Sub topic 13
Shortcuts, Traps and Sanity Checks for CAT
This chapter assumes that you know fractions, reciprocals, ratios, LCM, direct and inverse proportion, and simple linear equations. You should also be comfortable representing a person's work as a rate, such as \(1/10\) job per day.
A fast setup for every problem
Use this sequence before calculating:
- Identify the complete work: one job, one tank, or a chosen number of units.
- Convert each worker or pipe into a rate.
- Use positive rates for work done or water entering.
- Use negative rates for work undone, outlets, or leaks.
- Add rates only during periods when the corresponding workers or pipes are active.
- Divide the remaining work by the current net rate.
The LCM method is often fastest in CAT questions. If A takes 12 days and B takes 18 days, choose 36 units as the total work. Their rates become 3 and 2 units per day. This avoids repeated fraction calculations.
from fractions import Fraction
# A completes 1/12 and B completes 1/18 of the job each day.
rate = Fraction(1, 12) + Fraction(1, 18)
time = 1 / rate
print(time) # 36/5 daysShortcuts that save time
Use efficiency ratios
If A is twice as efficient as B, their rates are in the ratio \(2:1\). Their times are in the inverse ratio \(1:2\). Do not assign the same ratio to their times.
For a fixed amount of work:
\[ \text{efficiency} \propto \text{rate} \propto \frac{1}{\text{time}} \]
If A and B work together and their efficiency ratio is \(3:2\), then A completes \(3/5\) of their combined work and B completes \(2/5\), provided both work for the same duration.
Split the timeline
When someone joins or leaves, divide the problem into intervals. Find the work completed in each interval, subtract it from the total, and solve for the remaining time. Never use one combined rate across a period when the group changes.
Use work units for wages
Wages should follow contribution, not simply the number of days present. If A does 24 units and B does 16 units, divide the total wage in the ratio \(24:16 = 3:2\).
Apply the man-days-hours check
For the same kind of work:
\[ \frac{M1D1H1}{W1} = \frac{M2D2H2}{W2} \]
Here, \(M\) is the number of people, \(D\) is days, \(H\) is hours per day, and \(W\) is work. This relation assumes equal efficiency per person and equal working conditions.
Pipes, leaks, and common traps
Treat an inlet as positive and an outlet or leak as negative. If an inlet fills a tank in 6 hours and a leak empties it in 10 hours, the net rate is:
\[ \frac{1}{6}-\frac{1}{10}=\frac{1}{15} \]
Therefore, the tank takes 15 hours to fill.
A partly filled tank requires the fraction still empty, not the entire tank. If a tank is \(3/5\) full, only \(2/5\) remains. The time is:
\[ \frac{\text{remaining fraction}}{\text{net rate}} \]
For pipes opened at different times, calculate each interval separately. If a leak begins later, do not subtract its rate before it opens.
| Situation | Correct model | Frequent error |
|---|---|---|
| Two workers together | Add their rates | Add their times |
| Inlet and outlet together | Subtract outlet rate | Subtract filling times |
| Worker leaves midway | Use separate intervals | Use the original group rate |
| Wages | Divide by work contribution | Divide only by attendance |
| Partly filled tank | Use the empty fraction | Use one full tank |
A CAT sanity-check routine
Check the direction before trusting the arithmetic:
- Adding a worker must reduce the completion time.
- Removing a worker must increase it.
- A leak must make filling slower than the inlet alone.
- A faster worker must complete more work in the same time.
- A result between two valid times is often reasonable for a combined rate.
- Convert fractional days or hours correctly. For example, \(7.2\) days means 7 days and \(0.2 \times 24 = 4.8\) hours.
Exercise
A pipe fills a tank in 8 hours. A leak empties it in 12 hours. If both remain open, how long does filling take?
Show answer
Net rate = 1/8 - 1/12 = 1/24 tank per hour, so the tank fills in 24 hours.