What a value stream map shows and why you draw the current state first
Prerequisites
You should understand a production, service, or software delivery process, be comfortable with simple time and rate arithmetic, and know the basic lean idea of waste.
What a value stream map shows
A value stream map (VSM) is a one-page picture of how material and information move from customer order to delivery. It shows each process step, the inventory waiting between steps, and how work gets scheduled.
Draw the current state first. You cannot improve a process you have not measured. A current-state map records what actually happens, not what the procedure manual says should happen. Future-state design depends on this baseline.
Value-added, necessary non-value-added, and waste
Classify each activity into one of three groups:
- Value-added: work the customer would pay for, such as welding a bracket.
- Necessary non-value-added: work that adds no value but is required today, such as inspection.
- Waste: everything else, such as waiting, rework, and excess inventory.
Treat necessary non-value-added work as a target to reduce, not a permanent fixture.
Choosing a product family and the start and end of the map
Map one product family at a time. A product family is a group of products that pass through similar steps. Start the map where the customer order enters the process and end it at delivery to the customer. Mapping every product at once produces a diagram too large to read.
Mapping symbols and layout
Arrange process boxes in process order, left to right. Use triangles for inventory between steps and arrows for material flow. Place a timeline along the bottom for wait times and process times.
Walking the process and collecting data
Go to the place where the work happens, called the gemba. Watch the process yourself and record cycle time, changeover time, batch size, uptime, and inventory count at each step.
Take several observations at different times. Suppose a welding step runs a 39-second cycle, and you count 5 parts waiting at 9:00 but 60 parts at 14:00. A single reading would hide that swing. Record each value, note whether it is measured or estimated, and keep the source of each number.
Exercise
Why should you take several observations at each step instead of one?
Show answer
Inventory and cycle times vary during the day, so one reading can misrepresent the typical state.