Sub topic 8
Getting good O, M and P values from people
This chapter assumes you can already compute a PERT expected duration, (O + 4M + P) / 6, and a standard deviation, (P - O) / 6. It also assumes you know the basic scheduling vocabulary of task, duration and path. The formulas are only as good as the three numbers fed into them. This chapter covers how to collect those numbers from the people doing the work and how to sanity-check them before they enter a schedule.
Why elicitation is the weak point
The arithmetic in PERT is exact. The inputs are opinions. If a developer says a task takes 4, 6 or 14 days, the method treats those numbers as facts about the task's probability distribution. Three problems recur:
- People give a most likely value that is really their best case.
- People give ranges that are too narrow, because they cannot easily imagine what would go wrong.
- People give padded values when they expect the estimate to become a commitment.
Each problem changes the output in a predictable direction. Narrow ranges understate the standard deviation, and the confidence levels you read from it become falsely tight. Padding inflates the mean and hides the real uncertainty. Elicitation is therefore a measurement problem, and you treat it as one: define what you are measuring, reduce bias in the instrument, and check the results against reality.
Define O, M and P before you ask
The first source of bad data is that "optimistic" and "pessimistic" mean different things to different people. One person hears "optimistic" as "everything goes perfectly". Another hears it as "a good week". Agree on written definitions and use them for every estimate.
| Value | Working definition | What it excludes |
|---|---|---|
| O (optimistic) | A duration you would beat only about 1 time in 20 or 1 in 100. Things go unusually well, with no rework and no waiting. | Impossible outcomes, such as the work already existing or the requirement vanishing. |
| M (most likely) | The single duration you would bet on, the peak of the distribution. Normal friction is included. | The average. In a right-skewed task M is smaller than the mean. |
| P (pessimistic) | A duration you would exceed only about 1 time in 20 or 1 in 100. Realistic bad luck, such as a failed first attempt, a late dependency or a sick teammate. | Catastrophes outside the task, such as the team being disbanded or the vendor going bankrupt. |
PERT's formulas treat O and P as the practical extremes of the distribution. Many teams use "1 in 20" (roughly the 5th and 95th percentiles) because people can imagine it. Whichever tail probability you choose, apply it consistently. Mixing definitions across tasks makes the variances incomparable, and you add variances along a path.
Also fix the unit once. Decide whether durations are working days of effort or elapsed calendar days, and whether they assume one person full time. A task estimated as "6 days" of effort that the assigned person can only work on half time takes 12 elapsed days. Write the resourcing assumption beside the three numbers.
Ask in a good order
The order of the questions changes the answers. If you ask for the most likely value first, the estimator anchors on it, and the optimistic and pessimistic values then sit too close to it. Asking for the extremes first pushes people to think about the range before they pick a center.
A sequence that works in practice:
- Describe the task's scope and the assumptions in writing, including who will do it and what must already be done.
- Ask for P first: "What is a realistic bad outcome that would happen about once in twenty times? What would cause it?"
- Ask for O next: "What is the fastest this could go if the main risks do not appear?"
- Ask for M last: "Between those, which duration would you bet on?"
- Record the reasons behind P. Each pessimistic value should name a cause.
Asking for the cause of P matters because a pessimistic number with no story attached is usually a feeling or padding. A story such as "the vendor API might not support batch export, and then we write our own" can be checked later and may turn into a risk entry.
Sanity-check each triple
Before a triple goes into the schedule, run simple checks. Most are mechanical and can be automated.
- Order: O ≤ M ≤ P, and all three are positive. A violation is almost always a typo or a misunderstanding.
- M equal to O: The estimator is describing the best case as the most likely case. This is the classic optimism pattern.
- M equal to P: The estimator is padding, or has already folded a safety margin into M.
- Very narrow range: If (P - O) is a small fraction of M, the estimator is probably overconfident. Few real tasks have a range of 10% of their typical duration.
- Very wide range: If (P - O) is several times M, the task is poorly understood or too large. Split it or run a short investigation, then re-estimate.
- Skew that matches the story: Software and construction tasks usually have a pessimistic side much farther from M than the optimistic side. If P - M is smaller than M - O, ask what the estimator thinks could make the task faster than most likely, because that is unusual.
