Building the timeline: wait time, process time, and lead time
This chapter assumes you already have a current-state map with process boxes, measured cycle times, inventory counts between steps, and the daily customer demand. You should also be comfortable converting between units per day and seconds per unit.
Building the timeline: wait time, process time, and lead time
The timeline sits at the bottom of the map. Each step gets two numbers. Process time is the seconds of work done on each unit. Wait time is the days a unit sits in the queue before that step. Lead time is the sum of both across the whole stream.
Wait time equals the inventory in front of a step divided by daily demand. The following script builds the timeline and flags any step slower than takt time, which is the pace needed to meet demand.
AVAILABLE_SECONDS_PER_DAY = 27000 # 7.5 working hours
DAILY_DEMAND = 450 # units per day
takt_s = AVAILABLE_SECONDS_PER_DAY / DAILY_DEMAND # 60.0 s per unit
steps = [
{"name": "Stamping", "cycle_s": 1, "queue_units": 4500},
{"name": "Welding", "cycle_s": 39, "queue_units": 1350},
{"name": "Assembly", "cycle_s": 46, "queue_units": 900},
{"name": "Shipping", "cycle_s": 62, "queue_units": 450},
]
total_wait_days = sum(s["queue_units"] / DAILY_DEMAND for s in steps)
total_wait_s = total_wait_days * AVAILABLE_SECONDS_PER_DAY
total_process_s = sum(s["cycle_s"] for s in steps)
lead_time_s = total_wait_s + total_process_s
print(f"Total wait: {total_wait_days:.0f} working days")
print(f"Total process time: {total_process_s} s")
print(f"Lead time: {lead_time_s / AVAILABLE_SECONDS_PER_DAY:.2f} working days")
for s in steps:
if s["cycle_s"] > takt_s:
print(f"{s['name']} cycle time exceeds takt time")Process cycle efficiency and a Little's Law cross-check
Process cycle efficiency (PCE) is total process time divided by lead time. For this map, process time is 148 s and lead time is about 432,148 s, so PCE is about 0.034 percent. Almost all of the lead time is waiting.
Little's Law gives an independent check. Average lead time equals work in process divided by throughput. Here, 7,200 units sit in the stream and 450 units ship per day, so lead time is 16 days. The timeline gave 16.01 days, so the two numbers agree.
> Note: Little's Law holds only when the stream is in a steady state, meaning inventory is not steadily growing or shrinking.
Reading the map: bottlenecks, excess inventory, and improvement opportunities
Shipping takes 62 s per unit, which is longer than the 60 s takt time. It cannot keep up with demand, so it is the bottleneck. Stamping runs in 1 s but holds 4,500 units, or 10 days of stock. That inventory is a candidate for reduction, not a sign of a fast step.
Mark these on the map as improvement opportunities. Mark push flow where a step produces ahead of what the next step needs.
Common pitfalls when mapping the current state
- Using design or target cycle times instead of measured ones.
- Drawing a single average for a step that varies widely between shifts.
- Forgetting to count inventory that sits between steps, which understates wait time.
- Mixing units, such as hours for process time and days for wait time, in one total.
From current state to future state
Once the timeline is complete, the bottleneck, excess queues, and push points become the inputs to future-state design. Each marked opportunity should point to a specific number on the timeline so the redesign can be measured against it.
Exercise
Exercise
Using the map above, if Shipping's cycle time were reduced to 55 s and the queue ahead of Stamping stayed at 4,500 units, what would the total lead time be in working days, rounded to two decimals?
Show answer
Total wait stays at 16 days, or 432,000 s. Process time becomes 1 + 39 + 46 + 55 = 141 s. Lead time is 432,141 s, which is 16.00 working days.