbs plus objects: "Collect Q2 numbers", "Choose a slide template", "Book the meeting room".
Step 3: Order and group
Put steps in the order they must happen. Mark dependencies, meaning steps that cannot start until another one finishes. For example, you cannot "Rehearse the talk" before "Build the slides".
Step 4: Check the size of each step
Each step should pass three checks:
- It starts with a verb.
- You can finish it in one sitting.
- You can say when it is done.
If a step fails any check, split it again. "Build the slides" is still big. "Create slides 1 to 3 from the outline (45 min)" passes.
Step 5: Pick the next action
Mark the first step that you can start now, with nothing blocking it. That step goes on your list. The others stay in the project notes.
Worked example: the Q3 presentation
Start with the vague item "Presentation" and the outcome "The Q3 results presentation is delivered to the leadership team on 20 November."
Project: Q3 presentation
Outcome: Q3 results are presented to leadership on 20 Nov, and slides are shared afterward
Steps (in order):
1. Ask Dana which topics leadership wants covered (5 min) <- NEXT
2. Collect Q3 numbers from the finance dashboard (30 min)
3. Draft a three-bullet outline (30 min)
4. Create slides 1 to 3 from the outline (45 min)
5. Create slides 4 to 6 from the outline (45 min)
6. Ask Sam to review the draft slides (5 min)
7. Revise slides using Sam's comments (30 min)
8. Rehearse the talk once with a timer (30 min)
9. Send the slides to leadership after the meeting (5 min)Notice what the breakdown does:
- Step 1 is tiny and has no blockers, so it removes the barrier to starting.
- Step 6 is a request to another person. After you send it, you are waiting, so you would record that on a waiting list with a date to check back.
- Every step has a duration, which prepares you for the estimating chapter that follows.
- The total is about 3 h 45 min of work spread over several days, which is easy to fit into daily plans but impossible to fit into one.
Choosing the right step size
Steps that are too large stay stuck. Steps that are too small create clutter. A useful range is 5 to 90 minutes.
| Step size | Symptom | What to do |
|---|---|---|
| Over 2 hours | You keep postponing it | Split it into parts you can finish in one sitting |
| 15 to 90 minutes | You can start and finish it | Keep it as is |
| Under 5 minutes | Writing it costs as much as doing it | Do it now, or group it with similar small steps |
For very small steps, batch them. "Reply to three vendor emails (15 min)" is better than three separate list items.
Common ways to split a project
Different projects split naturally in different ways. If you are stuck, try one of these.
- By phase. Research, draft, review, finalize. Works well for writing and planning.
- By deliverable. One step per output, such as each slide set, each chapter, or each form.
- By person. Group the steps that need input from a specific colleague, so you can ask once.
- By place or tool. Group steps that need the same setting, such as "at the bank" or "in the spreadsheet".
- By the first thing that unblocks you. If you do not know where to start, ask "what is the smallest thing that would make the rest clearer?" and use that as step 1.
Common errors
Writing a project name as a task
"Website redesign" on the daily list is a project name. The symptom is that you read it every day and never act. Move it to a project list and put only its next action on the daily list.
Planning every step in detail
Detailed plans for steps weeks away go out of date. Break down fully only the next two or three steps. Leave later phases as rough bullets and refine them when you reach them.
Having no next action
A project with no marked next action is stalled. During your weekly review, check every project and confirm it has exactly one next action you could start today.
Hiding waiting steps
If a step depends on someone else, the next action is usually the request, not the result. Write "Ask Sam to review the slides" and track the reply separately. Otherwise the project looks like it is moving when it is not.
Treating a recurring chore as a project
"Pay rent every month" is a repeating task, not a project. Projects end. If it never ends, use a recurring reminder instead.
A reusable template
Keep a simple structure in your list tool or on paper. This version fits in any plain-text note.
Project: <short name>
Outcome: <one sentence describing the finished state>
Deadline: <date or "none">
Next action: <verb + object (duration)>
Later steps:
- <step> (duration)
- <step> (duration)
Waiting for:
- <person>: <what> (check back on <date>)Practice
Exercise
You have the project "Organize the team offsite" on your list. Write the outcome sentence, then list four steps with durations, and mark which one is the next action. Make sure each step starts with a verb and can be finished in one sitting.
Show answer
One valid answer. Outcome: "The team offsite on 12 December is booked, the agenda is shared, and everyone has confirmed attendance." Steps: 1. Ask the team for date and budget constraints (10 min) <- NEXT. 2. List three possible venues with prices (45 min). 3. Book the chosen venue and pay the deposit (20 min). 4. Send the agenda and a confirmation request to the team (30 min). Any answer is good if the outcome describes a finished state, every step starts with a verb, each takes under about 90 minutes, and exactly one step is marked as next and is not blocked by another step.
Exercise
A step reads "Write the report (6 h)". What is wrong with it, and how would you fix it?
Show answer
It is too large to finish in one sitting, so it will keep being postponed and cannot fit into a daily plan. Split it into steps of 30 to 90 minutes, for example: "Outline the report's five sections (30 min)", "Write the findings section (90 min)", "Write the recommendations section (60 min)", "Edit the full draft for clarity (60 min)", "Format and send the report (30 min)". The first of these becomes the next action.