Sub topic 4
Common Causes and Special Causes
Assume you know basic arithmetic, percentages, the mean, and the general idea of a business or manufacturing process. This chapter explains how to decide whether variation is part of a process's normal behavior or a signal that something unusual happened.
Two kinds of process variation
Variation means that process outputs are not identical. A delivery process may take slightly different amounts of time. A filling machine may put a little more or less product into each container. Even when people follow the same method, inputs and conditions change.
Six Sigma separates variation into two categories:
- Common-cause variation is the routine variation built into the process. It comes from many small causes that work together.
- Special-cause variation is unusual variation caused by a specific, identifiable change or event.
The distinction matters because the correct response is different. Common causes usually require changing the process itself. Special causes require finding and addressing the unusual condition.
| Type of variation | Typical source | Appropriate response |
|---|---|---|
| Common cause | Normal differences in materials, equipment, or method | Improve or redesign the process |
| Special cause | Broken tool, wrong setting, or unusual event | Investigate and correct the specific cause |
Common-cause variation
Common causes are sometimes called random causes or routine causes. They are not necessarily random in a strict scientific sense. They are causes that occur regularly enough, or in combination, to form the process's usual pattern.
For example, a call center's handling time may vary because of small differences in customer questions, agent experience, and system response time. If these factors remain stable, the process has a predictable amount of variation.
A process affected only by common causes is called statistically stable or in control. This does not mean that every output meets the customer's requirement. A stable process can consistently produce too many defects. Stability describes predictability, not quality.
To reduce common-cause variation, a team might:
- simplify the work method;
- improve equipment maintenance;
- use more consistent materials;
- train people on a clearer standard;
- reduce delays or handoffs; or
- redesign the process using DMAIC.
Changing one operator's behavior may not fix a common cause if the same issue affects the entire system.
Special-cause variation
A special cause creates a result that does not fit the process's usual pattern. Examples include:
- a measuring instrument that loses calibration;
- a machine tool that becomes damaged;
- a new material batch with different properties;
- an inexperienced person using the wrong setting;
- a software update that changes processing time; or
- an unusual temperature, outage, or supplier problem.
Special causes are often easier to investigate because they have a specific time, location, or condition. However, the cause is not automatically obvious. A point that looks unusual is a signal to investigate, not proof of a particular explanation.
The usual response is to contain any immediate risk, verify the data, identify what changed, and correct or document the cause. If the cause becomes part of the normal process, the team must decide whether to remove it or update the process model.
Control charts and response discipline
A control chart displays measurements over time with a center line and calculated control limits. The limits describe the amount of variation expected from the process when only common causes are present. A point outside a limit, or a nonrandom pattern inside the limits, may indicate a special cause.
Control limits are not the same as specification limits. Control limits describe process behavior. Specification limits describe what the customer accepts. A stable process can be outside specification, while an unstable process can temporarily meet specification.
When a control chart signals a special cause, record the time, operator, material, equipment, and conditions. Compare the signal with process knowledge. Do not remove data merely because it is inconvenient. Remove a point only when a documented measurement or data-collection error explains it.
Exercise
A stable process has a mean delivery time of 20 minutes, but its variation causes many deliveries to exceed the customer's 25-minute limit. Should the team search for a special cause in every late delivery?
Show answer
No. The process may be stable but incapable of meeting the specification. The team should reduce common-cause variation or shift the process, while still investigating any separate control-chart signals.