This function implements the checks. It returns a list of warnings, so an empty list means the triple passed.
def check_triple(o, m, p):
issues = []
if not (0 < o <= m <= p):
return ["need 0 < O <= M <= P"]
spread = (p - o) / m
if spread < 0.25:
issues.append(f"range is only {spread:.0%} of M; likely overconfident")
if spread > 3:
issues.append("range is more than 3x M: consider splitting the task")
if m == o:
issues.append("M equals O: ask what the most likely case assumes")
if m == p:
issues.append("M equals P: check for padding already included")
return issues
for triple in [(4, 6, 14), (5, 5, 6), (2, 3, 20)]:
print(triple, check_triple(*triple))The output is:
(4, 6, 14) []
(5, 5, 6) ['range is only 20% of M; likely overconfident', 'M equals O: ask what the most likely case assumes']
(2, 3, 20) ['range is more than 3x M: consider splitting the task']The thresholds 0.25 and 3 are starting points. Tune them against your own history, as described below. A warning is a prompt for a conversation and not a rejection, because some tasks really are well understood and narrow.
Why the range width matters so much
The standard deviation is (P - O) / 6, so it depends only on the range. An estimator who shrinks P by a few days changes the spread of the whole path. Compare three estimators describing the same task:
| Estimator | O | M | P | PERT mean | Standard deviation |
|---|---|---|---|---|---|
| Overconfident | 5 | 6 | 8 | 6.17 | 0.50 |
| Realistic | 5 | 6 | 14 | 7.17 | 1.50 |
| Padded | 5 | 6 | 20 | 8.17 | 2.50 |
All three give the same M. The overconfident estimator reports a spread three times narrower than the realistic one, and the path-level standard deviation scales with it. Later, when you read an 85% confidence duration from a path, the number would be too close to the mean, and you would promise a date that the team meets far less than 85% of the time. The padded estimator has the opposite effect: the mean drifts up and the 85% date becomes needlessly distant.
The mean moves less than the spread does. PERT weights M by four, so a change in P of 6 days moves the mean by 1 day but moves the standard deviation by 1 day as well. Because variance adds along a path, errors in spread matter more than they appear in a single task.
Common biases and how to counter them
| Bias | What you see | Countermeasure |
|---|---|---|
| Planning fallacy | M equals O. The estimate imagines the plan going well and ignores similar past tasks. | Ask for a similar completed task and its actual duration. Estimate from that reference class first. |
| Anchoring | Estimates cluster around a number someone said aloud, such as a deadline or a manager's guess. | Collect estimates individually and in writing before any discussion. Do not state a target. |
| Overconfidence | Ranges are too narrow. Actuals fall outside [O, P] often. | Ask for P first, ask for causes, and calibrate against history. |
| Padding (Parkinson's and safety margins) | M equals P, or every task is rounded up. | Separate the estimate from the commitment. State that buffer is managed at the project level, not hidden inside tasks. |
| Sandbagging under pressure | P is inflated because the estimator expects to be held to it. | Make clear that P is a one-in-twenty case and that missing M is expected half the time. |
| Group conformity | The most senior or loudest person's numbers become everyone's. | Use independent estimates followed by discussion of differences. |
Padding deserves special attention. Teams that pad every task and then also add a project buffer pay for the margin twice. If your organization adds contingency at the project level, tell estimators so. They can then give honest numbers without defending themselves.
Use more than one person
For significant tasks, collect triples from several people and compare them. A structured version is Wideband Delphi:
- Each estimator writes O, M and P privately, with the assumptions behind them.
- The facilitator shows all triples anonymously.
- The group discusses the largest disagreements. Differences usually reveal a hidden assumption, such as one person planning for a security review and another not.
- Estimators revise privately and the round repeats once or twice.
- Combine the final triples, for example by taking the median of each of O, M and P.
The conversation matters more than the combination rule. If one estimator's P is double everyone else's, find out what that person knows. They may know about a flaky test environment, or they may be misreading the scope. Either result improves the estimate.
Prefer estimates from the people who will do the work. A manager's triple for a task the manager will not perform tends to be more optimistic and narrower than the doer's. If the doer is unknown at estimation time, use someone with similar experience and note the assumption.
Calibrate against history
The most reliable correction is data. After each task finishes, record the actual duration next to the triple. Over a few dozen tasks you can ask a direct question: if O and P are meant to bracket about 90% of outcomes, do they?
history = [
# (O, P, actual) in days for completed tasks
(3, 10, 12), (2, 6, 5), (4, 9, 11), (5, 12, 9), (1, 4, 6),
(3, 8, 7), (2, 5, 8), (6, 14, 13), (2, 7, 9), (4, 10, 15),
]
hits = sum(o <= a <= p for o, p, a in history)
over = sum(a > p for o, p, a in history)
under = sum(a < o for o, p, a in history)
print(f"inside range: {hits / len(history):.0%}, above P: {over}, below O: {under}")The output is:
inside range: 40%, above P: 6, below O: 0If these ranges were intended to cover roughly 90% of outcomes, a 40% hit rate shows they are far too narrow. The misses are all on the high side, which is the typical pattern: optimism more than random error. This team's actuals never beat O but often exceed P.
