Sub topic 3
Naming the sponsor, project lead, and team
This chapter assumes you know the five DMAIC phases (Define, Measure, Analyze, Improve, Control), can write a problem statement, and have a draft goal statement with a baseline. The examples use the Dayton service center project: a 6.2% order entry error rate, with a target of 3.0% by 2026-12-18.
Naming the sponsor, project lead, and team
The sponsor is the senior leader who owns the business result and can remove barriers. The project lead, often a Green Belt, runs the project day to day. Team members supply process knowledge, such as a service representative, an order management analyst, and a finance partner. Record each person by name and role, and confirm that each has agreed to the time commitment.
Planning the timeline and phase milestones
Set a completion date for each DMAIC phase. Milestones give the sponsor checkpoints to judge progress. The final milestone should match the goal deadline, and the plan should leave time for the eight-week sustain period in Control.
| Phase | Milestone date |
|---|---|
| Define | 2026-07-17 |
| Measure | 2026-08-14 |
| Analyze | 2026-09-11 |
| Improve | 2026-10-30 |
| Control | 2026-12-18 |
Recording risks, assumptions, and constraints
A risk is an event that could hurt the project. An assumption is a fact you accept without proof, so test it early. A constraint is a limit you cannot change.
- Risk: a November order peak may strain the pilot.
- Assumption: the rework log is complete and accurate.
- Constraint: no budget for new software licenses.
Reviewing the charter and getting sign-off
Walk the draft through with the sponsor before the Measure phase starts. Revise until the sponsor agrees, then record the signature and date.
Common charter mistakes and how to fix them
- Embedded solution. "Automate order entry" names a fix. Describe only the gap.
- Vague goal. "Improve quality" has no metric or deadline. State the metric, baseline, target, and date.
- No named sponsor. Without a sponsor, the team cannot get resources. Name one person who can approve them.
- Open-ended scope. Without a stop point, the team cannot tell what is finished. Define both the process start and end.
Worked example: team and milestones
| Charter element | Dayton example |
|---|---|
| Sponsor | Director of Customer Operations |
| Project lead | Green Belt, Customer Operations |
| Team | Service representative, order management analyst, finance partner |
| Final milestone | 2026-12-18, the goal deadline |
| Top risk | November order peak |
Exercise
A draft charter lists "Director of Customer Operations" as the sponsor and sets the Control milestone to 2026-12-31, after the goal deadline of 2026-12-18. Name the two problems and how to fix them.
Show answer
First, the milestone falls after the goal deadline, so move the Control milestone to 2026-12-18 or earlier and leave time for the eight-week sustain period. Second, the sponsor role is named but the sponsor has not reviewed or signed the charter. Schedule a sponsor review and record the signature and date.