Sub topic 8
Men, Days and Hours: The M₁D₁H₁/W₁ = M₂D₂H₂/W₂ Relation
Assume you know fractions, ratios, direct and inverse proportion, and the basic rule:
\[ \text{Work}=\text{rate}\times\text{time} \]
In work problems, the total effort depends on the number of workers, the number of days, and the working hours per day. When all workers have the same efficiency,
\[ \frac{M1D1H1}{W1} = \frac{M2D2H2}{W2} \]
Here, \(M\) is the number of workers, \(D\) is the number of days, \(H\) is the number of hours worked per day, and \(W\) is the amount of work.
Understanding the relation
If one worker works one hour, that produces one worker-hour of effort. Therefore:
\[ \text{Total worker-hours}=M\times D\times H \]
For workers of equal efficiency, work is proportional to worker-hours:
\[ W\propto MDH \]
So, for two situations,
\[ \frac{M1D1H1}{W1} = \frac{M2D2H2}{W2} \]
When the work is the same, \(W1=W2\), and the relation becomes:
\[ M1D1H1=M2D2H2 \]
This means that increasing workers, days, or daily hours can compensate for a decrease in another factor.
Solving a same-work problem
Suppose 12 workers complete a project in 15 days by working 8 hours per day. How many workers are needed to complete the same project in 20 days by working 6 hours per day?
Since the work is unchanged:
\[ 12\times15\times8=M_2\times20\times6 \]
\[ 1440=120M_2 \]
\[ M_2=12 \]
The longer schedule has 20 days instead of 15, but each day has only 6 hours instead of 8. These changes exactly balance each other, so the required workforce remains 12.
When the amount of work changes
Suppose 8 workers complete 60 units of work in 10 days, working 6 hours per day. How many workers are needed for 90 units in 15 days, working 8 hours per day?
Use the full relation:
\[ \frac{8\times10\times6}{60} = \frac{M_2\times15\times8}{90} \]
The left side is:
\[ \frac{480}{60}=8 \]
Therefore:
\[ 8=\frac{120M_2}{90} \]
\[ M_2=6 \]
Although the second task is larger, it allows more days and longer working hours. Six workers are enough.
Adjusting for efficiency
The basic relation assumes equal worker efficiency. If workers differ, include efficiency \(E\):
\[ W\propto M\times D\times H\times E \]
For two groups:
\[ \frac{M1D1H1E1}{W1} = \frac{M2D2H2E2}{W2} \]
If worker A is twice as efficient as worker B, one worker A contributes as much as two workers B. Do not count them as equal workers.
| Quantity | Effect on time for fixed work |
|---|---|
| More workers | Time decreases |
| More hours per day | Time decreases |
| More work | Time increases |
| Higher efficiency | Time decreases |
Common errors and checks
- Use the same unit for time throughout. Convert weeks to days if other values are in days.
- Treat “hours per day” as a multiplier of the number of days.
- Check whether the work is the same or different before cancelling \(W\).
- Remember that workers, days, and hours are inversely related when work is fixed.
- If the new task is larger but has substantially more time and hours, a smaller workforce may still be reasonable.
For a quick check, compare worker-hours:
\[ \text{worker-hours}=M\times D\times H \]
For equal work, the worker-hour totals should match. For different work, their ratio should match the ratio of the work amounts.
from fractions import Fraction
# Situation 1: 8 workers, 10 days, 6 hours per day, 60 units
work_rate = Fraction(8 * 10 * 6, 60)
# Situation 2: unknown workers, 15 days, 8 hours per day, 90 units
workers = work_rate * 90 / (15 * 8)
print(workers) # 6Exercise
Twelve workers finish a job in 18 days by working 7 hours per day. How many workers are needed to finish the same job in 14 days by working 9 hours per day?
Show answer
Let the required number be M. Since the work is the same, 12 × 18 × 7 = M × 14 × 9. Thus M = 1512/126 = 12 workers.