The 1.5 Sigma Shift and the 3.4 DPMO Goal
This chapter assumes you know how to calculate a mean and understand that a process has variation. It also assumes you know that a defect is a failure to meet a requirement and that one unit can contain several defect opportunities.
What DPMO measures
DPMO means defects per million opportunities. It adjusts the defect count for both the number of units inspected and the number of possible defects per unit.
Use this formula:
\[ \text{DPMO} = \frac{\text{number of defects}} {\text{number of units} \times \text{opportunities per unit}} \times 1{,}000{,}000 \]
For example, suppose a process produces 2,000 forms. Each form has five fields that can contain an error. Inspectors find 12 errors.
\[ \text{DPMO} = \frac{12}{2{,}000 \times 5} \times 1{,}000{,}000 = 1{,}200 \]
The process has 1,200 defects per million opportunities. DPMO counts defects, so one form with two errors contributes two defects.
| Term | Meaning |
|---|---|
| Defect | One failure to meet a requirement |
| Opportunity | One possible place where a defect can occur |
| DPMO | Defects normalized to one million opportunities |
| Yield | The proportion of opportunities without defects |
DPMO is useful when comparing processes with different product volumes or different numbers of requirements. It does not tell you whether every defect has the same business impact. A minor labeling error and a safety failure may contribute equally to DPMO but require very different responses.
From DPMO to sigma level
A sigma level expresses how far the process output is from a specification limit in units of standard deviation. A higher sigma level means a smaller predicted defect rate.
The conversion first turns DPMO into a long-term yield:
\[ \text{yield} = 1 - \frac{\text{DPMO}}{1{,}000{,}000} \]
The corresponding normal-distribution z-score estimates the distance from the process center to the nearest specification limit. Six Sigma reporting then commonly adds a 1.5 sigma shift:
\[ \text{reported sigma level} = Z_{\text{long-term}} + 1.5 \]
from statistics import NormalDist
def sigma_level(dpmo, shift=1.5):
# Short-term sigma level = long-term z-score plus the conventional shift.
if not 0 < dpmo < 1_000_000:
raise ValueError("dpmo must be between 0 and 1,000,000 (exclusive)")
long_term_yield = 1 - dpmo / 1_000_000
return NormalDist().inv_cdf(long_term_yield) + shift
print(sigma_level(3.4)) # approximately 6.0
print(sigma_level(66807)) # approximately 3.0Why use a 1.5 sigma shift?
The shift is a convention used to connect short-term process performance with long-term performance. A process may appear centered during a short study but drift over months because of changes in tools, materials, operators, temperature, calibration, or other conditions.
The model assumes that the long-term process mean can move by as much as 1.5 standard deviations from its short-term position. Under this convention, a process described as “Six Sigma” has a short-term distance of six standard deviations, but its long-term distance is treated as 4.5 standard deviations. A one-sided normal tail at 4.5 standard deviations corresponds to about 3.4 defects per million opportunities.
Using the goal responsibly
The 3.4 DPMO target is a useful benchmark, not a guarantee that every process should pursue the same number. First confirm that the defect definition, opportunity count, inspection method, and time period are consistent. Also check whether defects are independent. A single failure can sometimes create several recorded defects, which may make the DPMO appear worse.
DMAIC uses this measure as a baseline and tracking signal. The team defines opportunities, measures current DPMO, identifies causes of variation, improves the process, and controls it over time. The goal is sustained reduction in customer-relevant defects, not simply a better reported number.
Exercise
A process records 25 defects while producing 10,000 units with four opportunities per unit. What is its DPMO, and what should you verify before comparing it with another process?
Show answer
Its DPMO is 625. Verify that both processes use the same defect definitions, opportunity counts, inspection rules, and measurement period.