Sub topic 10
Running sprint planning with the team
This chapter assumes you know what a product backlog and a user story are, and that you have worked alongside software engineers. It also assumes you have read the earlier chapters on refinement, Definition of Ready, the sprint goal, and capacity and velocity. Here they come together in one meeting.
What sprint planning is for
Sprint planning is the Scrum event where the team decides what it will try to deliver in the coming sprint and how it will start. It produces three things:
- A sprint goal: one outcome the team aims for.
- A selection of backlog items that supports the goal.
- A plan for how the work will get done, at least for the first days.
The developers own the forecast of what they can finish. You own the case for why the work matters and the order of the backlog. Planning is the point where those two things meet. If you arrive with a finished list and ask the team to sign it, you have skipped the conversation the event exists for.
Before the meeting: what you bring
Good planning is mostly decided by preparation. Bring:
- A backlog ordered by priority, with the top items refined and meeting your Definition of Ready.
- A draft sprint goal. It is a proposal, and the team will reshape it.
- Known constraints: holidays, launch dates, dependencies on other teams, and commitments to stakeholders.
- The team's capacity for the sprint and recent velocity. The Scrum Master or team usually supplies these, but you should know the numbers.
- Context on any open questions, such as customer research or data, so you can answer quickly.
Here is a draft goal in the form to aim for:
Sprint goal: Let new customers finish checkout without creating an account.
Why it matters: Guest checkout is our largest known drop-off point in the funnel.
How we will know: A guest can place and pay for an order end to end in staging.
Must-have stories: guest email capture, guest payment, order confirmation email.
Flexible stories: saved cart reminder, address autocomplete.The split between must-have and flexible stories matters later. It tells the team what to protect when something goes wrong.
The flow of the meeting
Planning usually covers three topics: why this sprint is valuable, what can be done, and how it will be done. The diagram shows the typical sequence.
Step 1: Present the goal and the why
Spend five to ten minutes on the goal and the reason behind it. Explain the customer problem, the evidence, and the date pressure if there is one. Then stop and ask what is unclear. Engineers often spot a better route to the same outcome when they understand the purpose, so invite that.
Step 2: Check capacity
Capacity is the working time the team really has this sprint. Subtract vacations, public holidays, planned training, and time for support or on-call duty. Then compare with velocity, which is the number of points the team finished in recent sprints.
A rolling average of recent sprints gives a rough anchor for scope:
import math
completed_points = [21, 18, 24, 20] # points finished in the last four sprints
remaining_points = 85
recent = completed_points[-3:]
average_velocity = sum(recent) / len(recent)
sprints_needed = math.ceil(remaining_points / average_velocity)
print(f"Average velocity (last 3 sprints): {average_velocity:.1f}")
print(f"Forecast: about {sprints_needed} sprints to finish {remaining_points} points")For planning, use the average as a guide for the sprint's size, not as a target. If a sprint has two developers on leave, expect less than the average.
Step 3: Select items and clarify them
Pull items from the top of the backlog, in order. Walk each one through three questions:
- Does it support the sprint goal?
- Does the team understand the acceptance criteria?
- Can the team finish it within the sprint?
Acceptance criteria are where misunderstandings show up. Read a few aloud. Scenarios written as Given/When/Then are easy to check together:
Feature: Password reset by email
Scenario: Registered user requests a reset link
Given a registered user with the email "[email protected]"
When the user submits that email on the reset form
Then the system sends a reset link to that address
And the page shows a confirmation message
Scenario: Unregistered email is submitted
Given no account exists for "[email protected]"
When someone submits that email on the reset form
Then the page shows the same confirmation message
And no email is sentIf a question takes more than a few minutes, note it and move on. Decide afterward whether the item is really ready.
Step 4: Let developers plan the how
Developers decide how to build each item and often split it into tasks. Your role in this part is to be available for questions, not to direct the design. Stay in the room, answer clarifications, and keep notes on any decisions about scope.
Step 5: Confirm the goal and forecast
Close by checking that the goal still reads correctly given what you selected. Ask the team directly whether they believe the plan is achievable. Silence is not agreement. If you sense hesitation, ask what worries them.
Negotiating scope
When the selected work exceeds capacity, scope has to give. Time and team size are fixed for the sprint. Use this order:
- Remove flexible stories first.
- Split a large story so a smaller slice still serves the goal.
- Simplify acceptance criteria, for example by deferring an edge case to a later story.
- Only then revisit the goal itself.
Do not push the team to take on more because a stakeholder wants it. Pressure produces hidden shortcuts, such as skipped testing, and the problem returns as defects.
Common errors
| Error | What happens | Better approach |
|---|---|---|
| Arriving with a fixed list | The team feels the plan was imposed and does not own it | Bring a draft goal and ordered backlog, then plan together |
| Selecting items that do not meet Definition of Ready | Questions pile up mid-sprint | Refine earlier, or leave the item out |
| Filling the sprint to the velocity ceiling | Any surprise breaks the sprint | Leave slack for support and unplanned work |
| Setting a goal that is a list of tickets | The team cannot trade scope when needed | Write one outcome with must-have and flexible items |
| Treating velocity as a promise | Estimates inflate and trust drops | Use it as a planning input only |
What you should have at the end
- A sprint goal the whole team can state in one sentence.
- A sprint backlog ordered by priority, with must-have and flexible items marked.
- Acceptance criteria that the team has read and understood.
- A shared view of risks and dependencies.
- A time-boxed meeting. For a two-week sprint, plan for up to about four hours. Shorter is fine when refinement was good.
Exercise
Your team's average velocity over the last three sprints is 21 points. Two of five developers will be on leave for half of the coming sprint, and a stakeholder asks you to commit to 28 points. What do you do in planning, and in what order do you trim scope if the selection runs over?
Show answer
Treat 21 as an upper reference and reduce it for the reduced capacity, so the team should plan for noticeably fewer points. Do not commit to 28. Explain the capacity numbers to the stakeholder and offer alternatives. If the selection runs over, trim in this order: remove flexible stories, split large stories into a smaller slice that still serves the goal, simplify acceptance criteria, and only then revise the goal. The developers make the final call on what they can forecast.
Exercise
A developer says nothing when you ask whether the plan feels achievable, but looks uneasy. What should you do?
Show answer
Do not treat silence as agreement. Ask an open question such as "What worries you about this plan?" or ask each person for a thumbs-up or a concern. Address the concern by clarifying a story, cutting scope, or splitting an item before the meeting ends.