Sub topic 2
Choosing the Primary Metric and Establishing a Baseline
Prerequisites
This chapter assumes you know the five DMAIC phases, what a defect is, and how to calculate a rate from counts. Familiarity with the problem statement from the previous chapter helps.
Choosing the primary metric
The primary metric is the single number that shows whether the project succeeds. Choose one metric that reflects the customer requirement, then write an operational definition: the exact formula and counting rules, so two analysts calculate the same value.
For the Dayton service center project, the metric is:
order entry error rate = orders with at least one data entry error / total orders entered
Record the data source too. Here it is the order management system rework log.
Establishing the baseline
The baseline is current performance, measured over a stable period before any change. Use several months of data where possible, and check that the log is complete. Note any unusual periods, such as holidays or system outages.
For January to June 2026, the Dayton center recorded 770 orders with errors out of 12,400 entered:
| Item | Value |
|---|---|
| Numerator | 770 orders with errors |
| Denominator | 12,400 orders entered |
| Baseline | 6.2% |
> Caution: a baseline is only as reliable as its data source. Verify the rework log before you set a target.
Writing a SMART goal statement
A SMART goal is Specific, Measurable, Achievable, Relevant, and Time-bound. Combine the metric, baseline, target, and deadline in one sentence:
Reduce the order entry error rate from 6.2% to 3.0% or lower by 2026-12-18, and sustain it for 8 consecutive weeks.
The goal names no solution. It states the result the team must reach, not how it will reach it.
Setting scope: in, out, and process boundaries
Scope defines where the process starts and stops, and what the project covers.
- Process start: customer order received by a service representative
- Process end: order released to the warehouse
- In scope: phone and email orders entered at the Dayton service center
- Out of scope: web orders, warehouse picking errors, and changes to the software vendor contract
Exercise
The Dayton team wants to include web orders in scope. Give one reason to keep them out of this project, and one reason to add them.
Show answer
Keep them out because the project's baseline covers only phone and email orders, so mixing channels would make the metric hard to interpret. Add them only if the baseline and rework log also cover web orders, and the team agrees the sample is comparable.