Sub topic 8
Getting good O, M and P values from people
This chapter assumes you know basic scheduling terms such as task, duration, dependency, and critical path. You should also be comfortable with averages, squares, and square roots. The goal here is to improve the three inputs used by PERT:
- O, optimistic: the shortest reasonable duration when the work goes unusually well.
- M, most likely: the duration that best represents the usual outcome under stated conditions.
- P, pessimistic: a long but still credible duration when known difficulties occur.
These values are not guesses about absolute best and worst imaginable cases. An impossible disaster should not become P. A hidden assumption should not make O unrealistically small.
Start with a clear estimating question
People give different answers when they answer different questions. Before collecting an estimate, define:
- What work is included?
- What counts as complete?
- Which team or person is doing it?
- Are the required inputs available?
- Is the duration calendar time or working time?
- Are review, testing, rework, and waiting included?
- Which dependencies are already known?
For example, “How long will the report take?” is incomplete. A better question is:
> How many working days will it take one analyst to produce the reviewed report, assuming the data extract is available on day one and one reviewer is available within two days?
Record these assumptions with the estimate. Otherwise, later changes can look like estimation errors even when the work conditions changed.
Ask for O, M and P separately
Do not begin by asking for one number and then stretch it into three. That approach often produces a narrow range around an initial anchor. Ask about each case independently.
Elicit the most likely value
Ask the estimator to describe a normal completion:
- What usually happens?
- Which steps consume most of the time?
- How much rework is normal?
- How long do reviews or handoffs usually take?
M should represent the most common outcome, not a management target or an average of O and P. If the work has never been done, use comparable work as a reference. A previous task with similar complexity is more useful than a general statement such as “this should be quick.”
Elicit the optimistic value
Ask:
> If the work goes smoothly, what is the shortest duration that is still realistic?
The optimistic case might require:
- No defects in the input
- Immediate access to a needed person or system
- No review changes
- A familiar implementation
- No interruption to the assigned worker
O should not mean “if everything is perfect in the universe.” If the value assumes an event that has only a tiny chance of occurring, it is probably too optimistic.
Elicit the pessimistic value
Ask:
> What duration is still credible if the known difficulties occur?
Then identify those difficulties. P might include one rejected review, a normal access delay, or a moderate data-cleaning problem. It should not silently include every conceivable catastrophe unless the project is explicitly modeling those events.
The estimator should explain why P is longer than M. A large gap is useful information, but it needs a cause.
Use more than one estimator
Estimates from a single person can reflect optimism, fear, unfamiliarity, or pressure from a deadline. Ask people to estimate independently before discussing the results. Independent estimates reduce anchoring, which happens when an early number influences later answers.
After collecting the values, compare the reasons rather than simply averaging the numbers. If one person gives P = 12 days because approval may take a week and another gives P = 8 days because approval is already arranged, the disagreement describes different assumptions. Resolve the assumptions before combining the estimates.
A short review can use this sequence:
- Give everyone the same task definition and assumptions.
- Collect O, M, and P independently.
- Ask each person to explain the main driver of the range.
- Compare differences and identify changed assumptions.
- Agree on one set of values, or preserve distinct scenarios.
A facilitator can use anonymous estimates or a planning-poker-style reveal to prevent seniority from dominating the discussion.
Sanity-check the three values
Use these checks before calculating PERT.
| Check | Question | Possible correction |
|---|---|---|
| Ordering | Is O less than or equal to M, and is M less than or equal to P? | Revisit definitions or correct a transcription error. |
| Scope | Do all three values include the same work? | Add missing testing, review, or handoff time. |
| Units | Are all values in the same unit and calendar? | Convert hours, working days, or elapsed days consistently. |
| Range cause | What explains the difference between O and P? | Add, remove, or quantify the relevant risk. |
| Capacity | Can the named person actually work for the estimated time? | Include interruptions or use effective working time. |
The values should also match the task's scale. If a task normally takes two days, a P of 90 days may indicate an unmodeled dependency or a task that should be split. Splitting a task can make the uncertainty easier to explain, but do not split it merely to make the numbers look smaller.
Visualize the conversation
The estimating process is a loop. New information can change the task definition or the assumptions, so the first set of values is not automatically final.
Avoid common estimation traps
Target substitution occurs when M becomes the date someone wants instead of the duration the work is likely to require. Keep the target date separate from the estimate.
Padding without explanation occurs when someone adds an unexplained buffer. Ask what uncertainty the buffer covers. A named risk can be tracked and managed; unexplained padding cannot.
Double counting occurs when the same delay appears in several places. For example, a five-day vendor delay should not be included in both P for a configuration task and P for a later integration task if the schedule already models that dependency separately.
False precision occurs when people report 6.37 days even though the inputs are rough. Use units and precision that match the evidence. Whole working days may be more honest than decimal hours.
Unclear ownership occurs when an estimate includes waiting for another team but that team's work has no separate task. Decide whether the waiting time belongs in the task duration or in a dependency. Apply the choice consistently.
Example: turn discussion into usable inputs
Suppose a team is estimating a data-validation task. They agree that:
- O = 2 working days if the extract is clean and the reviewer is available immediately.
- M = 4 working days with normal corrections and one review cycle.
- P = 9 working days if the extract needs substantial cleaning and the reviewer is delayed.
The values are useful because each one has a condition. If the project later confirms that the reviewer will be unavailable for five days, the team should update the dependency or schedule rather than quietly changing M.
PERT uses these inputs to calculate a weighted expected duration:
\[ E = \frac{O + 4M + P}{6} \]
For these values, the expected duration is:
\[ E = \frac{2 + 4(4) + 9}{6} = 4.5\text{ working days} \]
The quality of 4.5 depends on the quality and consistency of the three inputs. PERT cannot correct a badly defined task or a range based on hidden assumptions.
def pert_expected_duration(optimistic, most_likely, pessimistic):
if not (optimistic <= most_likely <= pessimistic):
raise ValueError("Expected O <= M <= P")
return (optimistic + 4 * most_likely + pessimistic) / 6
o, m, p = 2, 4, 9
expected = pert_expected_duration(o, m, p)
print(f"PERT expected duration: {expected:.1f} working days")Exercise
An estimator gives O = 3 days, M = 5 days, and P = 20 days. They explain that P includes a possible six-month regulatory failure that is outside the project's modeled scope. What should you do before using these values?
Show answer
Clarify the scope and the risk treatment. Remove the six-month failure from P if it is outside the agreed model, or model it explicitly as a separate risk or scenario. Then re-estimate P so it represents a long but credible outcome for the defined task.