Sub topic 9
Assumptions and limitations: independence, critical path shifts, bias
PERT gives you a mean, a standard deviation and a confidence level from three numbers per task. Those outputs are only as good as the assumptions underneath them. This chapter lists the assumptions, shows what happens when each one fails, and gives checks you can run before you trust a PERT result.
It assumes you can already compute a PERT expected duration (O + 4M + P) / 6 and standard deviation (P - O) / 6. It also assumes you can sum means and variances along a path and read a confidence level from a normal distribution. It uses the terms critical path, float and dependency without redefining them.
What the method assumes
The PERT result for a project rests on five assumptions. Each one is a place where real projects can differ from the model.
| Assumption | Where it enters | What breaks if it is false |
|---|---|---|
| The `(P - O) / 6` rule describes the real spread | Task standard deviation | The spread is understated or overstated, so every confidence level is off |
| Task durations are independent | Summing variances on a path | The path's spread is understated |
| The path total is roughly normal | Reading a confidence level | Percentiles are wrong, especially on short or skewed paths |
| The critical path stays the critical path | Using one path for the whole project | The project finishes later than the single-path result suggests |
| O, M and P are honest, calibrated estimates | All formulas | Precise-looking numbers carry no real information |
The rest of the chapter takes these in turn.
The spread rule is a convention
The formula (P - O) / 6 comes from treating the range from O to P as six standard deviations wide, which is roughly the full range of a normal curve. It is a convention, not a measurement. It works when O and P are true extremes, meaning values you would be surprised to see exceeded or undercut.
People rarely give true extremes. Asked for a pessimistic value, most give something like a bad-but-plausible case, often near the 90th or 95th percentile. If O and P are really the 10th and 90th percentiles, the range covers only about 2.56 standard deviations (plus or minus 1.28). The standard deviation is then about (P - O) / 2.56, which is more than twice what the PERT rule reports.
The mean formula has a similar limit. The weight of 4 on M approximates a beta distribution whose mean sits between M and the midpoint of the range. It is a good fit for moderately skewed tasks. For a task with an extreme tail (M = 2, P = 60, say), the weighted mean can still hide a risk that a single number cannot represent.
Independence
The path rule "sum the variances" holds only if task durations are independent. Independent means that learning one task ran long tells you nothing about whether the next one will. In practice, tasks often share causes of delay:
- The same person or team does several tasks, and that person is slow or unavailable.
- The tasks depend on the same vendor, environment or approval body.
- The same underlying uncertainty (a new technology, an unclear requirement) affects all of them.
- A management or culture effect, such as a hiring freeze or a re-org, hits every task at once.
When durations are positively correlated, overruns arrive together. The variance of a sum of two tasks is σ1² + σ2² + 2ρσ1σ2, where ρ is the correlation between them. The sum-of-variances rule is the special case ρ = 0.
from math import sqrt
def path_sd(s1, s2, rho):
"""Standard deviation of two task durations that are correlated by rho."""
return sqrt(s1 ** 2 + s2 ** 2 + 2 * rho * s1 * s2)
for rho in (0, 0.5, 1.0):
print(rho, round(path_sd(2, 3, rho), 2))
# 0 3.61
# 0.5 4.36
# 1.0 5.0With the same two tasks, the path's standard deviation grows from 3.61 days to 5.0 days as correlation rises from 0 to 1. The expected duration does not change at all. Only the spread grows, and with it the gap between the 50% and the 85% duration.
The effect gets stronger as the path gets longer. With many correlated tasks, the errors do not average out as the independence rule predicts. A path of twenty tasks that all depend on one overloaded team behaves more like one large task than like twenty small ones.
What to do about it
You rarely know ρ, so the practical responses are structural:
- Group tasks that share a cause of delay, and estimate that cause as its own risk, outside the individual tasks.
- Treat the computed standard deviation as a lower bound when tasks share people, vendors or technology.
- Test sensitivity: recompute with a plausible ρ (0.3 to 0.5) and see how much the 85% date moves.
