01Chapter 1: Why a single number is not enoughProject schedules often begin with a question such as, “How long will this task take?” A common answer is a single number: five days, three weeks, or two hours.4 min read
03Chapter 3: Triangular estimate: the simple averageThis chapter assumes you know the meaning of a task, duration, dependency, and critical path. You should also be comfortable with averages and basic arithmetic. A triangular estimate is a way to describe one task with three duration estimates instead of one.4 min read
04Chapter 4: PERT expected duration: (O + 4M + P) / 6This chapter assumes you know basic scheduling terms such as task, duration, dependency, and critical path. You should also be comfortable with averages and basic arithmetic. The goal is to calculate a task’s PERT expected duration from three estimates:4 min read
05Chapter 5: Measuring spread: standard deviation (P - O) / 6 and varianceThis chapter assumes you know basic scheduling terms such as task, duration, dependency, and critical path. It also assumes you can calculate averages, squares, and square roots. The previous chapter introduced three-point estimates:4 min read
06Chapter 6: Combining tasks on a path: sum the means, sum the variancesAt the intermediate level, this chapter assumes you know basic scheduling terms such as task, duration, dependency, and critical path. You should also be comfortable with averages, squares, square roots, and the basic idea of a probability distribution.3 min read
07Chapter 7: Reading a confidence level from the mean and standard deviationThis chapter assumes you know the basic terms task, duration, dependency, and critical path. You should also be comfortable with averages, squares, square roots, and the general meaning of a probability distribution.4 min read
08Chapter 8: Getting good O, M and P values from peopleThis chapter assumes you know basic scheduling terms such as task, duration, dependency, and critical path. You should also be comfortable with averages, squares, and square roots. The goal here is to improve the three inputs used by PERT:5 min read
09Chapter 9: Assumptions and limitations: independence, critical path shifts, biasPERT gives a useful probability estimate, but it is a model, not a guarantee. This chapter assumes that you know basic scheduling terms such as task, duration, dependency, and critical path. It also assumes that you can calculate averages, squares, square roots, and understand that a standard deviat5 min read
10Chapter 10: Going further: Monte Carlo simulationThis chapter assumes you know tasks, dependencies, critical paths, three-point estimates, averages, variances, and standard deviation. It also assumes basic Python. The earlier PERT method summarizes uncertainty with one mean and one standard deviation. Monte Carlo simulation keeps more of the shape4 min read