Sub topic 2
Drawing process boxes and filling in data boxes
This chapter assumes you can classify activities as value-added or waste, and that you can divide one quantity by another to get a rate.
Drawing process boxes and filling in data boxes
Draw one process box for each step where work changes the product or the information. Place the boxes in flow order, left to right. Under each box, add a data box with values you measured on the floor: cycle time (C/T), changeover time (C/O), uptime, batch size, and operator count. Record measured values, not design values.
Customer demand and takt time
Takt time is the pace the customer requires. It equals available working time divided by customer demand.
AVAILABLE_SECONDS_PER_DAY = 27000 # 7.5 working hours
DAILY_DEMAND = 450 # units per day
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND
print(f"Takt time: {takt_s:.0f} s per unit")The output is Takt time: 60 s per unit. A step with a cycle time above 60 seconds cannot keep up with demand on its own.
Material flow, inventory, and push versus pull
Draw a triangle between two processes to show inventory waiting in a queue, and write its quantity inside the triangle. In push flow, a step produces on its own schedule and sends output downstream whether or not that output is needed. In pull flow, the downstream step signals what it needs, and upstream steps respond. Large inventory triangles usually point to push flow.
Information flow and how work is scheduled
Draw information flow as dashed arrows from the planning function or the customer to each process. Name the signal, such as a weekly forecast, a daily schedule, or a kanban card, and note how often it arrives. Information that moves by paper or email can add days to lead time.
Exercise
A line runs 27,000 seconds per day and the customer orders 540 units per day. What is the takt time?
Show answer
27000 / 540 = 50 seconds per unit. Any step with a cycle time above 50 seconds cannot meet demand alone.