Where the Charter Fits in DMAIC
Prerequisites
This chapter assumes you know what a process, a defect, and a metric are. You should also recognize the five DMAIC phases: Define, Measure, Analyze, Improve, and Control.
Where the charter fits in DMAIC
DMAIC is a structured method for improving an existing process. The project charter is the main output of the Define phase. It records the problem the team will solve, why it matters, and how the team will know it has succeeded. Later phases depend on it. Measure confirms the baseline the charter names. Analyze looks for causes of the problem the charter describes. Improve tests fixes against the goal. Control keeps the gains in place.
What a project charter is and what it contains
A project charter is a short document that authorizes a team to work on a problem. It usually holds the business case, problem statement, primary metric, goal statement, scope, team roles, milestones, and risks. A sponsor, often a senior leader, signs it before the team starts Measure.
Making the business case
The business case explains what it costs to leave the problem alone. State the cost in money, time, or customer impact, and use measured figures where you can. "Errors are costly" will not win resources. "Rework adds about $18 per order" will.
From customer needs to critical-to-quality requirements
Voice of the customer (VOC) is what customers say they need. Critical-to-quality (CTQ) requirements turn those needs into measurable limits, such as "delivery within two days." CTQs link the customer's view to the metric the charter tracks.
Writing the problem statement
The problem statement describes the gap, its size, its location, and its impact. It does not name a cause or a fix. Back every number with measured data.
Exercise
Which statement is a problem statement rather than a solution? (a) "We need new order software." (b) "From January to June 2026, 6.2% of orders at the Dayton center contained a data entry error."
Show answer
Statement (b). It gives the size, location, and period without naming a fix.