Assumptions and Limitations: Independence, Critical Path Shifts, Bias
PERT gives a useful probability estimate, but it is a model, not a guarantee. This chapter assumes that you know basic scheduling terms such as task, duration, dependency, and critical path. It also assumes that you can calculate averages, squares, square roots, and understand that a standard deviation measures spread.
A PERT estimate uses three values for each task:
- Optimistic duration, O: a realistic best case when conditions are favorable.
- Most likely duration, M: the duration expected under normal conditions.
- Pessimistic duration, P: a realistic difficult case, excluding extreme disasters.
For one task, the PERT expected duration is:
(O + 4M + P) / 6
The PERT standard deviation is:
(P - O) / 6
The method becomes less reliable when the assumptions behind these calculations do not match the project.
Independence is an assumption, not a fact
When combining tasks on one path, the usual PERT method adds their expected durations:
path mean = mean1 + mean2 + mean3 + ...
It also adds their variances:
path variance = variance1 + variance2 + variance3 + ...
Adding variances assumes that task durations are independent. Two tasks are independent when knowing that one task took longer does not change your estimate for the other task.
For example, suppose a design task and a testing task use different people, tools, and inputs. A delay in design may have little effect on testing. Their durations might be approximately independent.
However, tasks often share causes of delay:
- Both depend on the same unavailable specialist.
- Both require an external supplier.
- Both are affected by the same approval process.
- Both become slower when the requirements are unclear.
- A delay in one task creates extra work for another.
These tasks are correlated. If one takes longer, the other is more likely to take longer too. Adding their variances as if they were independent understates the total uncertainty.
In probability terms, the variance of a sum includes covariance terms when tasks are related. Positive correlation increases the total spread. Negative correlation can reduce it, although negative correlation is less common in project work.
Critical paths can change
A critical path is the sequence of dependent tasks that controls the earliest possible project finish. A deterministic schedule often shows one critical path. In an uncertain schedule, several paths may be close in duration.
The path with the largest expected duration is not always the path that finishes last in a particular outcome. A normally shorter path can receive several delays and become the longest path. This is called a critical path shift.
A calculation based only on the current critical path may miss this behavior. For example, you might calculate an 85% completion date for Path A, while Path B has enough uncertainty to overtake it in many scenarios. The project-level probability is then lower than the path-level probability suggests.
This problem is especially important when:
- Several paths have similar expected durations.
- Parallel work contains different levels of uncertainty.
- A path has a small mean but a large standard deviation.
- Dependencies or resource limits can make paths interact.
A full project analysis should consider all relevant paths and shared constraints. Monte Carlo simulation is often better than a single-path normal approximation because it can sample every task and identify which path finishes last in each trial.
Estimates can contain systematic bias
PERT formulas cannot correct poor inputs. If the optimistic, most likely, and pessimistic values are biased, the result will also be biased.
Common sources of bias include:
- Optimism bias: people expect their work to proceed without interruptions.
- Planning fallacy: people focus on the work itself and omit meetings, reviews, rework, and waiting.
- Anchoring: a previous estimate influences all three values even when the new task differs.
- Pressure bias: a person gives a short estimate because a sponsor expects an aggressive date.
- Availability bias: a recent failure makes a person overestimate similar risks.
- Scope ambiguity: different people estimate different interpretations of the task.
- Defensive estimation: a person makes P extremely large to protect against blame.
A good pessimistic value is not an impossible catastrophe. It should describe a difficult but credible outcome. If the project needs a separate contingency reserve for rare disasters, keep that reserve visible rather than hiding it in P.
How to improve the inputs
Use a consistent estimation process:
- Define what “finished” means for the task.
- Ask for O, M, and P separately.
- Ask what conditions make each value plausible.
- Include normal waiting, review, rework, and handoffs.
- Compare the estimates with historical results from similar work.
- Record assumptions, dependencies, and known risks.
- Re-estimate when scope, resources, or dependencies change.
Ask for evidence instead of accepting unexplained precision. A person who says that a task will take exactly 6.25 days may be expressing false precision. The useful question is what would make the task take 4 days, 6 days, or 10 days.
| Problem | Effect on the PERT result | Useful response |
|---|---|---|
| Shared supplier risk | Uncertainty is understated | Model the shared risk or use correlated scenarios |
| Two paths have similar means | The selected critical path may change | Analyze both paths |
| P is an impossible disaster | Spread is exaggerated | Use a credible difficult case and track contingency separately |
| Reviews and rework are omitted | Mean duration is too short | Include them in the task definition |
| Estimates are given under deadline pressure | All values may be too optimistic | Use historical data and independent review |
When PERT is a poor fit
PERT works best when a task has a meaningful lower and upper range and its duration is uncertain but bounded. It is less suitable when:
- The task has no clear definition of done.
- The pessimistic outcome is open-ended.
- The project contains strong dependencies between tasks.
- Resources are shared in ways the schedule does not model.
- Work is exploratory and the range changes as learning occurs.
- The three estimates are guesses with no supporting assumptions.
In these situations, separate the work into smaller tasks, model explicit risks, or use simulation. Treat the output as decision support rather than a promise.
Exercise
A project has two parallel paths. Path A has an expected duration of 12 days with a standard deviation of 1 day. Path B has an expected duration of 10 days with a standard deviation of 4 days. Why might a calculation based only on Path A be misleading?
Show answer
Path B has a shorter mean but much greater uncertainty. In some outcomes, delays could make Path B longer than Path A, so the critical path can shift and the project-level completion probability may be lower than Path A's probability.