Critical path shifts
PERT is usually applied to the critical path, the path with the longest expected duration. That is correct for the mean. It does not follow that the critical path alone tells you the project's chance of finishing on time, for two reasons.
Near-critical paths compete
The project finishes when the last path finishes. If two paths have similar means, each has its own chance of running late, and the project is late if either does. For independent paths, the probability that the project meets a date is the product of the probabilities that each path does.
The diagram shows the situation. Two parallel chains of tasks merge at the end.
The next listing uses path A from the earlier chapters (mean 12.33, standard deviation 1.97) and a second, independent path B (mean 12.0, standard deviation 2.05). It also adds a third path C with a lower mean but a larger spread.
from statistics import NormalDist
path_a = NormalDist(12.33, 1.97)
path_b = NormalDist(12.0, 2.05)
path_c = NormalDist(11.0, 4.0)
# Merge effect: A is the critical path, so plan to its mean.
target = 12.33
p_a = path_a.cdf(target)
p_b = path_b.cdf(target)
print(round(p_a, 2), round(p_b, 2), round(p_a * p_b, 2))
# 0.5 0.56 0.28
# Risk ranking: which path is more likely to exceed 14 days?
print(round(1 - path_a.cdf(14), 2), round(1 - path_c.cdf(14), 2))
# 0.2 0.23The first result is the merge effect. Path A alone has a 50% chance of finishing by day 12.33. Once path B is included, the chance that both finish by then falls to about 28%. The critical-path analysis says "12.33 is the 50% date". The project as a whole is far less likely than 50% to meet it.
The second result shows a shift in which path matters. Path C has a lower mean (11.0 against 12.33), so it is never on the critical path by expected duration. But its wide spread gives it a 23% chance of exceeding 14 days, against 20% for path A. For a deadline of 14 days, C is the riskier path.
Paths change during execution
The critical path is calculated from expected values at planning time. Once work starts, durations come in as actuals, and a path with float can lose it. A change in scope or a delayed dependency can also reroute the longest path. A PERT figure computed once at kickoff describes the project at kickoff.
Two habits reduce the damage:
- List near-critical paths as well as the critical one. A common rule is any path within about one standard deviation of the critical path's mean.
- Recompute at each status date. Replace finished tasks with their actuals (variance zero) and re-estimate the remaining ones.
Bias in the estimates
PERT turns three numbers into a distribution. If the three numbers are systematically wrong, the output is precisely wrong. Three biases are common.
- Optimism bias or the planning fallacy. People base estimates on the best case for the plan in front of them, not on how similar work has gone before. Optimistic estimates push O, M and P all too low, and often compress the range.
- Anchoring. The first number mentioned, such as a sponsor's wish or last quarter's figure, pulls the estimates toward it. The range often ends up centered on the anchor instead of on the evidence.
- Padding and gaming. If people know estimates become commitments, they pad P. If they know estimates get cut, they inflate everything. The numbers then describe negotiating positions, not likely durations.
A narrow range is a warning sign of its own. If a team's O and P are close together on uncertain work, the resulting standard deviation is small, and the confidence levels look reassuring for no good reason.
Check estimates against history
You can test calibration with data from finished tasks. For each, record O, M, P and the actual duration. Two quantities are useful:
- The hit rate: how often the actual fell between O and P. If O and P are meant to be near-extremes, the hit rate should be high, around 90% or more.
- The bias ratio: total actual duration divided by total PERT expected duration. A ratio near 1.0 means the expected values are unbiased on average. A ratio of 1.3 means work took 30% longer than the model predicted.
history = [
# (optimistic, most likely, pessimistic, actual) in days
(3, 5, 9, 10),
(2, 4, 6, 5),
(4, 6, 10, 12),
(1, 2, 4, 2),
(5, 8, 12, 13),
]
hits = sum(1 for o, m, p, actual in history if o <= actual <= p)
total_expected = sum((o + 4 * m + p) / 6 for o, m, p, _ in history)
total_actual = sum(actual for *_, actual in history)
print(hits / len(history), round(total_actual / total_expected, 2))
# 0.4 1.62Here only 40% of actuals fell inside the O to P range, and the work took 62% longer than the PERT means predicted. Both numbers say the same thing: this team's ranges are too narrow and too low. Five tasks is a tiny sample, so treat these figures as a prompt to collect more history, not as a calibration factor to apply.
