01Chapter 1: Why a single number is not enoughA schedule built from single-number duration estimates looks precise, but the precision is not real. This chapter shows what a single number hides and measures the effect with small, checkable calculations. The following chapters replace the single number with three values and turn them into an expe8 min read
02Chapter 2: The three inputs: optimistic, most likely, pessimisticThis chapter assumes you know basic scheduling vocabulary (task, duration, dependency, critical path) and have a rough idea of what a probability distribution is. It covers the three numbers every three-point or PERT estimate starts from. It defines them precisely, shows the rules a valid set of thr8 min read
03Chapter 3: Triangular estimate: the simple averageThis chapter covers the triangular estimate, the simplest way to turn three duration values into one number. It assumes you know the schedule vocabulary of task, duration, dependency and critical path. It also assumes you can compute averages, squares and square roots, and that you have a rough idea10 min read
04Chapter 4: PERT expected duration: (O + 4M + P) / 6This chapter assumes you know basic scheduling vocabulary (task, duration, dependency, critical path) and what an average is. It also assumes you have a rough idea of what a probability distribution is. You do not need to know the beta distribution. The chapter explains the one fact about it that yo10 min read
05Chapter 5: Measuring spread: standard deviation (P - O) / 6 and varianceThis chapter assumes you can compute the PERT expected duration (O + 4M + P) / 6 for a task. It also assumes you know that a standard deviation is a typical distance of outcomes from the average, and that you can square numbers and take square roots. Combining tasks along a path and reading confiden8 min read
06Chapter 6: Combining tasks on a path: sum the means, sum the variancesThis chapter assumes you can compute a PERT expected duration and a standard deviation for one task. It also assumes you know what a dependency chain and a critical path are, and that you are comfortable with squares and square roots. Here you will combine several task estimates into one estimate fo9 min read
07Chapter 7: Reading a confidence level from the mean and standard deviationThis chapter turns a path's expected duration and standard deviation into a statement such as "there is an 85% chance this path finishes within 14.4 days." It assumes you can compute PERT task estimates and combine them along a path by summing means and variances. It also assumes a rough idea of wha7 min read
08Chapter 8: Getting good O, M and P values from peopleThis chapter assumes you can already compute a PERT expected duration, (O + 4M + P) / 6, and a standard deviation, (P - O) / 6. It also assumes you know the basic scheduling vocabulary of task, duration and path. The formulas are only as good as the three numbers fed into them. This chapter covers h11 min read
09Chapter 9: Assumptions and limitations: independence, critical path shifts, biasPERT gives you a mean, a standard deviation and a confidence level from three numbers per task. Those outputs are only as good as the assumptions underneath them. This chapter lists the assumptions, shows what happens when each one fails, and gives checks you can run before you trust a PERT result.10 min read
10Chapter 10: Going further: Monte Carlo simulationThis chapter assumes you can compute a PERT mean and standard deviation for a task and sum them along a path. It also assumes you know how a normal-approximation confidence level is read. You should be comfortable reading short Python programs. Earlier chapters covered all of this.10 min read