What you do with the result depends on how much data you have:
- Few tasks (under about 20): Treat the result as a conversation starter. Show it to the team and ask them to widen P in the next round, especially for the task types that missed.
- Many tasks: Fit a correction. For example, compute the ratio of actual to M for each past task and use a high quantile of those ratios as a guide for the typical P/M relationship in your environment. Keep corrections by task type, because a database migration and a UI tweak have different distributions.
- Always: Keep the definitions of O and P stable while you collect data. Changing them mid-stream makes the history incomparable.
Feedback also changes behavior. Teams that see their own hit rate usually widen their ranges within a few iterations, without being told to.
Handling tasks nobody can estimate
Sometimes the three values cannot be given with any honesty. Common causes and responses:
- Unknown scope: Spend a short, time-boxed spike to learn enough to estimate. Record the spike as its own task with its own triple.
- First-time technology: Widen the range openly and add the unknown to the risk register. Do not hide uncertainty by choosing a narrow triple.
- Dependencies on other teams: Estimate your effort separately from the waiting time, and give the waiting time its own pessimistic value, because waits are often the long tail.
- Very large tasks: If the task exceeds a few weeks, decompose it. Estimating several small tasks and summing variances usually yields a better aggregate than one large guess, as long as the pieces are reasonably independent. The next chapter covers when that independence assumption fails.
A worked elicitation
You are planning "Migrate the reporting database". You meet with the engineer who will do the work.
- You write down the scope: move 40 tables to the new engine, keep the nightly report job working. Assumption: one engineer, full time, working days, staging environment available.
- You ask for P: "A one-in-twenty bad case?" She says 18 days. You ask what causes it. She explains that two tables use a data type with no direct equivalent and the report job may need rewriting.
- You ask for O: "If the type issue does not appear?" She says 7 days.
- You ask for M: "What would you bet on?" She says 10 days.
- You run the checks. The order is fine and the spread is (18 - 7) / 10 = 110% of M, so there are no warnings.
- PERT gives (7 + 40 + 18) / 6 = 10.83 days with a standard deviation of 11 / 6 = 1.83 days.
- You record the triple, the cause for P and the resourcing assumption. After the migration, you compare the actual duration and update the team's calibration history.
The record of the cause for P also gives you something to watch. If the data-type problem appears early, you know the task is heading toward the pessimistic side and can warn the project manager before the schedule slips.
Summary of practices
- Write definitions for O, M and P, and fix the unit and the resourcing assumption.
- Ask for P and its cause first, then O, then M.
- Collect estimates independently, then discuss differences.
- Run mechanical checks on order, spread and equal values.
- Keep the estimate separate from the commitment, and manage buffer at the project level.
- Record actuals and compute the hit rate of [O, P] to calibrate.
Exercise
A team's last 10 completed tasks show that only 4 actuals fell inside their [O, P] ranges, and all 6 misses were above P. The team defines O and P as roughly the 5th and 95th percentiles. What does this tell you, and what two changes would you make to the next elicitation round?
Show answer
A 40% hit rate against an intended 90% means the ranges are far too narrow, and the misses all lie above P, so the main problem is optimism in P (and likely in M). Two changes: ask for P before O and M, with a written cause for each P, so estimators imagine concrete bad cases; and show the team their hit rate and use a reference-class check, such as comparing against the actual duration of a similar past task, before accepting the triple. Keep the O/P definitions fixed so the next batch of actuals is comparable.
Exercise
Two estimators give triples for the same task. Estimator A gives (5, 6, 8). Estimator B gives (5, 6, 14). Compute the PERT mean and standard deviation for each, and say which triple you would question first and what you would ask.
Show answer
A: mean (5 + 24 + 8) / 6 = 6.17, standard deviation (8 - 5) / 6 = 0.50. B: mean (5 + 24 + 14) / 6 = 7.17, standard deviation (14 - 5) / 6 = 1.50. Question A's triple first, because its range is only 3 days on a 6-day task (50% of M) and its P is just 2 days above M, which is typical of overconfidence. Ask what could cause a one-in-twenty bad outcome, and what the estimator saw on similar past tasks. If A cannot name a cause, compare with B's reasoning and run a short discussion on the difference.
Exercise
An estimator submits (10, 10, 10) for a task. Which checks does the triple fail, what does it imply for the path's variance, and what should you do?
Show answer
It passes the order check (O ≤ M ≤ P) but fails the narrow-range check (spread is 0) and the M-equals-O and M-equals-P checks. The standard deviation is (10 - 10) / 6 = 0, so the task adds no variance to the path and makes the path's confidence levels look tighter than they are. Do not accept it. Ask what could make the task longer or shorter, apply the P-first order, and have the estimator name causes. If the task truly has no uncertainty, such as a fixed-length vendor lead time, record that reason explicitly.