If you have enough history, you can use the bias ratio as a correction, scaling expected durations and widening ranges. Do this with data from the same kind of work by the same kind of team, and review it periodically. A correction taken from unrelated projects only trades one bias for another.
Other limitations
Some problems are outside what any three-point formula can address.
- Discrete risks. A task's range describes ordinary variation. A one-in-five chance that a supplier fails, a regulator rejects the design or a key person leaves is an event, not a spread. Modeling it as a stretched P blurs it. Track such risks separately, with their own probability and impact.
- Resource constraints. PERT assumes tasks start as soon as their predecessors finish. If tasks compete for the same people, their start dates depend on resource availability, and the path logic no longer describes the real schedule.
- Normal approximation on short paths. The central limit theorem makes sums of many independent tasks roughly normal. On a path with two or three tasks, one of them heavily skewed, the normal curve can put probability on durations below the sum of the O values or above the sum of the P values. Neither can happen under the model's own inputs. Check that your 85% or 95% result lies inside the range from the summed O values to the summed P values.
- Behavioral effects. Work often expands to fill the time allowed and starts late when a deadline seems far away. A task's duration can depend on the date it was given. PERT treats duration as a property of the task alone.
- False precision. A result such as "14.38 days at 85%" has two decimal places that the inputs cannot support. Report dates rounded to the precision of the data, and say what the confidence level is conditional on.
A practical checklist
Run this before presenting a PERT-based date:
- State what O and P mean (true extremes or percentiles) and use the matching divisor.
- Check the ranges against history if you have it: hit rate and bias ratio.
- Identify tasks that share people, vendors or technology, and test the result with correlated spread.
- List near-critical paths and estimate the chance that any path exceeds the target date.
- Remove discrete risk events from the ranges and track them separately.
- Confirm the result lies between the summed O values and the summed P values.
- Plan to recompute at each status date.
If a path has many tasks, no shared causes and calibrated ranges, the basic method is reasonable. If the checklist raises problems you cannot fix by adjusting inputs, a Monte Carlo simulation, covered in the next chapter, can represent parallel paths, correlation and discrete risks directly.
Exercise
Two independent paths merge at a milestone. Each path has exactly a 50% chance of finishing by the planned date. What is the chance the milestone is met on that date, and what does this tell you about planning to the critical path's mean?
Show answer
The chance is 0.5 × 0.5 = 25%. The milestone needs both paths to finish on time, so its probability is the product of the two. Planning to the mean of one critical path overstates the likelihood of meeting the date. The more near-critical paths merge, the larger the effect.
Exercise
A team gives O = 4 and P = 14 days for a task, and tells you these are the 10th and 90th percentiles of their belief. Using 2.56 standard deviations between the 10th and 90th percentiles, estimate the standard deviation, and compare it with the PERT rule (P - O) / 6.
Show answer
The estimate is (14 - 4) / 2.56 ≈ 3.9 days. The PERT rule gives (14 - 4) / 6 ≈ 1.67 days. The PERT rule understates the spread by a factor of about 2.3 for these inputs, so confidence levels computed from it would be too optimistic.
Exercise
A project has three tasks on one path with standard deviations of 2, 2 and 3 days. All three are done by one overloaded team, so you suspect the durations are positively correlated. Does the independence calculation give a standard deviation that is too high or too low, and does the expected duration change?
Show answer
The independence calculation gives sqrt(4 + 4 + 9) = sqrt(17) ≈ 4.12 days. With positive correlation, the true standard deviation is higher, so 4.12 is too low. The expected duration does not change, because correlation affects only the spread of the sum, not its mean.